LIC-SR 16/SR 79-VAR
LIC County · est $2.5M
Bid dateThursday, May 11—
LIC County · est $2.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 95 more items below.
| Item | Quantity | R1Bcc Ohio INC | R2Complete General Construction Company | % of bid |
|---|---|---|---|---|
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $426,233 | $700,000 | 30% |
| 624E10000 MOBILIZATION | 1 LS | $128,181 | $100,000 | 9% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: WITH EARLY STRENGTH PUM | 45 CY | $1,638 | $3,000 | 5% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: WITH EARLY STRENGTH PUM | 42 CY | $1,632 | $3,000 | 5% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: WITH EARLY STRENGTH PUM | 41 CY | $1,638 | $2,200 | 5% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.:STEEL JOIN | 93 FT | $660 | $560 | 4% |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 17 CY | $2,910 | $6,000 | 4% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: STEEL JOI | 93 FT | $530 | $560 | 4% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.:STEEL JOIN | 71 FT | $674 | $560 | 3% |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 17 CY | $2,726 | $3,300 | 3% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: ACCELERATING ADDMIXTURE | 13 CY | $3,438 | $5,500 | 3% |
| 601E21000 CONCRETE SLOPE PROTECTION | 149 SY | $297 | $225 | 3% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 500 HOUR | $84.00 | $90.00 | 3% |
| 513E95000 STRUCTURAL STEEL, MISC.: REPAIR OF DAMAGED MAIN ME | 31 FT | $1,264 | $1,190 | 3% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: STEEL JOI | 71 FT | $545 | $560 | 3% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: ACCELERATING ADMIXTURE | 10 CY | $3,750 | $4,800 | 3% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: ACCELERATING ADDMIXTURE | 10 CY | $3,750 | $4,000 | 3% |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 1,388 LB | $26.36 | $36.00 | 3% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: ACCELERATING ADDMIXTURE | 8 CY | $4,088 | $4,000 | 2% |
| 514E27700 FIELD PAINTING, MISC.: MAIN AND SECONDARY MEMBERS | 1,352 SF | $23.93 | $54.00 | 2% |
| Item | Quantity | R1Bcc Ohio INC | R2Complete General Construction Company |
|---|---|---|---|
| 646E10200 CENTER LINE | 0.08 MILE | $88,872 | $48,700 |
| 646E10300 CHANNELIZING LINE, 8" | 200 FT | $3.68 | $7.00 |
| 646E20300 LANE ARROW | 1 EACH | $368 | $200 |
| 646E20410 WORD ON PAVEMENT, 96" | 1 EACH | $394 | $200 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $1,110 | $1,100 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 8 SNMT | $1,279 | $900 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| — |
| $15,964 |
| $220,000 |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 8 CY | $3,126 | $3,500 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 6,327 LB | $1.82 | $2.47 |
| 510E10001 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT, AS | 380 EACH | $20.48 | $18.00 |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 8 CY | $3,040 | $6,600 |
| 519E11600 SPECIAL - PATCHING CONCRETE STRUCTURE, VERTICOAT | 30 SF | $132 | $150 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 72 SY | $159 | $130 |
| 202E30000 WALK REMOVED | 32 SF | $14.06 | $20.00 |
| 608E13001 6" CONCRETE WALK, AS PER PLAN | 32 SF | $65.63 | $60.00 |
| 202E22901 APPROACH SLAB REMOVED, AS PER PLAN | 2 SY | $563 | $650 |
| 202E23000 PAVEMENT REMOVED | 38 SY | $139 | $300 |
| 202E98200 REMOVAL MISC.: JOINT SEAL | 13 FT | $19.05 | $50.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 113 FT | $13.07 | $4.00 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 977 LB | $1.82 | $2.34 |
| 510E10001 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT, AS | 104 EACH | $20.48 | $18.00 |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: EMSEAL (2 | 113 FT | $86.11 | $85.00 |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 113 FT | $16.25 | $25.00 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | — | $15,963 | $190,000 |
| 202E32800 CONCRETE SLOPE PROTECTION REMOVED | 178 SY | $75.42 | $300 |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 10 CY | $2,501 | $3,800 |
| 509E10001 EPOXY COATED REINFORCING STEEL, AS PER PLAN | 7,970 LB | $1.82 | $2.65 |
| 510E10001 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT, AS | 378 EACH | $20.48 | $18.00 |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 10 CY | $3,013 | $7,400 |
| 202E11401 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (SECOND | 674 LB | $6.29 | $5.35 |
| 202E98000 REMOVAL MISC.: BEAM SEAT DEBRIS | 1 LS | $1,800 | $8,000 |
| 202E98400 REMOVAL MISC.: POWER WASHING | 2,160 SF | $1.49 | $4.00 |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 674 LB | $14.30 | $13.70 |
| 513E95000 STRUCTURAL STEEL, MISC.: REPAIR OF DAMAGED SECONDA | 18 FT | $293 | $255 |
| 202E11401 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (MAIN M | 1,734 LB | $11.34 | $19.00 |
| 202E11401 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN (SECOND | 500 LB | $7.46 | $6.25 |
| 202E23000 PAVEMENT REMOVED | 33 SY | $160 | $400 |
| 202E98000 REMOVAL MISC.: BEAM SEAT DEBRIS | 1 LS | $1,800 | $8,000 |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 10 CY | $2,726 | $3,800 |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 10 CY | $3,013 | $7,500 |
| 513E95000 STRUCTURAL STEEL, MISC.: REPAIR OF DAMAGED SECONDA | 15 FT | $148 | $338 |
| 513E95030 STRUCTURAL STEEL, MISC.: REPAIR OF DAMAGED MEMBERS | 15 EACH | $114 | $80.00 |
| 514E27700 FIELD PAINTING, MISC.: MAIN AND SECONDARY MEMBERS | 151 SF | $86.92 | $250 |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: EMSEAL (3 | 75 FT | $113 | $130 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $19,203 | $90,000 |
| 601E32205 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 57 CY | $179 | $128 |
| 203E10001 EXCAVATION, AS PER PLAN | 9 CY | $143 | $105 |
| 518E12500 SCUPPER, MISC.: 6" CONDUIT | 6 EACH | $1,249 | $1,500 |
| 519E11600 SPECIAL - PATCHING CONCRETE STRUCTURE, VERTICOAT | 64 SF | $132 | $160 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 6 SY | $160 | $340 |
| 203E10001 EXCAVATION, AS PER PLAN | 9 CY | $143 | $95.00 |
| 518E12500 SCUPPER, MISC.: 6" CONDUIT | 6 EACH | $1,249 | $1,500 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 3 SY | $159 | $340 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | — | $15,963 | $230,000 |
| 202E32800 CONCRETE SLOPE PROTECTION REMOVED | 121 SY | $193 | $285 |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 9 CY | $2,726 | $3,800 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 9,012 LB | $1.82 | $2.64 |
| 510E10001 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT, AS | 352 EACH | $20.48 | $18.00 |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 9 CY | $3,067 | $7,500 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 13 SF | $29.86 | $12.00 |
| 601E21000 CONCRETE SLOPE PROTECTION | 96 SY | $306 | $300 |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 10 CY | $2,726 | $3,800 |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 10 CY | $3,013 | $7,000 |
| 516E31001 JOINT SEALER, AS PER PLAN (A) | 4 FT | $19.50 | $85.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 8 SF | $46.83 | $250 |
| 609E98000 CURB, MISC.: REMOVED AND REPLACED | 3 FT | $200 | $350 |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN, SUBSTR | 7 CY | $2,743 | $5,000 |
| 202E23500 WEARING COURSE REMOVED (2.50" THICK) | 537 SY | $14.32 | $14.00 |
| 407E20000 NON-TRACKING TACK COAT | 70 GAL | $3.68 | $3.50 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 19 CY | $835 | $795 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (19 CY | $798 | $760 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 991 LB | $1.82 | $5.49 |
| 512E33010 TYPE 3 WATERPROOFING | 537 SY | $45.79 | $35.00 |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: EMSEAL (2 | 76 FT | $89.66 | $95.00 |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 141 FT | $16.25 | $25.00 |
| 519E11600 SPECIAL - PATCHING CONCRETE STRUCTURE, VERTICOAT | 6 SF | $132 | $180 |
| 844E10000 CONCRETE PATCHING WITH GALVANIC ANODE PROTECTION | 3 SF | $171 | $390 |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN, SUBSTR | 9 CY | $2,743 | $5,000 |
| 202E23500 WEARING COURSE REMOVED (2.50" THICK) | 769 SY | $13.06 | $12.75 |
| 407E20000 NON-TRACKING TACK COAT | 100 GAL | $3.68 | $3.50 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 27 CY | $683 | $650 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (27 CY | $651 | $620 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,212 LB | $1.82 | $2.47 |
| 512E33010 TYPE 3 WATERPROOFING | 769 SY | $36.90 | $35.00 |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: EMSEAL (2 | 97 FT | $93.54 | $85.00 |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 185 FT | $16.25 | $25.00 |
| 519E00100 SPECIAL - COMPOSITE FIBER WRAP SYSTEM | 175 SF | $80.16 | $72.00 |
| 630E86321 REMOVAL OF STRUCTURE MOUNTED SIGN AND REERECTION, | 1 EACH | $450 | $1,200 |
| 843E50000 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 27 SF | $144 | $150 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 2 SY | $86.25 | $150 |
| 844E10000 CONCRETE PATCHING WITH GALVANIC ANODE PROTECTION | 12 SF | $171 | $240 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 3 SF | $125 | $185 |
| 601E20010 CRUSHED AGGREGATE SLOPE PROTECTION | 6 CY | $159 | $350 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $6,750 | $6,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $28,715 | $22,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $426,233 | $426k | 18% |
| 624E10000 MOBILIZATION | 1 LS | $128,181 | $128k | 6% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: WITH EARLY STRENGTH PUM | 45 CY | $1,638 | $74k | 3% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: WITH EARLY STRENGTH PUM | 42 CY | $1,632 | $69k | 3% |
| 511E53012 CLASS QC2 CONCRETE, MISC.: WITH EARLY STRENGTH PUM | 41 CY | $1,638 | $67k | 3% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.:STEEL JOIN | 93 FT | $659.71 | $61k | 3% |
| 511E34451 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 17 CY | $2,910 | $49k | 2% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: STEEL JOI | 93 FT | $529.59 | $49k | 2% |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.:STEEL JOIN | 71 FT | $674.38 | $48k | 2% |
| 202E98500 REMOVAL MISC.: PORTIONS OF PARAPET REMOVED | 17 CY | $2,726 | $46k | 2% |