WAR-SR 73-14.58/14.62
WAR County · est $3.7M
Bid dateThursday, August 10—
WAR County · est $3.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 111 more items below.
| Item | Quantity | R1Double Z Construction Company | R2Kt Holden Construction LLC | R3Sunesis Construction CO | R4Complete General Construction Company | R5Eagle Bridge CO | % of bid |
|---|---|---|---|---|---|---|---|
| 840E20000 MECHANICALLY STABILIZED EARTH WALL | 7,547 SF | $48.00 | $40.00 | $41.08 | $45.00 | $62.50 | 12% |
| 515E15020 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 6 EACH | $52,000 | $48,000 | $59,468 | $49,805 | $56,000 | 11% |
| 511E53014 CLASS QC3 CONCRETE, MISC.:WITH QC/QA, BRIDGE DECK, | 213 CY | $1,270 | $1,115 | $1,509 | $1,250 | $1,600 | 9% |
| 840E23000 SELECT GRANULAR BACKFILL | 3,782 CY | $60.00 | $89.00 | $78.38 | $80.00 | $105 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $158,500 | $70,000 | $102,313 | $130,000 | $165,000 | 5% |
| 202E11202 |
| Item | Quantity | R1Double Z Construction Company | R2Kt Holden Construction LLC | R3Sunesis Construction CO | R4Complete General Construction Company | R5Eagle Bridge CO |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $44,000 | $24,000 | $38,022 | $45,000 | $50,000 |
| 202E32000 CURB REMOVED | 43 FT | $10.00 | $4.00 | $6.67 | $25.00 | $6.00 |
| 202E38000 GUARDRAIL REMOVED | 665 FT | $6.00 | $6.00 | $6.04 | $6.00 | $2.80 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $75.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $150,000 |
| $170,000 |
| $159,227 |
| $265,000 |
| $190,000 |
| 5% |
| 511E53012 CLASS QC2 CONCRETE, MISC.:MOMENT SLAB/PARAPET WITH | 252 CY | $550 | $760 | $738 | $850 | $725 | 5% |
| 867E00100 TEMPORARY WIRE FACED MECHANICALLY STABILIZED EARTH | 1 LS | $130,000 | $80,000 | $176,135 | $250,000 | $130,000 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 90,968 LB | $1.40 | $1.33 | $1.74 | $1.50 | $1.40 | 4% |
| 526E30001 REINFORCED CONCRETE APPROACH SLABS (T=17"), AS PER | 316 SY | $400 | $430 | $513 | $500 | $550 | 4% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 960 SY | $128 | $139 | $141 | $90.00 | $88.00 | 4% |
| 840E26000 CONCRETE COPING | 555 FT | $200 | $208 | $261 | $150 | $200 | 4% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $105,000 | $139,710 | $103,802 | $50,000 | $80,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $77,848 | $100,000 | $100,000 | 3% |
| 507E00650 14" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 1,330 FT | $75.00 | $78.00 | $58.34 | $50.00 | $80.00 | 3% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,072 SY | $88.00 | $96.00 | $36.20 | $90.00 | $93.00 | 3% |
| 513E10001 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 1 LS | $80,000 | $80,000 | $55,263 | $85,000 | $125,000 | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (261 CY | $300 | $300 | $293 | $275 | $300 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 232 CY | $300 | $300 | $352 | $330 | $300 | 2% |
| 840E21000 WALL EXCAVATION | 1,892 CY | $36.00 | $28.00 | $30.79 | $30.00 | $30.00 | 2% |
| $75.00 |
| $75.49 |
| $75.00 |
| $125 |
| 203E10000 EXCAVATION | 349 CY | $20.00 | $30.00 | $20.88 | $30.00 | $45.00 |
| 203E20000 EMBANKMENT | 1,572 CY | $23.00 | $18.00 | $27.59 | $40.00 | $16.00 |
| 204E10000 SUBGRADE COMPACTION | 889 SY | $9.00 | $4.20 | $5.76 | $20.00 | $10.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 250 FT | $21.00 | $21.00 | $21.14 | $21.00 | $21.00 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 37.5 FT | $24.00 | $24.00 | $24.15 | $24.00 | $25.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350 OR MASH 201 | 1 EACH | $2,550 | $2,550 | $2,566 | $2,550 | $2,600 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,225 | $1,225 | $1,233 | $1,225 | $1,300 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 5 EACH | $2,550 | $2,550 | $2,566 | $2,550 | $2,600 |
| 622E24000 CONCRETE BARRIER, TYPE D | 38 FT | $180 | $145 | $38.25 | $275 | $250 |
| 622E25000 CONCRETE BARRIER END SECTION, TYPE D | 1 EACH | $4,500 | $3,500 | $4,428 | $10,000 | $7,000 |
| 622E25050 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 1 EACH | $4,500 | $4,250 | $4,428 | $20,000 | $7,000 |
| 623E40501 REFERENCE MONUMENT, AS PER PLAN | 1 EACH | $800 | $1,180 | $677 | $1,000 | $650 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $25,000 | $21,250 | $44,215 | $26,150 | $50,000 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 3 CY | $240 | $200 | $73.48 | $900 | $110 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $200 | $150 | $151 | $100 | $375 |
| 659E00300 TOPSOIL | 51 CY | $80.00 | $58.00 | $125 | $25.00 | $50.00 |
| 659E10000 SEEDING AND MULCHING | 459 SY | $10.00 | $3.00 | $6.79 | $9.50 | $10.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 23 SY | $1.00 | $1.00 | $1.01 | $17.00 | $3.50 |
| 659E15000 INTER-SEEDING | 23 SY | $0.01 | $1.00 | $1.01 | $17.00 | $3.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.08 TON | $1,500 | $2,000 | $2,013 | $700 | $1,750 |
| 659E31000 LIME | 0.1 ACRE | $200 | $200 | $201 | $100 | $10.00 |
| 659E35000 WATER | 4 MGAL | $1.00 | $20.00 | $20.13 | $20.00 | $20.00 |
| 659E40000 MOWING | 2 MSF | $1.00 | $10.00 | $1.01 | $200 | $50.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1 CY | $3,500 | $2,800 | $4,030 | $4,084 | $3,500 |
| 605E31100 AGGREGATE DRAINS | 43 FT | $25.00 | $16.00 | $26.90 | $54.00 | $12.00 |
| 611E06700 15" CONDUIT, TYPE F, 707.05 TYPE C | 161 FT | $120 | $118 | $134 | $150 | $130 |
| 611E99114 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE D | 2 EACH | $15,000 | $13,000 | $13,883 | $12,000 | $12,500 |
| 202E23000 PAVEMENT REMOVED | 498 SY | $20.00 | $25.00 | $24.07 | $60.00 | $35.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=3") | 4,184 SY | $5.00 | $5.00 | $5.33 | $5.00 | $5.00 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 204 CY | $270 | $270 | $346 | $325 | $270 |
| 304E20000 AGGREGATE BASE | 209 CY | $105 | $75.00 | $96.21 | $95.00 | $140 |
| 407E20000 NON-TRACKING TACK COAT | 1,807 GAL | $1.00 | $1.00 | $4.26 | $4.00 | $1.00 |
| 609E24510 CURB, TYPE 4-C | 146 FT | $45.00 | $37.00 | $40.26 | $75.00 | $55.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1 1/2") | 484 SY | $14.26 | $11.88 | $22.11 | $20.75 | $12.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 4 CY | $500 | $500 | $693 | $650 | $500 |
| 621E00100 RPM | 26 EACH | $147 | $147 | $128 | $147 | $150 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 26 EACH | $10.00 | $9.00 | $128 | $12.00 | $20.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 3 EACH | $14.00 | $12.00 | $10.06 | $10.00 | $10.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 14 EACH | $14.00 | $10.00 | $10.06 | $10.00 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 73 FT | $12.00 | $12.00 | $12.08 | $12.00 | $20.00 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 35 FT | $19.50 | $19.50 | $19.63 | $19.50 | $23.50 |
| 630E08600 SIGN POST REFLECTOR | 1 EACH | $75.00 | $75.00 | $75.48 | $75.00 | $50.00 |
| 630E80100 SIGN, FLAT SHEET | 6 SF | $26.00 | $26.00 | $26.17 | $26.00 | $30.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $15.00 | $15.00 | $15.10 | $15.00 | $20.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 7 EACH | $85.00 | $85.00 | $85.55 | $85.00 | $125 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 8 EACH | $50.00 | $50.00 | $50.32 | $50.00 | $20.00 |
| 644E00104 EDGE LINE, 6" | 0.16 MILE | $11,205 | $11,205 | $11,277 | $11,205 | $11,205 |
| 644E00300 CENTER LINE (BROKEN & SOLID, DOUBLE) | 0.34 MILE | $9,390 | $9,390 | $9,451 | $9,390 | $9,390 |
| 644E00300 CENTER LINE (SOLID, DOUBLE) | 0.05 MILE | $14,285 | $14,285 | $14,377 | $14,285 | $14,285 |
| 644E00500 STOP LINE | 21 FT | $26.00 | $26.00 | $26.17 | $26.00 | $26.00 |
| 645E00117 EDGE LINE, 6", TYPE A3, AS PER PLAN (WHITE) | 0.06 MILE | $117,420 | $117,420 | $118,178 | $117,420 | $117,420 |
| 645E00311 CENTER LINE, TYPE A3, AS PER PLAN | 0.03 MILE | $168,190 | $168,190 | $169,275 | $168,190 | $168,190 |
| 646E10010 EDGE LINE, 6" (WHITE) | 0.11 MILE | $27,410 | $27,410 | $27,587 | $27,410 | $27,410 |
| 646E10200 CENTER LINE | 0.06 MILE | $36,585 | $36,585 | $36,821 | $36,585 | $36,585 |
| 646E10600 TRANSVERSE/DIAGONAL LINE (YELLOW) | 6 FT | $65.62 | $65.62 | $66.04 | $65.62 | $65.62 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $60.00 | $70.00 | $77.50 | $85.00 | $105 |
| 614E11630 INCREASED BARRIER DELINEATION | 475 FT | $4.00 | $3.50 | $3.52 | $3.50 | $3.50 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,350 | $2,350 | $2,365 | $2,350 | $2,200 |
| 614E12420 DETOUR SIGNING | 1 LS | $20,500 | $32,160 | $18,862 | $32,160 | $25,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 91 EACH | $20.00 | $14.00 | $14.09 | $14.00 | $14.00 |
| 614E13312 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 8 EACH | $20.00 | $14.00 | $14.09 | $14.00 | $14.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 99 EACH | $20.00 | $21.00 | $21.14 | $21.00 | $21.00 |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 3 SNMT | $1,000 | $1,050 | $1,057 | $1,050 | $1,100 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I (DOUBLE SOLID) | 0.18 MILE | $5,060 | $5,060 | $5,093 | $5,060 | $5,060 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" (WHITE) | 0.72 MILE | $3,930 | $3,930 | $3,955 | $3,930 | $3,930 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 44 FT | $10.00 | $10.00 | $10.06 | $10.00 | $10.00 |
| 616E10000 WATER | 4 MGAL | $150 | $65.00 | $10.31 | $95.00 | $15.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,290 FT | $29.00 | $19.50 | $19.63 | $19.50 | $26.00 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 310 FT | $45.00 | $24.00 | $23.65 | $23.50 | $30.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 22 SY | $75.00 | $150 | $75.48 | $75.00 | $75.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 22 SY | $28.50 | $150 | $28.68 | $28.50 | $28.50 |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 10 EACH | $2,000 | $2,145 | $2,865 | $1,800 | $2,250 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $36,000 | $48,200 | $33,706 | $25,000 | $100,000 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 196 SF | $150 | $175 | $406 | $200 | $250 |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 112 SY | $110 | $120 | $238 | $90.00 | $88.00 |
| 848E50000 HAND CHIPPING | 48 SY | $120 | $120 | $321 | $130 | $250 |
| 848E50100 TEST SLAB | 1 LS | $500 | $500 | $2,862 | $500 | $1,500 |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED (THICKNESS 3.00 | 960 SY | $20.00 | $22.00 | $17.49 | $20.00 | $16.00 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 9 CY | $400 | $400 | $443 | $350 | $405 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 144 SY | $75.00 | $75.00 | $307 | $30.00 | $37.00 |
| 202E22900 APPROACH SLAB REMOVED | 97 SY | $50.00 | $35.00 | $55.62 | $75.00 | $75.00 |
| 202E23500 WEARING COURSE REMOVED | 97 SY | $5.00 | $15.00 | $16.86 | $5.00 | $25.00 |
| 203E35111 GRANULAR MATERIAL, TYPE B, AS PER PLAN | 723 CY | $74.00 | $77.00 | $72.84 | $100 | $110 |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $22,000 | $56,000 | $20,702 | $35,000 | $35,000 |
| 507E00600 14" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 1,190 FT | $10.00 | $47.00 | $34.77 | $55.00 | $10.00 |
| 511E33500 SEMI-INTEGRAL DIAPHRAGM GUIDE | 2 EACH | $3,700 | $2,500 | $2,991 | $7,000 | $4,500 |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 104 CY | $550 | $600 | $711 | $800 | $900 |
| 511E53014 CLASS QC3 CONCRETE, MISC.:WITH QC/QA, BRIDGE DECK | 29 CY | $1,860 | $970 | $1,043 | $750 | $1,400 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 1,553 SY | $12.00 | $13.50 | $12.08 | $12.00 | $12.00 |
| 512E33000 TYPE 2 WATERPROOFING | 6 SY | $120 | $110 | $115 | $135 | $90.00 |
| 515E20000 INTERMEDIATE DIAPHRAGMS | 15 EACH | $2,100 | $3,000 | $4,105 | $6,500 | $4,500 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 92 FT | $60.00 | $50.00 | $70.45 | $70.00 | $60.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 16 SF | $20.00 | $8.00 | $8.45 | $10.00 | $20.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 96 FT | $25.00 | $50.00 | $45.29 | $45.00 | $40.00 |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 12 EACH | $2,600 | $2,800 | $3,306 | $2,500 | $3,500 |
| 523E20000 DYNAMIC LOAD TESTING | 4 EACH | $3,370 | $2,300 | $5,204 | $10,000 | $5,000 |
| 526E90030 TYPE C INSTALLATION | 96 FT | $300 | $225 | $244 | $350 | $400 |
| 601E21001 CONCRETE SLOPE PROTECTION, AS PER PLAN | 65 SY | $230 | $150 | $204 | $200 | $275 |
| 607E39900 VANDAL PROTECTION FENCE, 6' STRAIGHT, COATED FABRI | 174 FT | $185 | $160 | $161 | $160 | $104 |
| 840E22000 FOUNDATION PREPARATION | 914 SY | $35.00 | $50.00 | $46.16 | $25.00 | $50.00 |
| 840E25010 6" DRAINAGE PIPE, PERFORATED | 578 FT | $14.00 | $10.00 | $7.53 | $10.00 | $25.00 |
| 840E25020 6" DRAINAGE PIPE, NON-PERFORATED | 78 FT | $20.00 | $20.00 | $7.48 | $30.00 | $18.00 |
| 840E27000 ON-SITE ASSISTANCE | 5 DAY | $500 | $600 | $5,052 | $1,000 | $600 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $23,000 | $45,100 | $0.01 | $45,000 | $75,000 |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $2,400 | $2,100 | $1,377 | $2,000 | $2,250 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $45,000 | $21,050 | $14,040 | $20,000 | $30,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 840E20000 MECHANICALLY STABILIZED EARTH WALL | 7,547 SF | $48 | $362k | 9% |
| 515E15020 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 6 EACH | $52,000 | $312k | 8% |
| 511E53014 CLASS QC3 CONCRETE, MISC.:WITH QC/QA, BRIDGE DECK, | 213 CY | $1,270 | $271k | 7% |
| 840E23000 SELECT GRANULAR BACKFILL | 3,782 CY | $60 | $227k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $158,500 | $159k | 4% |
| 202E11202 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $150,000 | $150k | 4% |
| 511E53012 CLASS QC2 CONCRETE, MISC.:MOMENT SLAB/PARAPET WITH | 252 CY | $550 | $139k | 3% |
| 867E00100 TEMPORARY WIRE FACED MECHANICALLY STABILIZED EARTH | 1 LS | $130,000 | $130k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 90,968 LB | $1.4 | $127k | 3% |
| 526E30001 REINFORCED CONCRETE APPROACH SLABS (T=17"), AS PER | 316 SY | $400 | $126k | 3% |