FRA-IR 70-16.76
FRA County · est $2.3M
Bid dateThursday, September 28—
FRA County · est $2.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 56 more items below.
| Item | Quantity | R1Complete General Construction Company | R2Shelly & Sands INC | % of bid |
|---|---|---|---|---|
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 3,289 SY | $117 | $100 | 16% |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 3,289 SY | $107 | $100 | 15% |
| 858E10000 THIN POLYMER EPOXY OVERLAY | 5,022 SY | $56.75 | $75.00 | 12% |
| 517E75501 BRIDGE RAILING REBUILT, AS PER PLAN | 686 FT | $275 | $256 | 8% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $110,000 | $150,000 | 5% |
| 519E12304 PATCHING CONCRETE BRIDGE DECK - TYPE C | 164 SY | $650 | $1,000 | 5% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $105,000 | $500,000 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $105,000 | $400,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $394,000 | 4% |
| 601E21000 CONCRETE SLOPE PROTECTION | 900 SY | $110 | $140 | 4% |
| 601E27001 DUMPED ROCK FILL, TYPE C, AS PER PLAN | 756 CY | $130 | $120 | 4% |
| 519E11100 PATCHING CONCRETE STRUCTURE | 463 SF | $190 | $200 | 4% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $65,000 | $9,500 | 3% |
| 601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE C | 325 CY | $185 | $160 | 3% |
| 900E00100 RAILROAD FLAGGING SERVICES | 49,950 EACH | $1.00 | $1.00 | 2% |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED 1 3/4" NOMINAL | 3,289 SY | $14.00 | $18.00 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $35,000 | $46,099 | 1% |
| 518E12801 SCUPPER, MODIFICATION, AS PER PLAN | 17 EACH | $1,600 | $1,800 | 1% |
| 848E50200 FULL-DEPTH REPAIR | 27 CY | $900 | $1,400 | 1% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 210 SY | $85.00 | $85.00 | 1% |
| Item | Quantity | R1Complete General Construction Company | R2Shelly & Sands INC |
|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 72 SY | $18.00 | $18.00 |
| 202E30000 WALK REMOVED | 733 SF | $4.75 | $2.00 |
| 202E30700 CONCRETE BARRIER REMOVED | 48 FT | $33.00 | $14.00 |
| 202E32000 CURB REMOVED | 260 FT | $7.00 | $10.00 |
| 202E32600 GUTTER REMOVED | 260 FT | $13.00 | $10.00 |
| 202E58200 INLET REMOVED | 2 EACH | $500 | $650 |
| 202E75000 FENCE REMOVED | 260 FT | $3.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $4.00 |
| 253E01000 PAVEMENT REPAIR | 72 SY | $150 | $300 |
| 607E23000 FENCE, TYPE CLT | 260 FT | $34.50 | $37.00 |
| 608E10000 4" CONCRETE WALK | 778 SF | $12.00 | $15.00 |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 260 FT | $55.00 | $75.00 |
| 609E26000 CURB, TYPE 6 | 260 FT | $43.00 | $40.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 15 FT | $60.00 | $60.00 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 326 FT | $18.00 | $14.00 |
| 602E20000 CONCRETE MASONRY | 0.48 CY | $2,700 | $2,500 |
| 611E04600 12" CONDUIT, TYPE C | 10 FT | $155 | $235 |
| 611E06100 15" CONDUIT, TYPE C | 5 FT | $232 | $450 |
| 611E98711 INLET, NO. 2-6, AS PER PLAN | 2 EACH | $7,500 | $8,500 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25") | 826 SY | $11.00 | $16.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 260 FT | $3.00 | $12.00 |
| 407E10000 TACK COAT | 62 GAL | $3.75 | $3.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 29 CY | $500 | $500 |
| 621E00100 RPM | 39 EACH | $150 | $110 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 42 EACH | $19.00 | $11.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 WHITE | 0.44 MILE | $1,250 | $1,350 |
| 642E00100 EDGE LINE, 4", TYPE 1 YELLOW | 0.27 MILE | $1,250 | $1,350 |
| 642E00200 LANE LINE, 4", TYPE 1 | 0.63 MILE | $780 | $850 |
| 642E00300 CENTER LINE, TYPE 1 | 0.11 MILE | $4,500 | $4,830 |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 422 FT | $1.20 | $1.50 |
| 423E00100 CRACK SEALING, TYPE I | 500 LB | $15.00 | $27.50 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 1 EACH | $4,000 | $2,300 |
| 516E46701 RESET BEARING, AS PER PLAN | 1 EACH | $600 | $2,000 |
| 607E30001 FENCE, SNOW, AS PER PLAN | 130 FT | $4.00 | $8.00 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 40 CY | $247 | $260 |
| 848E50000 HAND CHIPPING | 71 SY | $85.00 | $200 |
| 848E50100 TEST SLAB | 1 LS | $1,500 | $3,000 |
| 848E50300 WEARING COURSE REMOVED, ASPHALT | 271 SY | $14.00 | $35.00 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 165 SY | $50.00 | $100 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $90.00 | $86.00 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 3 EACH | $4,500 | $20,000 |
| 614E11630 INCREASED BARRIER DELINEATION | 2,302 FT | $2.40 | $2.00 |
| 614E12470 WORK ZONE SPEED LIMIT SIGN | 8 EACH | $225 | $450 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 4.35 CY | $300 | $1,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 8 EACH | $25.00 | $21.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 8 EACH | $21.00 | $24.00 |
| 614E20210 WORK ZONE LANE LINE, CLASS I, 6", 740.06, TYPE I | 1.07 MILE | $6,170 | $14,500 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.22 MILE | $1,440 | $3,350 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.54 MILE | $9,980 | $23,500 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 34 FT | $3.35 | $8.00 |
| 616E10000 WATER | 1 MGAL | $150 | $600 |
| 896E00012 PORTABLE NON-INTRUSIVE TRAFFIC SENSOR, CLASS II | 1 SNMT | $12,000 | $15,000 |
| 896E00021 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 1 SNMT | $13,000 | $15,000 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $5,000 | $10,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $17,000 | $25,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $4,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 3,289 SY | $117 | $385k | 15% |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 3,289 SY | $107 | $352k | 13% |
| 858E10000 THIN POLYMER EPOXY OVERLAY | 5,022 SY | $56.75 | $285k | 11% |
| 517E75501 BRIDGE RAILING REBUILT, AS PER PLAN | 686 FT | $275 | $189k | 7% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $110,000 | $110k | 4% |
| 519E12304 PATCHING CONCRETE BRIDGE DECK - TYPE C | 164 SY | $650 | $107k | 4% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $105,000 | $105k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $105,000 | $105k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 601E21000 CONCRETE SLOPE PROTECTION | 900 SY | $110 | $99k | 4% |