MEG-SR 7-05.80
MEG County · est $1.2M
Bid dateThursday, September 28—
MEG County · est $1.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 34 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Complete General Construction Company | R3Bcc Ohio INC | R4Catts Construction INC | R5Perk Company INC | % of bid |
|---|---|---|---|---|---|---|---|
| 847E10100 LATEX MODIFIED CONCRETE OVERLAY (2.5" THICK) | 1,266 SY | $116 | $120 | $139 | $142 | $197 | 18% |
| 847E10100 LATEX MODIFIED CONCRETE OVERLAY (2.5" THICK) | 1,266 SY | $110 | $120 | $139 | $142 | $197 | 17% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 3,744 FT | $21.00 | $25.00 | $22.58 | $26.00 | $21.50 | 10% |
| 847E10100 LATEX MODIFIED CONCRETE OVERLAY (1.5" THICK) | 453 SY | $140 | $170 | $168 | $160 | $210 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $46,000 | $65,000 | $78,362 | $51,000 | $212,300 | 6% |
| 624E10000 MOBILIZATION | 1 LS |
| Item | Quantity | R1Shelly & Sands INC | R2Complete General Construction Company | R3Bcc Ohio INC | R4Catts Construction INC | R5Perk Company INC |
|---|---|---|---|---|---|---|
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 200 SY | $15.00 | $25.00 | $4.46 | $5.00 | $7.60 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" DEPTH) | 1,058 SY | $9.50 | $9.50 | $9.98 | $12.00 | $10.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $40,000 |
| $40,000 |
| $72,975 |
| $124,050 |
| $228,800 |
| 5% |
| 847E20100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 37 CY | $770 | $730 | $1,263 | $1,182 | $850 | 3% |
| 847E20100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 37 CY | $770 | $730 | $1,263 | $1,083 | $850 | 3% |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 2.95 MILE | $9,575 | $9,575 | $10,054 | $2,932 | $9,575 | 3% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 264 SY | $105 | $130 | $127 | $169 | $84.10 | 3% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $25,000 | $20,000 | $4,305 | $7,000 | $10,500 | 3% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 44 CY | $505 | $505 | $530 | $631 | $500 | 3% |
| 847E30400 EXISTING CONCRETE OVERLAY REMOVED (2.25" THICK) | 1,266 SY | $16.00 | $25.00 | $9.74 | $27.50 | $39.40 | 2% |
| 847E30400 EXISTING CONCRETE OVERLAY REMOVED (2.25" THICK) | 1,266 SY | $16.00 | $25.00 | $9.74 | $19.00 | $39.40 | 2% |
| 847E30200 FULL DEPTH REPAIR | 15 CY | $1,300 | $250 | $800 | $650 | $1,500 | 2% |
| 847E30200 FULL DEPTH REPAIR | 15 CY | $1,300 | $250 | $800 | $650 | $1,500 | 2% |
| 847E30400 EXISTING CONCRETE OVERLAY REMOVED (1.25" THICK) | 453 SY | $39.00 | $35.00 | $15.13 | $85.00 | $36.00 | 2% |
| 847E50000 HAND CHIPPING | 190 SY | $90.00 | $125 | $159 | $65.00 | $100 | 2% |
| 847E50000 HAND CHIPPING | 190 SY | $90.00 | $125 | $159 | $63.00 | $100 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $15,001 | $30,000 | $15,734 | $15,018 | $17,920 | 2% |
| 96 GAL |
| $3.70 |
| $3.70 |
| $3.89 |
| $4.50 |
| $3.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 14 EACH | $20.00 | $20.00 | $30.00 | $32.00 | $25.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 3.77 MILE | $1,650 | $2,170 | $1,733 | $2,058 | $1,650 |
| 642E00204 LANE LINE, 6", TYPE 1 | 1.76 MILE | $1,250 | $1,445 | $1,313 | $1,560 | $1,250 |
| 642E00300 CENTER LINE, TYPE 1 | 0.14 MILE | $6,050 | $4,335 | $6,353 | $7,546 | $6,050 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,200 | $2,320 | $2,415 | $2,870 | $2,300 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,200 | $2,320 | $2,468 | $2,932 | $2,350 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, 1 WAY | 130 EACH | $7.00 | $22.00 | $23.10 | $27.50 | $22.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 28 EACH | $7.00 | $38.00 | $39.90 | $47.50 | $38.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 130 EACH | $16.00 | $30.00 | $31.50 | $37.50 | $30.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 28 EACH | $16.00 | $47.00 | $49.35 | $59.00 | $47.00 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.1 MILE | $15,500 | $15,500 | $16,275 | $31,807 | $15,500 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 3,840 FT | $0.60 | $0.60 | $0.63 | $1.00 | $1.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 24 FT | $13.00 | $13.00 | $13.65 | $17.50 | $15.00 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 50 LB | $2.00 | $10.00 | $5.08 | $5.00 | $13.25 |
| 516E31250 SPECIAL - SAWING AND SEALING CONCRETE JOINTS | 64 FT | $32.50 | $32.50 | $25.92 | $43.00 | $32.90 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 232 FT | $15.00 | $15.00 | $19.95 | $35.00 | $22.50 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 18 CF | $750 | $875 | $546 | $542 | $87.20 |
| 847E20100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 14 CY | $770 | $730 | $1,263 | $1,145 | $850 |
| 847E30000 TEST SLAB | 1 LS | $3,900 | $1,000 | $4,136 | $300 | $1,000 |
| 847E30200 FULL DEPTH REPAIR | 10 CY | $1,300 | $250 | $1,199 | $650 | $1,500 |
| 847E50000 HAND CHIPPING | 68 SY | $160 | $125 | $159 | $193 | $175 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 1 LS | $9,000 | $25,000 | $9,303 | $26,390 | $5,080 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 50 LB | $2.00 | $10.00 | $5.08 | $5.00 | $13.25 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 3 CY | $1,500 | $9,000 | $4,366 | $1,570 | $1,570 |
| 847E30000 TEST SLAB | 1 LS | $3,900 | $1,000 | $4,136 | $300 | $500 |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 1 LS | $9,000 | $25,000 | $9,303 | $26,400 | $5,000 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 50 LB | $2.00 | $10.00 | $5.08 | $5.00 | $13.25 |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 3 CY | $1,500 | $9,000 | $4,366 | $1,570 | $1,570 |
| 847E30000 TEST SLAB | 1 LS | $3,900 | $1,000 | $4,136 | $300 | $500 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,500 | $11,000 | $14,387 | $12,840 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 847E10100 LATEX MODIFIED CONCRETE OVERLAY (2.5" THICK) | 1,266 SY | $116 | $147k | 15% |
| 847E10100 LATEX MODIFIED CONCRETE OVERLAY (2.5" THICK) | 1,266 SY | $110 | $139k | 14% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 3,744 FT | $21 | $79k | 8% |
| 847E10100 LATEX MODIFIED CONCRETE OVERLAY (1.5" THICK) | 453 SY | $140 | $63k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $46,000 | $46k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 847E20100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 37 CY | $770 | $28k | 3% |
| 847E20100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 37 CY | $770 | $28k | 3% |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 2.95 MILE | $9,575 | $28k | 3% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 264 SY | $105 | $28k | 3% |