HAM-/WAR-IR 71-13.50/19.29/03.58
HAM County · est $0.6M
Bid dateThursday, December 14—
HAM County · est $0.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 8 more items below.
| Item | Quantity | R1Bcc Ohio INC | R2Sunesis Construction CO | R3Axis Civil Construction LLC | % of bid |
|---|---|---|---|---|---|
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 150" C | 426 FT | $254 | $289 | $270 | 23% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 126" C | 408 FT | $218 | $298 | $815 | 19% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 132" C | 162 FT | $235 | $254 | $960 | 8% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 60" CMP | 300 FT | $122 | $502 | $150 | 8% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $25,653 | $97,250 | $55,000 | 6% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 100 CY | $233 | $253 | $150 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $21,345 |
| Item | Quantity | R1Bcc Ohio INC | R2Sunesis Construction CO | R3Axis Civil Construction LLC |
|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" AND UNDER | 10 FT | $46.20 | $48.50 | $30.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.65 TON | $1,292 | $1,100 | $1,100 |
| 659E31000 LIME | 1 ACRE | $630 | $250 | $250 |
| 659E35000 WATER | 27 MGAL | $10.50 | $10.00 | $10.00 |
| 611E07600 18" CONDUIT, TYPE C | 10 FT | $249 | $370 | $300 |
| 843E50000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $55,000 |
| $25,000 |
| 5% |
| 659E10000 SEEDING AND MULCHING | 4,840 SY | $4.04 | $2.35 | $0.82 | 4% |
| 606E10900 SPECIAL - NOISE BARRIER PANEL REMOVAL AND REUSE | 1 LS | $17,334 | $5,700 | $30,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $17,060 | $57,400 | $20,000 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $14,322 | $44,950 | $75,000 | 3% |
| 509E25000 UNCOATED STEEL REINFORCEMENT | 2,988 LB | $3.55 | $5.75 | $5.10 | 2% |
| 611E97700 CONDUIT, MISC.:, REPAIR METHOD A | 70 SF | $110 | $60.00 | $110 | 2% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | 1% |
| 602E20000 CONCRETE MASONRY | 1 CY | $5,958 | $1,950 | $2,600 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,938 | $5,125 | $5,000 | 1% |
| 611E97700 CONDUIT, MISC.:, REPAIR METHOD A | 50 SF | $115 | $65.00 | $110 | 1% |
| 611E97700 CONDUIT, MISC.:, REPAIR METHOD A | 50 SF | $115 | $80.00 | $110 | 1% |
| 202E11200 PORTIONS OF STRUCTURE REMOVED | 1 LS | $3,234 | $8,200 | $1,250 | 1% |
| 611E97700 CONDUIT, MISC.:, REPAIR METHOD B | 20 SF | $156 | $210 | $275 | 1% |
| 20 SF |
| $151 |
| $148 |
| $200 |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 24" CM | 10 FT | $266 | $278 | $125 |
| 611E97700 CONDUIT, MISC.:, REPAIR METHOD B | 20 SF | $156 | $225 | $275 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 150" C | 426 FT | $254.31 | $108k | 23% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 126" C | 408 FT | $217.89 | $89k | 19% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 132" C | 162 FT | $234.95 | $38k | 8% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 60" CMP | 300 FT | $121.81 | $37k | 8% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $25,653 | $26k | 5% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 100 CY | $233.25 | $23k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $21,345 | $21k | 4% |
| 659E10000 SEEDING AND MULCHING | 4,840 SY | $4.04 | $20k | 4% |
| 606E10900 SPECIAL - NOISE BARRIER PANEL REMOVAL AND REUSE | 1 LS | $17,334 | $17k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $17,060 | $17k | 4% |