JEF-US 22-13.83/14.71
JEF County · est $1.0M
Bid dateThursday, November 30—
JEF County · est $1.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 17 more items below.
| Item | Quantity | R1Marucci & Gaffney Excavating CO | R2Rudzik Excavating INC | R3Litman Excavating INC | R4Eclipse CO LLC | R5Ohio-west Virginia Excavating CO | R6S E T INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 837E10000 LINER PIPE, 66" ID 707.85 | 341 FT | $493 | $592 | $802 | $488 | $458 | $647 | 20% |
| 837E21000 BACKFILL FOR LINER PIPE | 806 FT | $151 | $239 | $127 | $167 | $285 | $293 | 15% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100,000 | $29,680 | $59,105 | $45,000 |
| Item | Quantity | R1Marucci & Gaffney Excavating CO | R2Rudzik Excavating INC | R3Litman Excavating INC | R4Eclipse CO LLC | R5Ohio-west Virginia Excavating CO | R6S E T INC |
|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $2,500 | $2,000 | $1,565 | $918 | $4,000 | $2,000 |
| 202E35200 PIPE REMOVED, OVER 24" | 18 FT | $50.00 | $55.00 | $174 | $100 | $288 | $85.00 |
| 202E75000 FENCE REMOVED | 113 FT | $2.00 | $5.00 | $9.05 | $2.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $44,700 |
| $27,800 |
| 12% |
| 837E10000 LINER PIPE, 60" ID 707.33, 707.85 | 299 FT | $329 | $400 | $507 | $345 | $368 | $505 | 12% |
| 602E20000 CONCRETE MASONRY | 24.6 CY | $2,800 | $1,245 | $622 | $1,950 | $1,845 | $2,890 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $65,000 | $20,350 | $13,225 | $20,000 | $27,200 | $26,700 | 8% |
| 837E10000 LINER PIPE, 54" ID 707.33, 707.85 | 166 FT | $258 | $375 | $533 | $318 | $232 | $614 | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $30,000 | $34,170 | $6,127 | $56,500 | $2,900 | $50,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $29,343 | $14,000 | $34,314 | $22,240 | $41,420 | 2% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 796 FT | $20.00 | $38.00 | $22.48 | $74.00 | $13.75 | $30.00 | 2% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 92 CY | $170 | $160 | $111 | $164 | $191 | $166 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,000 | $9,135 | $10,740 | $12,500 | $10,875 | $12,000 | 1% |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 38 SY | $275 | $340 | $181 | $304 | $458 | $322 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,030 FT | $10.00 | $5.50 | $28.08 | $58.00 | $32.00 | $63.70 | 1% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 659E10000 SEEDING AND MULCHING | 3,206 SY | $3.00 | $2.00 | $1.26 | $1.64 | $2.82 | $4.40 | 1% |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $3,000 | $3,390 | $4,025 | $2,130 | $3,685 | $2,750 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $1,000 | $900 | $2,875 | $684 | $3,895 | $940 | 1% |
| 659E00300 TOPSOIL | 356 CY | $20.00 | $8.00 | $27.80 | $65.00 | $96.00 | $89.89 | 1% |
| 601E11000 RIPRAP, TYPE D | 11 SY | $500 | $300 | $433 | $456 | $680 | $331 | 1% |
| $34.00 |
| $2.64 |
| 202E98300 REMOVAL MISC.: RIPRAP REMOVED | 49 SY | $50.00 | $30.00 | $18.23 | $40.00 | $52.00 | $45.00 |
| 607E15000 FENCE, TYPE 47 | 113 FT | $40.00 | $50.00 | $57.50 | $43.00 | $108 | $100 |
| 659E00100 SOIL ANALYSIS TEST | 4 EACH | $10.00 | $50.00 | $115 | $125 | $183 | $500 |
| 659E14000 REPAIR SEEDING AND MULCHING | 160 SY | $0.10 | $0.50 | $12.85 | $1.80 | $2.82 | $1.82 |
| 659E20000 COMMERCIAL FERTILIZER | 0.43 TON | $500 | $700 | $3,107 | $971 | $1,700 | $1,535 |
| 659E31000 LIME | 0.66 ACRE | $10.00 | $0.02 | $2,286 | $167 | $120 | $22.00 |
| 659E35000 WATER | 20 MGAL | $0.10 | $0.01 | $11.50 | $1.00 | $1.25 | $0.28 |
| 611E28000 84" CONDUIT, TYPE A, 707.02 | 10 FT | $500 | $1,640 | $422 | $800 | $1,141 | $1,318 |
| 614E12200 SPECIAL - WORK ZONE GUARDRAIL | 50 FT | $10.00 | $50.00 | $48.63 | $105 | $59.50 | $150 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $50.00 | $200 | $212 | $368 | $790 | $730 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE WAY) | 25 EACH | $30.00 | $40.00 | $30.17 | $9.00 | $44.00 | $18.70 |
| 614E13350 OBJECT MARKER, ONE WAY | 25 EACH | $30.00 | $40.00 | $30.17 | $17.00 | $44.00 | $9.90 |
| 616E10000 WATER | 10 MGAL | $0.10 | $0.01 | $11.50 | $92.00 | $1.25 | $52.50 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,000 | $16,469 | $4,025 | $10,000 | $3,652 | $11,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 837E10000 LINER PIPE, 66" ID 707.85 | 341 FT | $493.31 | $168k | 20% |
| 837E21000 BACKFILL FOR LINER PIPE | 806 FT | $150.71 | $121k | 14% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100,000 | $100k | 12% |
| 837E10000 LINER PIPE, 60" ID 707.33, 707.85 | 299 FT | $329.42 | $98k | 12% |
| 602E20000 CONCRETE MASONRY | 24.6 CY | $2,800 | $69k | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $65,000 | $65k | 8% |
| 837E10000 LINER PIPE, 54" ID 707.33, 707.85 | 166 FT | $258.35 | $43k | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $30,000 | $30k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 796 FT | $20 | $16k | 2% |