ATB-SR 534-12.06
ATB County · est $1.9M
Bid dateThursday, February 23—
ATB County · est $1.9M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 12 more items below.
| Item | Quantity | R1A P O'horo Company | R2Suburban Maintenance & Construction | R3Marucci & Gaffney Excavating CO | % of bid |
|---|---|---|---|---|---|
| 530E99020 SPECIAL - SUPERSTRUCTURE | 1 LS | $1,325,000 | $422,000 | $1,486,000 | 73% |
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $81,000 | $110,000 | $39,750 | 4% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $75,000 | $75,000 | $35,000 | 4% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $40,000 | $40,000 | $100,000 | 2% |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $38,847 | $30,000 | $35,000 | 2% |
| 606E99000 SPECIAL - GUARDRAIL | 1 LS | $35,000 | $40,000 | $45,000 | 2% |
| 512E99000 SPECIAL - SEALING OF CONCRETE | 1 LS |
| Item | Quantity | R1A P O'horo Company | R2Suburban Maintenance & Construction | R3Marucci & Gaffney Excavating CO |
|---|---|---|---|---|
| 201E99000 SPECIAL - CLEARING AND GRUBBING | 1 LS | $3,000 | $10,000 | $78,000 |
| 204E13000 EXCAVATION OF SUBGRADE | 14 CY | $25.00 | $30.00 | $10.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 14 CY | $80.00 | $55.00 | $90.00 |
| 204E50000 GEOTEXTILE FABRIC | 40 SY | $5.00 | $5.00 | $10.00 |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $3,000 | $10,000 | $5,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $30,000 |
| $6,000 |
| $22,500 |
| 2% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 150 SF | $176 | $25.00 | $150 | 1% |
| 530E99010 SPECIAL - SUBSTRUCTURE | 1 LS | $25,000 | $900,000 | $225,000 | 1% |
| 202E99020 SPECIAL - PAVEMENT REMOVED | 1 LS | $20,000 | $15,000 | $13,000 | 1% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $20,000 | $65,000 | $20,000 | 1% |
| 300E99000 SPECIAL - BASES | 1 LS | $17,000 | $20,000 | $68,150 | 1% |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | 1% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $12,000 | $20,000 | $25,000 | 1% |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $11,283 | $11,283 | $11,283 | 1% |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $10,000 | $25,000 | 1% |
| 203E99000 SPECIAL - EARTHWORK | 1 LS | $9,000 | $5,000 | $20,000 | 0% |
| 843E50000 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 50 SF | $176 | $25.00 | $150 | 0% |
| 619E16000 FIELD OFFICE, TYPE A | 6 MNTH | $1,000 | $1,400 | $500 | 0% |
| 690E20020 SPECIAL - FIELD SURVEYS | 1 LS | $5,000 | $20,000 | $20,000 | 0% |
| 1 LS |
| $3,000 |
| $2,000 |
| $3,000 |
| 640E99000 SPECIAL - PAVEMENT MARKING | 1 LS | $2,500 | $3,000 | $3,000 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $500 | $5,000 | $5,000 |
| 690E20030 SPECIAL - UTILITY COORDINATION AND RELOCATION | 1 LS | $5,000 | $5,000 | $10,000 |
| 690E20220 SPECIAL - CONSTRUCTION PLANS | 1 LS | $1,000 | $10,000 | $20,000 |
| 690E98000 SPECIAL - SULS LEVEL A TEST HOLE | 2 EACH | $1,000 | $3,500 | $2,000 |
| 100E99010 SPECIAL - PROFESSIONAL LIABILITY INSURANCE | 1 LS | $1,000 | $10,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 530E99020 SPECIAL - SUPERSTRUCTURE | 1 LS | $1,325,000 | $1.32M | 72% |
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $81,000 | $81k | 4% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $75,000 | $75k | 4% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $40,000 | $40k | 2% |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $38,847 | $39k | 2% |
| 606E99000 SPECIAL - GUARDRAIL | 1 LS | $35,000 | $35k | 2% |
| 512E99000 SPECIAL - SEALING OF CONCRETE | 1 LS | $30,000 | $30k | 2% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 150 SF | $176 | $26k | 1% |
| 530E99010 SPECIAL - SUBSTRUCTURE | 1 LS | $25,000 | $25k | 1% |
| 202E99020 SPECIAL - PAVEMENT REMOVED | 1 LS | $20,000 | $20k | 1% |