WAY-SR 21-00.00
WAY County · est $36M
Bid dateThursday, June 8—
WAY County · est $36M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 29 more items below.
| Item | Quantity | R1Kenmore Construction CO INC | R2Shelly & Sands INC | R3Shelly Company | % of bid |
|---|---|---|---|---|---|
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $10,940,873 | $11,000,000 | $5,730,751 | 37% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $3,318,505 | $4,200,000 | $3,518,309 | 11% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $2,244,965 | $100,000 | $34,884 | 8% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $2,128,748 | $2,600,000 | $4,900,080 | 7% |
| 300E99000 SPECIAL - BASES | 1 LS | $1,614,249 | $2,600,000 | $9,413,860 | 5% |
| 203E99000 SPECIAL - EARTHWORK | 1 LS | $1,128,824 | $4,500,000 | $999,743 | 4% |
| 202E99020 SPECIAL - PAVEMENT REMOVED | 1 LS | $927,670 |
| Item | Quantity | R1Kenmore Construction CO INC | R2Shelly & Sands INC | R3Shelly Company |
|---|---|---|---|---|
| 201E99000 SPECIAL - CLEARING AND GRUBBING | 1 LS | $25,000 | $200,000 | $100,000 |
| 690E98000 SPECIAL - SUL QUALITY LEVEL A TEST HOLES | 18 EACH | $2,778 | $3,000 | $1,725 |
| 450E99000 SPECIAL - RIGID PAVEMENT | 1 LS | $14,790 | $110,000 | $107,307 |
| 530E99050 SPECIAL - RETAINING WALL | 1 LS | $121,783 | $330,000 | $526,722 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 100 SF | $150 | $150 | $150 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1,400,000 |
| $1,782,438 |
| 3% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $910,000 | $670,000 | $840,000 | 3% |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $872,419 | $1,000,000 | $694,536 | 3% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $800,000 | $800,000 | $800,000 | 3% |
| 632E99000 SPECIAL - TRAFFIC SIGNALS | 1 LS | $654,855 | $850,000 | $632,539 | 2% |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 593,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 622E99000 SPECIAL - CONCRETE BARRIER | 1 LS | $584,773 | $726,000 | $1,544,230 | 2% |
| 625E99000 SPECIAL - LIGHTING | 1 LS | $582,262 | $560,000 | $440,007 | 2% |
| 606E99000 SPECIAL - GUARDRAIL | 1 LS | $518,932 | $720,000 | $471,584 | 2% |
| 614E18000 MAINTAINING TRAFFIC, MISC.:PAVEMENT REPAIRS | 500,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 615E99000 SPECIAL - TEMPORARY ROADS AND PAVEMENTS | 1 LS | $351,840 | $2,100,000 | $2,237,120 | 1% |
| 640E99000 SPECIAL - PAVEMENT MARKING | 1 LS | $351,287 | $450,000 | $379,340 | 1% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $344,000 | $390,000 | $275,000 | 1% |
| 630E99000 SPECIAL - SIGNS AND SUPPORTS | 1 LS | $258,197 | $100,000 | $167,166 | 1% |
| 1 LS |
| $9,456 |
| $9,000 |
| $9,540 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 10 FT | $150 | $150 | $200 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 100 SF | $150 | $150 | $150 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $9,444 | $9,000 | $9,540 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $15,300 | $14,500 | $15,330 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $15,276 | $14,500 | $15,330 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $20,400 | $18,000 | $20,778 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $20,616 | $18,000 | $14,754 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $14,328 | $12,000 | $14,754 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 15 SF | $250 | $250 | $150 |
| 530E99040 SPECIAL - STRUCTURES | 1 LS | $18,804 | $25,000 | $28,504 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $11,000 | $50,000 | $20,000 |
| 690E20020 SPECIAL - FIELD SURVEYS | 1 LS | $37,000 | $35,000 | $35,000 |
| 690E20030 SPECIAL - UTILITY COORDINATION AND RELOCATION | 1 LS | $5,000 | $95,000 | $17,000 |
| 690E20080 SPECIAL - SUBSURFACE INVESTIGATIONS | 1 LS | $24,000 | $50,000 | $162,000 |
| 690E20220 SPECIAL - CONSTRUCTION PLANS | 1 LS | $172,000 | $108,000 | $100,000 |
| 100E51200 DEPARTMENT'S SHARE OF THE DISPUTE RESOLUTION ADVIS | 120,000 EACH | $1.00 | $1.00 | $1.00 |
| 100E99000 SPECIAL - PREMIUM ON RAILROAD'S PROTECTIVE PUBLIC | 1 LS | $5,000 | $5,000 | $5,500 |
| 100E99010 SPECIAL - PROFESSIONAL LIABILITY INSURANCE | 1 LS | $5,000 | $1,000 | $5,000 |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $250,000 | $300,000 | $250,000 |
| 108E99000 SPECIAL - CPM PROGRESS SCHEDULE | 1 LS | $50,000 | $11,100 | $50,000 |
| 111E10100 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 10,000 EACH | $1.00 | $1.00 | $1.00 |
| 619E16020 FIELD OFFICE, TYPE C | 31 MNTH | $3,500 | $3,700 | $5,235 |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $50,000 | $500,000 | $410,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $10,940,873 | $10.9M | 35% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $3,318,505 | $3.32M | 11% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $2,244,965 | $2.24M | 7% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $2,128,748 | $2.13M | 7% |
| 300E99000 SPECIAL - BASES | 1 LS | $1,614,249 | $1.61M | 5% |
| 203E99000 SPECIAL - EARTHWORK | 1 LS | $1,128,824 | $1.13M | 4% |
| 202E99020 SPECIAL - PAVEMENT REMOVED | 1 LS | $927,670 | $928k | 3% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $910,000 | $910k | 3% |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $872,419 | $872k | 3% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $800,000 | $800k | 3% |