CLE-CLI Culverts FY24
CLE County · est $0.5M
Bid dateThursday, September 28—
CLE County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 38 more items below.
| Item | Quantity | R1Rack & Ballauer Excavating CO INC | R2Axis Civil Construction LLC | R3Djx Construction Company LLC | % of bid |
|---|---|---|---|---|---|
| 602E20000 CONCRETE MASONRY | 47 CY | $1,600 | $1,850 | $2,021 | 16% |
| 659E00300 TOPSOIL | 897 CY | $67.00 | $22.00 | $45.70 | 13% |
| 611E53200 48" X 76" CONDUIT, TYPE A, 706.04 | 79 FT | $750 | $1,650 | $1,267 | 13% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $40,000 | $84,143 | 7% |
| 203E20000 EMBANKMENT | 573 CY | $40.00 | $25.00 | $42.12 | 5% |
| 659E10000 SEEDING AND MULCHING | 8,083 SY | $2.80 | $1.35 | $2.43 | 5% |
| 614E12420 DETOUR SIGNING | 1 LS | $20,000 | $13,375 |
| Item | Quantity | R1Rack & Ballauer Excavating CO INC | R2Axis Civil Construction LLC | R3Djx Construction Company LLC |
|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 4 EACH | $750 | $2,000 | $1,270 |
| 202E23000 PAVEMENT REMOVED | 145 SY | $16.00 | $16.00 | $36.57 |
| 202E32800 CONCRETE SLOPE PROTECTION REMOVED | 18 SY | $20.00 | $80.00 | $64.93 |
| 202E35200 PIPE REMOVED, OVER 24" | 5 FT | $115 | $1,000 | $222 |
| 202E38000 GUARDRAIL REMOVED | 113 FT | $3.00 | $12.00 | $3.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $13,375 |
| 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $35,000 | $19,250 | 4% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 75" CMP | 135 FT | $145 | $135 | $228 | 4% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 6 EACH | $2,720 | $2,725 | $2,720 | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 19 CY | $760 | $800 | $19.00 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $14,000 | $20,000 | $23,614 | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 38 CY | $325 | $450 | $1,100 | 3% |
| 202E11004 STRUCTURE REMOVED | 2 EACH | $6,000 | $8,000 | $8,339 | 3% |
| 611E22200 54" CONDUIT, TYPE A, 707.02 ALUMINIZED, 706.02 | 38 FT | $300 | $850 | $905 | 2% |
| 611E98230 CATCH BASIN, NO. 4 (SAG) | 1 EACH | $11,000 | $8,000 | $14,209 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3" | 193 SY | $50.00 | $50.00 | $88.34 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 40.8 CY | $235 | $150 | $220 | 2% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 57 CY | $144 | $150 | $232 | 2% |
| 203E10000 EXCAVATION | 211 CY | $37.00 | $25.00 | $57.76 | 2% |
| 202E42001 ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER PLAN | 3 EACH | $295 | $450 | $295 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 1 EACH | $110 | $150 | $110 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $950 | $2,000 | $1,808 |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 29 FT | $55.00 | $40.00 | $239 |
| 202E75000 FENCE REMOVED | 100 FT | $5.50 | $8.00 | $10.83 |
| 204E10000 SUBGRADE COMPACTION | 158 SY | $16.00 | $4.00 | $9.32 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $500 | $10,000 | $36,939 |
| 606E15050 GUARDRAIL, TYPE MGS | 350 FT | $19.60 | $26.75 | $19.60 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 125 FT | $21.80 | $29.25 | $21.80 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,345 | $1,325 | $1,345 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 8 EACH | $300 | $250 | $405 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $2,500 | $9,500 | $3,000 |
| 202E35200 PIPE REMOVED, OVER 24" | 30 FT | $25.00 | $120 | $85.79 |
| 601E11000 RIPRAP, TYPE D | 24.1 SY | $200 | $200 | $234 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 3.9 CY | $215 | $150 | $903 |
| 659E20000 COMMERCIAL FERTILIZER | 1.09 TON | $1,100 | $1,500 | $1,500 |
| 659E31000 LIME | 1.67 ACRE | $200 | $200 | $200 |
| 659E35000 WATER | 43.6 MGAL | $65.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 |
| 611E20700 48" CONDUIT, TYPE A, 707.02 ALUMINIZED, 706.02 | 30 FT | $260 | $650 | $1,103 |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 74"x42" ARCH | 30 FT | $240 | $400 | $761 |
| 611E97700 CONDUIT, MISC.: ZINC RICH PAINT | 40 SF | $50.00 | $110 | $46.08 |
| 843E50000 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 16 SF | $125 | $300 | $372 |
| 304E20000 AGGREGATE BASE | 26 CY | $142 | $200 | $225 |
| 407E10000 TACK COAT | 49 GAL | $5.00 | $5.00 | $10.00 |
| 621E00100 RPM | 2 EACH | $1,800 | $820 | $820 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2 EACH | $35.00 | $50.00 | $6.51 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 16 EACH | $12.25 | $15.00 | $12.25 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.04 MILE | $37,750 | $70,515 | $70,515 |
| 642E00300 CENTER LINE, TYPE 1 | 0.02 MILE | $50,525 | $94,020 | $94,020 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $75.00 | $80.00 | $100 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $6,500 | $10,074 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $15,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 602E20000 CONCRETE MASONRY | 47 CY | $1,600 | $75k | 14% |
| 659E00300 TOPSOIL | 897 CY | $67 | $60k | 11% |
| 611E53200 48" X 76" CONDUIT, TYPE A, 706.04 | 79 FT | $750 | $59k | 11% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 5% |
| 203E20000 EMBANKMENT | 573 CY | $40 | $23k | 4% |
| 659E10000 SEEDING AND MULCHING | 8,083 SY | $2.8 | $23k | 4% |
| 614E12420 DETOUR SIGNING | 1 LS | $20,000 | $20k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $20k | 4% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 75" CMP | 135 FT | $145 | $20k | 4% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 6 EACH | $2,720 | $16k | 3% |