HUR-SR 103-02.04
HUR County · est $0.3M
Bid dateThursday, January 25—
HUR County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 7 more items below.
| Item | Quantity | R1Stanley Miller Construction Company | R2Bcc Ohio INC | R3Adena Corporation | R4Madex Construction CO | % of bid |
|---|---|---|---|---|---|---|
| 833E10000 CONDUIT RENEWAL USING SPRAY APPLIED STRUCTURAL LIN | 80 FT | $1,025 | $1,105 | $1,335 | $1,656 | 41% |
| 624E10000 MOBILIZATION | 1 LS | $22,000 | $3,871 | $13,465 | $24,621 | 11% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,000 | $2,768 | $2,935 | $7,526 | 6% |
| 203E20000 EMBANKMENT | 109 CY | $100 | $47.87 | $26.56 | $52.66 | 5% |
| 602E20000 CONCRETE MASONRY | 6.6 CY | $1,500 | $5,178 | $4,022 | $4,540 | 5% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 70 CY | $125 | $179 | $155 | $155 |
| Item | Quantity | R1Stanley Miller Construction Company | R2Bcc Ohio INC | R3Adena Corporation | R4Madex Construction CO |
|---|---|---|---|---|---|
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $118 | $200 | $226 |
| 659E14000 REPAIR SEEDING AND MULCHING | 20 SY | $3.00 | $2.10 | $1.00 | $11.45 |
| 659E15000 INTER-SEEDING | 20 SY | $1.00 | $0.26 | $1.00 | $11.45 |
| 659E20000 COMMERCIAL FERTILIZER | 0.05 TON | $800 | $2,048 | $1,467 | $7,526 |
| 659E31000 LIME | 0.08 ACRE |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,500 | $2,625 | $2,861 | $3,242 | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $7,200 | $26,108 | $29,021 | $25,662 | 4% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 37 CY | $185 | $214 | $145 | $164 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,610 | $693 | $10,131 | $1,659 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,200 | $17,784 | $4,730 | $8,395 | 3% |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $4,400 | $2,048 | $4,292 | $4,377 | 2% |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $4,400 | $2,048 | $4,292 | $4,377 | 2% |
| 832E30000 EROSION CONTROL | 2,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 203E10000 EXCAVATION | 29 CY | $77.00 | $28.88 | $49.92 | $70.18 | 1% |
| 659E00300 TOPSOIL | 43 CY | $39.00 | $92.81 | $59.49 | $79.11 | 1% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 80 FT | $20.00 | $69.30 | $72.39 | $39.41 | 1% |
| 659E10000 SEEDING AND MULCHING | 390 SY | $3.50 | $6.14 | $4.49 | $3.87 | 1% |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 34 FT | $38.00 | $16.99 | $25.93 | $62.27 | 1% |
| 670E00520 SLOPE EROSION PROTECTION MAT, TYPE B | 240 SY | $5.00 | $3.62 | $3.03 | $8.00 | 1% |
| $150 |
| $99.75 |
| $306 |
| $2,822 |
| 659E35000 WATER | 2.16 MGAL | $1.00 | $2.63 | $1.00 | $34.84 |
| 611E97400 CONDUIT, MISC.: VIDEO LOG | 80 FT | $3.00 | $11.16 | $9.04 | $19.66 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 833E10000 CONDUIT RENEWAL USING SPRAY APPLIED STRUCTURAL LIN | 80 FT | $1,025 | $82k | 41% |
| 624E10000 MOBILIZATION | 1 LS | $22,000 | $22k | 11% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,000 | $12k | 6% |
| 203E20000 EMBANKMENT | 109 CY | $100 | $11k | 5% |
| 602E20000 CONCRETE MASONRY | 6.6 CY | $1,500 | $10k | 5% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 70 CY | $125 | $9k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,500 | $8k | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $7,200 | $7k | 4% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 37 CY | $185 | $7k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,610 | $6k | 3% |