D11-DS-FY2024
D11 County · est $0.3M
Bid dateThursday, February 8—
D11 County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 2 more items below.
| Item | Quantity | R1Catts Construction INC | R2Becdir Construction Company | R3Marucci & Gaffney Excavating CO | R4Aad Contracting INC | R5Ram Construction Services Of Michigan, | R6INC Athos Contracting | % of bid |
|---|---|---|---|---|---|---|---|---|
| 512E10300 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN | 8,560 SY | $12.00 | $15.10 | $12.90 | $16.00 | $17.55 | $15.00 | 51% |
| 512E74500 REMOVAL OF EXISTING PAVEMENT MARKING | 6,475 FT | $5.75 | $2.00 | $2.78 | $4.60 | $0.83 | $4.60 | 18% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $21,000 | $48,500 |
| Item | Quantity | R1Catts Construction INC | R2Becdir Construction Company | R3Marucci & Gaffney Excavating CO | R4Aad Contracting INC | R5Ram Construction Services Of Michigan, | R6INC Athos Contracting |
|---|---|---|---|---|---|---|---|
| 646E20300 LANE ARROW | 4 EACH | $2.00 | $185 | $175 | $175 | $250 | $175 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 122 FT | $1.00 | $0.55 | $0.50 | $0.50 | $0.50 | $0.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $65,000 |
| $30,000 |
| $42,815 |
| $30,000 |
| 10% |
| 624E10000 MOBILIZATION | 1 LS | $18,000 | $19,000 | $20,000 | $8,000 | $20,664 | $30,000 | 9% |
| 646E10010 EDGE LINE, 6" | 0.78 MILE | $6,173 | $5,250 | $5,000 | $5,000 | $25,000 | $5,000 | 2% |
| 690E98100 SPECIAL - DEBRIS REMOVAL | 4,065 FT | $1.00 | $0.75 | $2.00 | $5.00 | $0.50 | $30.00 | 2% |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 350 FT | $7.50 | $6.50 | $6.00 | $6.00 | $25.00 | $6.00 | 1% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.88 MILE | $2,963 | $2,500 | $2,400 | $2,400 | $2,640 | $2,400 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,500 | $5,000 | $2,500 | $4,000 | $2,500 | $10,000 | 1% |
| 646E10510 CROSSWALK LINE, 12" | 325 FT | $4.00 | $3.75 | $3.50 | $3.50 | $15.00 | $3.50 | 1% |
| 646E10110 LANE LINE, 6" | 0.21 MILE | $5,926 | $5,100 | $4,800 | $4,800 | $10,000 | $4,800 | 1% |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 0% |
| 646E10400 STOP LINE | 55 FT | $15.00 | $13.00 | $12.00 | $12.00 | $25.00 | $12.00 | 0% |
| 646E10200 CENTER LINE | 0.1 MILE | $6,420 | $5,500 | $5,200 | $5,200 | $27,500 | $5,200 | 0% |
| 807E12010 WET REFLECTIVE EPOXY PAVEMENT MARKING, EDGE LINE, | 0.1 MILE | $6,173 | $5,250 | $5,000 | $5,000 | $25,000 | $5,000 | 0% |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 0.25 MILE | $2,346 | $2,000 | $1,900 | $1,900 | $2,640 | $1,900 | 0% |
| 646E20320 WRONG WAY ARROW | 2 EACH | $246 | $210 | $200 | $200 | $425 | $200 | 0% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.1 MILE | $3,200 | $2,700 | $2,600 | $2,600 | $2,640 | $2,600 | 0% |
| 646E10310 CHANNELIZING LINE, 12" | 122 FT | $2.00 | $1.80 | $1.70 | $1.70 | $5.00 | $1.70 | 0% |
| 807E12110 WET REFLECTIVE EPOXY PAVEMENT MARKING, LANE LINE, | 0.05 MILE | $3,704 | $3,150 | $3,000 | $3,000 | $10,000 | $3,000 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 512E10300 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN | 8,560 SY | $12 | $103k | 51% |
| 512E74500 REMOVAL OF EXISTING PAVEMENT MARKING | 6,475 FT | $5.75 | $37k | 18% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $21,000 | $21k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $18,000 | $18k | 9% |
| 646E10010 EDGE LINE, 6" | 0.78 MILE | $6,173 | $5k | 2% |
| 690E98100 SPECIAL - DEBRIS REMOVAL | 4,065 FT | $1 | $4k | 2% |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 350 FT | $7.5 | $3k | 1% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.88 MILE | $2,963 | $3k | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,500 | $3k | 1% |
| 646E10510 CROSSWALK LINE, 12" | 325 FT | $4 | $1k | 1% |