TUS-SR 800-28.44
TUS County · est $2.4M
Bid dateThursday, March 21—
TUS County · est $2.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 74 more items below.
| Item | Quantity | R1Complete General Construction Company | R2Perk Company INC | R3Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|
| 517E70001 RAILING (TWIN STEEL TUBE), AS PER PLAN | 667 FT | $385 | $376 | $352 | 12% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $250,000 | $240,000 | $480,000 | 12% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 22,365 SF | $9.00 | $9.00 | $9.20 | 9% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,609 SY | $95.00 | $90.40 | $70.00 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $132,000 | $52,800 | $100,000 | 6% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 95 CY | $1,200 | $2,195 | $3,000 | 5% |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR |
| Item | Quantity | R1Complete General Construction Company | R2Perk Company INC | R3Shelly & Sands INC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $10,000 | $7,000 |
| 202E23000 PAVEMENT REMOVED | 247 SY | $50.00 | $47.80 | $15.00 |
| 202E38000 GUARDRAIL REMOVED | 212.5 FT | $2.00 | $20.10 | $2.50 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $75.00 | $625 | $120 |
| 203E10000 EXCAVATION | 100 CY | $60.00 | $51.75 | $54.00 |
| 203E20000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1,609 SY |
| $70.00 |
| $93.00 |
| $105 |
| 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 22,365 SF | $5.00 | $5.00 | $5.10 | 5% |
| 526E25011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 252 SY | $425 | $420 | $425 | 5% |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 8,973 LB | $10.00 | $11.15 | $11.00 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 22,365 SF | $4.00 | $4.00 | $4.10 | 4% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $85,000 | $28,500 | $80,000 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $80,000 | $115,000 | $55,000 | 4% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 48 CY | $1,500 | $1,640 | $2,000 | 3% |
| 516E11210 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 104 FT | $650 | $1,115 | $702 | 3% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 22,365 SF | $3.00 | $2.00 | $3.10 | 3% |
| 513E95000 STRUCTURAL STEEL, MISC.: GIRDER REPAIR, COMPLETE P | 57 FT | $1,100 | $1,006 | $1,006 | 3% |
| 516E46200 BEARING DEVICE, ROCKER (R-100) | 12 EACH | $3,000 | $2,375 | $2,600 | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,312 FT | $25.00 | $36.00 | $18.00 | 2% |
| 526E90010 TYPE A INSTALLATION | 105 FT | $300 | $395 | $235 | 1% |
| 20 CY |
| $50.00 |
| $215 |
| $14.00 |
| 204E10000 SUBGRADE COMPACTION | 544 SY | $9.00 | $1.80 | $8.50 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 212.5 FT | $22.40 | $22.40 | $22.00 |
| 606E32160 BRIDGE TERMINAL ASSEMBLY, TYPE TST | 4 EACH | $1,960 | $1,960 | $2,200 |
| 690E98400 SPECIAL - WORK INVOLVING ASBESTOS CONTAINING MATER | 1 LS | $750 | $1,000 | $500 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $250 | $150 |
| 659E00300 TOPSOIL | 14 CY | $50.00 | $100 | $100 |
| 659E10000 SEEDING AND MULCHING | 125 SY | $20.00 | $10.00 | $25.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 7 SY | $25.00 | $10.00 | $25.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.02 TON | $1,400 | $1,000 | $1,400 |
| 659E31000 LIME | 0.03 ACRE | $150 | $1,000 | $150 |
| 659E35000 WATER | 1 MGAL | $1.00 | $100 | $1.00 |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 29 CY | $455 | $650 | $455 |
| 304E20000 AGGREGATE BASE | 91 CY | $95.00 | $88.00 | $120 |
| 407E10000 TACK COAT | 43 GAL | $5.00 | $10.00 | $5.00 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 9 CY | $1,270 | $850 | $1,270 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (12 CY | $1,120 | $750 | $1,120 |
| 621E00100 RPM | 8 EACH | $380 | $470 | $380 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 8 EACH | $30.00 | $250 | $26.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 8 EACH | $11.00 | $14.65 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 54 FT | $25.00 | $42.70 | $15.00 |
| 630E80100 SIGN, FLAT SHEET | 12 SF | $30.00 | $46.55 | $20.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4 EACH | $10.00 | $16.15 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $10.00 | $21.50 | $20.00 |
| 642E01650 BIKE LANE ARROW, TYPE 1 | 2 EACH | $200 | $200 | $245 |
| 646E10010 EDGE LINE, 6" | 0.32 MILE | $12,000 | $12,000 | $27,500 |
| 646E10200 CENTER LINE | 0.08 MILE | $12,500 | $15,000 | $27,500 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 68 FT | $8.00 | $8.00 | $15.00 |
| 646E20600 BIKE LANE SYMBOL MARKING | 2 EACH | $75.00 | $75.00 | $245 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $85.00 | $100 | $100 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,240 | $2,325 | $2,250 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 27 EACH | $28.00 | $12.50 | $8.00 |
| 614E13312 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 27 EACH | $34.00 | $14.35 | $8.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 54 EACH | $30.00 | $21.70 | $15.00 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.08 MILE | $10,750 | $5,160 | $10,750 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.16 MILE | $14,650 | $12,750 | $14,650 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.32 MILE | $3,450 | $3,750 | $3,450 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 1.02 MILE | $9,950 | $9,090 | $9,950 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 26 FT | $14.00 | $5.70 | $14.00 |
| 616E10000 WATER | 5 MGAL | $100 | $200 | $70.00 |
| 202E22900 APPROACH SLAB REMOVED | 245 SY | $95.00 | $51.60 | $40.00 |
| 202E23500 WEARING COURSE REMOVED | 1,867 SY | $15.00 | $26.30 | $14.00 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $25,000 | $44,650 | $46,001 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 14,124 LB | $2.00 | $1.95 | $2.05 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 250 LB | $2.00 | $1.95 | $2.14 |
| 511E81300 CONCRETE, MISC.: EMBEDDED GALVANIC ANODES (EGA) | 388 EACH | $75.00 | $165 | $50.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 463 SY | $38.50 | $45.00 | $35.00 |
| 512E33000 TYPE 2 WATERPROOFING | 3 SY | $325 | $365 | $115 |
| 513E21000 TRIMMING OF BEAM END | 10 EACH | $420 | $420 | $420 |
| 513E95000 STRUCTURAL STEEL, MISC.: GIRDER REPAIR, FIELD FILL | 152 FT | $150 | $125 | $126 |
| 513E95000 STRUCTURAL STEEL, MISC.: GRINDING PER FOOT | 57 FT | $175 | $158 | $158 |
| 513E95030 STRUCTURAL STEEL, MISC.: GIRDER REPAIR, COPE HOLES | 13 EACH | $460 | $460 | $460 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 33 MNHR | $150 | $150 | $154 |
| 514E10000 FINAL INSPECTION REPAIR | 10 EACH | $200 | $200 | $205 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 92 CY | $175 | $205 | $155 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 160 FT | $15.00 | $28.00 | $8.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 40 FT | $20.00 | $28.00 | $16.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 11 SF | $500 | $560 | $500 |
| 601E20001 CRUSHED AGGREGATE SLOPE PROTECTION, AS PER PLAN | 308 SY | $28.00 | $87.00 | $110 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $10,000 | $10,000 | $22,000 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 44 CF | $576 | $600 | $750 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 45 CY | $250 | $250 | $245 |
| 848E50000 HAND CHIPPING | 17 SY | $100 | $750 | $135 |
| 848E50100 TEST SLAB | 1 LS | $500 | $2,500 | $2,350 |
| 848E50200 FULL-DEPTH REPAIR | 18 CY | $250 | $3,350 | $1,500 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $27,500 | $35,000 | $16,500 |
| 619E16000 FIELD OFFICE, TYPE A | 8 MNTH | $1,500 | $3,275 | $4,900 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,000 | $30,000 | $8,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 517E70001 RAILING (TWIN STEEL TUBE), AS PER PLAN | 667 FT | $385 | $257k | 10% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $250,000 | $250k | 9% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 22,365 SF | $9 | $201k | 8% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 1,609 SY | $95 | $153k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $132,000 | $132k | 5% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 95 CY | $1,200 | $114k | 4% |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 1,609 SY | $70 | $113k | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 22,365 SF | $5 | $112k | 4% |
| 526E25011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 252 SY | $425 | $107k | 4% |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 8,973 LB | $10 | $90k | 3% |