GEA-West Woods Road Replace
GEA County · est $0.7M
Bid dateThursday, April 4—
GEA County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Eclipse CO LLC | R2Digioia-suburban Excavating LLC | R3Union Industrial Contractors INC | % of bid |
|---|---|---|---|---|---|
| 611E70001 CONDUIT, TYPE A, PRECAST REINFORCED CONCRETE THREE | 52 FT | $2,556 | $1,850 | $2,800 | 19% |
| 507E00700 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 1,210 FT | $91.00 | $125 | $75.00 | 16% |
| 507E00750 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 1,320 FT | $72.00 | $75.00 | $110 | 14% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 81 CY | $846 | $1,325 | $850 | 10% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $35,000 | $5,500 | $20,000 | 5% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 10 CY | $3,101 | $3,900 | $2,200 | 4% |
| 202E11000 STRUCTURE REMOVED | 1 LS |
| Item | Quantity | R1Eclipse CO LLC | R2Digioia-suburban Excavating LLC | R3Union Industrial Contractors INC |
|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 63 SY | $11.00 | $25.00 | $66.00 |
| 203E10000 EXCAVATION | 67 CY | $42.00 | $15.00 | $40.00 |
| 204E10000 SUBGRADE COMPACTION | 193 SY | $1.00 | $4.00 | $4.00 |
| 601E20001 CRUSHED AGGREGATE SLOPE PROTECTION, AS PER PLAN | 53 SY | $93.00 | $50.00 | $60.00 |
| 606E98000 GUARDRAIL, MISC.: STEEL-BACKED TIMBER GUARDRAIL, T | 60 FT | $139 | $150 | $139 |
| 659E00300 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $30,000 |
| $38,500 |
| $92,000 |
| 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $29,000 | $18,500 | $25,000 | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 6,981 LB | $4.00 | $1.25 | $3.50 | 4% |
| 203E20000 EMBANKMENT | 601 CY | $36.00 | $40.00 | $120 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $18,125 | $43,000 | $20,000 | 3% |
| 530E00200 SPECIAL - STRUCTURESTEMPORARY BRIDLE TRAIL BRIDGE | 1 LS | $15,332 | $12,500 | $15,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $5,500 | $10,000 | 2% |
| 523E20000 DYNAMIC LOAD TESTING | 1 EACH | $11,750 | $5,200 | $2,500 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $8,500 | $1,000 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $13,500 | $7,500 | 1% |
| 607E98000 FENCE, MISC.: TIMBER RAILING | 71 FT | $135 | $140 | $130 | 1% |
| 606E98100 GUARDRAIL, MISC.: STEEL-BACKED TIMBER GUARDRAIL TE | 2 EACH | $4,550 | $4,900 | $4,445 | 1% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 17 CY | $525 | $655 | $525 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,430 | $6,500 | $7,500 | 1% |
| 12 CY |
| $113 |
| $100 |
| $220 |
| 659E10000 SEEDING AND MULCHING | 112 SY | $21.50 | $25.00 | $8.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 6 SY | $7.00 | $40.00 | $10.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.02 TON | $999 | $850 | $1,500 |
| 659E31000 LIME | 0.02 ACRE | $21.00 | $3,000 | $1.00 |
| 659E35000 WATER | 0.6 MGAL | $1.00 | $20.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,500 EACH | $1.00 | $1.00 | $1.00 |
| 304E20000 AGGREGATE BASE | 32 CY | $109 | $85.00 | $135 |
| 407E10000 TACK COAT | 8 GAL | $5.00 | $7.00 | $5.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 5 CY | $685 | $860 | $685 |
| 643E00100 EDGE LINE, 4" | 0.04 MILE | $95,750 | $27,000 | $95,672 |
| 643E00300 CENTER LINE | 0.02 MILE | $95,750 | $27,000 | $96,408 |
| 503E21100 UNCLASSIFIED EXCAVATION | 128 CY | $51.00 | $50.00 | $81.00 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 3 CY | $2,122 | $2,650 | $2,050 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 81 SY | $21.00 | $35.00 | $80.00 |
| 512E33000 TYPE 2 WATERPROOFING | 203 SY | $25.00 | $30.00 | $30.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 34 SF | $8.00 | $6.00 | $25.00 |
| 518E21201 POROUS BACKFILL WITH GEOTEXTILE FABRIC, AS PER PLA | 15 CY | $98.00 | $75.00 | $350 |
| 518E40012 6" NON-PERFORATED CORRUGATED PLASTIC PIPE | 10 FT | $11.00 | $25.00 | $50.00 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 34 CY | $185 | $150 | $220 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $6,835 | $10,500 | $2,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E70001 CONDUIT, TYPE A, PRECAST REINFORCED CONCRETE THREE | 52 FT | $2,556 | $133k | 17% |
| 507E00700 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 1,210 FT | $91 | $110k | 14% |
| 507E00750 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 1,320 FT | $72 | $95k | 12% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 81 CY | $846 | $69k | 9% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $35,000 | $35k | 5% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 10 CY | $3,101 | $31k | 4% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $30,000 | $30k | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $29,000 | $29k | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 6,981 LB | $4 | $28k | 4% |
| 203E20000 EMBANKMENT | 601 CY | $36 | $22k | 3% |