HAM-CR 101-13.63
HAM County · est $1.1M
Bid dateThursday, April 4—
HAM County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 73 more items below.
| Item | Quantity | R1Barrett Paving Materials INC | R2John R Jurgensen Company | R3Eagle Bridge CO | R4Prus Construction Company | R5Sunesis Construction CO | R6Ford Development CORP | % of bid |
|---|---|---|---|---|---|---|---|---|
| 638E98100 WATER WORK, MISC.: GCWW RELOCATION | 1 LS | $93,000 | $69,746 | $100,000 | $80,000 | $110,206 | $80,000 | 12% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 1,048 CY | $74.00 | $62.33 | $80.00 | $82.50 | $106 | $100 | 10% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 315 CY | $228 | $230 | $228 |
| Item | Quantity | R1Barrett Paving Materials INC | R2John R Jurgensen Company | R3Eagle Bridge CO | R4Prus Construction Company | R5Sunesis Construction CO | R6Ford Development CORP |
|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $75.00 | $589 | $150 | $1,250 | $300 | $250 |
| 202E23000 PAVEMENT REMOVED | 2,412 SY | $8.00 | $6.90 | $11.00 | $17.50 | $16.02 | $20.00 |
| 202E32000 CURB REMOVED | 18 FT | $10.00 | $11.40 | $11.00 | $35.50 | $15.18 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $255 |
| $174 |
| $295 |
| 10% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $51,000 | $23,000 | $70,130 | $40,000 | 5% |
| 611E10600 24" CONDUIT, TYPE C | 246 FT | $160 | $186 | $125 | $108 | $179 | $215 | 5% |
| 204E13000 EXCAVATION OF SUBGRADE, 14" DEEP | 1,048 CY | $36.00 | $43.37 | $32.00 | $40.00 | $71.42 | $50.00 | 5% |
| 304E20000 AGGREGATE BASE | 424 CY | $88.00 | $85.96 | $95.00 | $105 | $121 | $100 | 5% |
| 611E98180 CATCH BASIN, NO. 3A | 10 EACH | $3,500 | $2,533 | $3,500 | $4,300 | $3,360 | $4,000 | 5% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (85 CY | $400 | $340 | $400 | $265 | $212 | $500 | 5% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 1,075 FT | $29.50 | $35.00 | $38.00 | $42.00 | $39.30 | $70.00 | 4% |
| 611E05900 15" CONDUIT, TYPE B | 259 FT | $120 | $135 | $115 | $127 | $134 | $204 | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 67 CY | $460 | $400 | $460 | $350 | $281 | $550 | 4% |
| 451E14011 9" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, AS P | 233 SY | $125 | $257 | $136 | $175 | $156 | $205 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,950 | $19,176 | $5,500 | $15,000 | $24,343 | $10,000 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,000 | $14,754 | $35,000 | $25,000 | $25,339 | $30,000 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $25,000 | $7,989 | $22,500 | $42,000 | $14,600 | $15,000 | 3% |
| 611E04600 12" CONDUIT, TYPE C | 216 FT | $110 | $116 | $100 | $88.00 | $111 | $190 | 3% |
| 611E06100 15" CONDUIT, TYPE C | 174 FT | $115 | $141 | $105 | $88.00 | $108 | $193 | 3% |
| 611E99574 MANHOLE, NO. 3 | 5 EACH | $4,000 | $3,773 | $4,000 | $5,400 | $4,264 | $6,000 | 3% |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $2,500 | $2,728 | $2,500 | $2,500 | $1,291 | $1,000 | 3% |
| $5.00 |
| 202E32500 CURB AND GUTTER REMOVED | 391 FT | $15.00 | $5.25 | $5.00 | $17.00 | $7.57 | $6.00 |
| 202E34900 PIPE REMOVED, 24" AND UNDER | 293 FT | $15.00 | $39.29 | $35.00 | $12.50 | $20.93 | $10.00 |
| 202E58000 MANHOLE REMOVED | 1 EACH | $500 | $1,136 | $250 | $1,700 | $740 | $750 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $400 | $1,136 | $250 | $725 | $534 | $500 |
| 203E10000 EXCAVATION | 359 CY | $42.00 | $40.17 | $40.00 | $42.50 | $53.26 | $50.00 |
| 203E20000 EMBANKMENT | 170 CY | $34.00 | $30.16 | $55.00 | $37.00 | $25.31 | $50.00 |
| 204E10000 SUBGRADE COMPACTION | 2,696 SY | $5.00 | $3.53 | $4.00 | $2.00 | $5.54 | $1.50 |
| 204E45000 PROOF ROLLING | 2 HOUR | $900 | $239 | $150 | $140 | $228 | $100 |
| 204E50000 GEOTEXTILE FABRIC | 2,696 SY | $2.50 | $2.86 | $1.50 | $2.75 | $1.10 | $4.00 |
| 608E13000 6" CONCRETE WALK | 1,428 SF | $7.00 | $9.02 | $10.00 | $13.50 | $10.11 | $20.00 |
| 608E52000 CURB RAMP | 275 SF | $17.50 | $23.00 | $22.00 | $31.00 | $22.04 | $25.00 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 7 EACH | $1,000 | $1,325 | $2,000 | $1,550 | $1,707 | $1,250 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 1 EACH | $1,000 | $573 | $500 | $750 | $1,305 | $1,500 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 2 EACH | $250 | $579 | $200 | $750 | $150 | $150 |
| 690E98400 SPECIAL - CONSULTANT FOR CONCRETE QUALITY CONTROL | 1 LS | $5,500 | $15,680 | $13,000 | $6,000 | $3,750 | $15,000 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $10,200 | $28,133 | $22,500 | $22,000 | $5,440 | $10,000 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER, 18" | 8 CY | $200 | $513 | $165 | $500 | $404 | $100 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $150 | $350 | $165 | $150 | $25.00 |
| 659E00300 TOPSOIL | 124 CY | $65.00 | $4.13 | $55.00 | $70.00 | $153 | $80.00 |
| 659E10000 SEEDING AND MULCHING | 1,116 SY | $1.25 | $2.75 | $4.00 | $3.00 | $5.77 | $5.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 56 SY | $2.00 | $1.00 | $2.50 | $1.50 | $2.00 | $5.00 |
| 659E15000 INTER-SEEDING | 56 SY | $2.00 | $1.00 | $2.50 | $1.50 | $2.00 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.16 TON | $1,400 | $2,500 | $1,750 | $2,750 | $1,400 | $50.00 |
| 659E31000 LIME | 0.23 ACRE | $450 | $250 | $1.00 | $275 | $450 | $100 |
| 659E35000 WATER | 6 MGAL | $1.00 | $50.00 | $10.00 | $55.00 | $1.00 | $100 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,000 | $1,925 | $2,500 | $2,500 | $1,925 | $2,250 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $5,500 | $3,160 | $10,000 | $4,000 | $5,400 | $1,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $9,446 | $9,445 | $10,000 | $10,500 | $9,445 | $9,500 |
| 832E30000 EROSION CONTROL | 12,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 42 SY | $3.25 | $5.00 | $9.00 | $5.50 | $3.25 | $6.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 104 FT | $17.00 | $38.30 | $20.00 | $44.00 | $23.00 | $20.00 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 858 FT | $15.00 | $29.66 | $20.00 | $22.50 | $17.25 | $20.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 184 FT | $30.00 | $52.05 | $20.00 | $73.25 | $41.74 | $25.00 |
| 611E04400 12" CONDUIT, TYPE B | 25 FT | $110 | $135 | $110 | $175 | $136 | $200 |
| 611E07400 18" CONDUIT, TYPE B | 97 FT | $135 | $162 | $125 | $140 | $150 | $210 |
| 611E07600 18" CONDUIT, TYPE C | 85 FT | $170 | $175 | $120 | $122 | $146 | $198 |
| 611E10400 24" CONDUIT, TYPE B | 55 FT | $180 | $187 | $150 | $220 | $206 | $225 |
| 611E98150 CATCH BASIN, NO. 3 | 2 EACH | $5,500 | $3,372 | $4,500 | $5,800 | $5,619 | $4,500 |
| 611E98300 CATCH BASIN, NO. 5 | 1 EACH | $4,500 | $5,246 | $6,500 | $4,800 | $4,679 | $5,500 |
| 611E98410 CATCH BASIN, NO. 8 | 1 EACH | $5,000 | $7,273 | $3,500 | $4,900 | $5,039 | $5,000 |
| 611E98470 CATCH BASIN, NO. 2-2B | 5 EACH | $1,500 | $1,900 | $2,000 | $3,500 | $2,128 | $2,500 |
| 407E20000 NON-TRACKING TACK COAT | 201 GAL | $3.00 | $10.00 | $3.00 | $8.00 | $3.50 | $10.00 |
| 451E11011 7" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, AS P | 54 SY | $130 | $202 | $140 | $245 | $139 | $200 |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 68 SY | $84.00 | $96.63 | $92.00 | $135 | $95.72 | $190 |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 45 SY | $100 | $107 | $113 | $155 | $109 | $195 |
| 609E10000 ASPHALT CONCRETE CURB, TYPE 1 | 9 FT | $200 | $85.00 | $75.00 | $75.00 | $300 | $40.00 |
| 609E22001 CURB, TYPE 3-B, AS PER PLAN | 322 FT | $23.50 | $35.50 | $31.00 | $48.00 | $39.57 | $75.00 |
| 609E26000 CURB, TYPE 6 | 164 FT | $26.50 | $28.00 | $31.00 | $46.00 | $40.98 | $75.00 |
| 609E31001 COMBINATION CURB AND GUTTER, TYPE 9, AS PER PLAN | 162 FT | $25.00 | $38.00 | $30.00 | $65.00 | $42.57 | $75.00 |
| 609E98100 CURB, MISC.: COMBINATION CURB AND GUTTER TURNOUT | 1 EACH | $22.85 | $903 | $500 | $2,000 | $1,310 | $1,000 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 1 EACH | $1,250 | $6,029 | $2,225 | $6,000 | $1,013 | $1,000 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 187.5 FT | $15.50 | $15.50 | $15.50 | $17.00 | $15.50 | $16.00 |
| 630E08600 SIGN POST REFLECTOR | 4 EACH | $55.00 | $55.00 | $55.00 | $60.00 | $55.00 | $60.00 |
| 630E80100 SIGN, FLAT SHEET | 102.35 SF | $16.00 | $16.00 | $16.00 | $18.00 | $16.00 | $17.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 12 EACH | $15.00 | $15.00 | $15.00 | $17.00 | $15.00 | $16.50 |
| 630E85000 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE | 1 EACH | $45.00 | $45.00 | $45.00 | $50.00 | $45.00 | $49.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $45.00 | $45.00 | $45.00 | $50.00 | $45.00 | $49.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $20.00 | $20.00 | $20.00 | $22.00 | $20.00 | $22.00 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 3 EACH | $15.00 | $15.00 | $15.00 | $17.00 | $15.00 | $17.00 |
| 644E00100 EDGE LINE, 4", WHITE | 0.04 MILE | $8,125 | $9,985 | $8,125 | $11,000 | $9,550 | $10,505 |
| 644E00100 EDGE LINE, 4", YELLOW | 0.1 MILE | $8,125 | $9,555 | $8,125 | $11,000 | $9,550 | $10,505 |
| 644E00300 CENTER LINE | 0.11 MILE | $12,495 | $17,600 | $12,495 | $20,900 | $19,000 | $20,900 |
| 644E00630 CROSSWALK LINE, 24" | 60 FT | $12.50 | $15.00 | $12.50 | $24.50 | $22.00 | $24.00 |
| 644E01520 DOTTED LINE, 12" | 97 FT | $6.25 | $3.00 | $6.25 | $5.00 | $4.35 | $5.00 |
| 644E20800 YIELD LINE | 57 FT | $18.75 | $20.00 | $18.75 | $28.00 | $25.00 | $27.00 |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 1 EACH | $4,000 | $2,500 | $2,500 | $2,750 | $5,825 | $15,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 32 HOUR | $80.00 | $98.61 | $100 | $100 | $68.65 | $50.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $10,995 | $9,485 | $15,000 | $12,000 | $10,995 | $12,000 |
| 616E10000 WATER | 2 MGAL | $50.00 | $155 | $25.00 | $75.00 | $14.18 | $100 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,995 | $7,663 | $10,000 | $15,000 | $7,233 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 638E98100 WATER WORK, MISC.: GCWW RELOCATION | 1 LS | $93,000 | $93k | 9% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 1,048 CY | $74 | $78k | 7% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 315 CY | $228 | $72k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 611E10600 24" CONDUIT, TYPE C | 246 FT | $160 | $39k | 4% |
| 204E13000 EXCAVATION OF SUBGRADE, 14" DEEP | 1,048 CY | $36 | $38k | 4% |
| 304E20000 AGGREGATE BASE | 424 CY | $88 | $37k | 4% |
| 611E98180 CATCH BASIN, NO. 3A | 10 EACH | $3,500 | $35k | 3% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (85 CY | $400 | $34k | 3% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 1,075 FT | $29.5 | $32k | 3% |