LOR-SR 611-00.01
LOR County · est $4.0M
Bid dateThursday, May 9—
LOR County · est $4.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 94 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Karvo Companies INC | % of bid |
|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 4,660 CY | $225 | $235 | 27% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)(TRANSVERSE) | 1,632 CY | $400 | $575 | 17% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $449,841 | $392,178 | 12% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(1.5") | 111,841 SY | $2.35 | $3.00 | 7% |
| 452E12011 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 2,950 SY | $87.00 | $85.00 | 7% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)(LONGITUDINAL) | 700 CY | $330 | $300 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $210,000 | $295,000 | 5% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 103 EACH | $1,540 | $2,200 | 4% |
| 253E02000 PAVEMENT REPAIR(FULL DEPTH FLEXIBLE) (TRANSVERSE) | 163 CY | $700 | $550 | 3% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 91 EACH | $715 | $1,425 | 2% |
| 253E02000 PAVEMENT REPAIR(FULL DEPTH FLEXIBLE) (LONGITUDINAL | 70 CY | $700 | $500 | 1% |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 47 EACH | $965 | $1,475 | 1% |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 15 EACH | $2,985 | $4,750 | 1% |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 492 SY | $90.00 | $95.00 | 1% |
| 608E52000 CURB RAMP | 1,505 SF | $26.00 | $28.00 | 1% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $1,500 | $325 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 300 HOUR | $120 | $100 | 1% |
| 611E99150 INLET ADJUSTED TO GRADE | 23 EACH | $1,565 | $2,200 | 1% |
| 611E98841 INLET, NO. 2-A-6, AS PER PLAN(8" TOP REPLACEMENT) | 10 EACH | $3,500 | $5,500 | 1% |
| 608E10000 4" CONCRETE WALK | 2,379 SF | $11.00 | $12.00 | 1% |
| Item | Quantity | R1Kokosing Construction Company INC | R2Karvo Companies INC |
|---|---|---|---|
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 2,950 SY | $3.00 | $12.00 |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN(DRIVEWAY APRON) | 492 SY | $18.00 | $32.00 |
| 202E30000 WALK REMOVED | 4,021 SF | $4.00 | $8.00 |
| 202E32000 CURB REMOVED | 966 FT | $12.00 | $25.00 |
| 203E10000 EXCAVATION | 492 CY | $15.00 | $80.00 |
| 203E20001 EMBANKMENT, AS PER PLAN(CURB RAMPS) (6" AVERAGE DE | 11 CY | $75.00 | $500 |
| 204E10000 SUBGRADE COMPACTION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 2,950 SY |
| $0.35 |
| $2.25 |
| 209E60500 LINEAR GRADING | 2.09 MILE | $4,000 | $2,575 |
| 608E15000 8" CONCRETE WALK | 221 SF | $13.00 | $15.00 |
| 608E52001 CURB RAMP, AS PER PLAN | 106 SF | $30.00 | $35.00 |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 12 EACH | $410 | $1,350 |
| 623E39601 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE, AS PER P | 6 EACH | $925 | $1,950 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $2,000 | $2,500 |
| 625E31600 PULL BOX, MISC.: SLIP RESISTANT LID | 3 EACH | $550 | $150 |
| 625E31600 PULL BOX, MISC.:PULL BOX ADJUSTED TO GRADE | 3 EACH | $1,100 | $100 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 |
| 611E98650 CATCH BASIN FRAME AND GRATE | 1 EACH | $750 | $1,000 |
| 611E98841 INLET, NO. 2-A-6, AS PER PLAN(8" TOP REPLACEMENT) | 4 EACH | $3,500 | $5,500 |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE | 1 EACH | $5,800 | $1,700 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 3,000 LB | $2.50 | $2.75 |
| 304E20000 AGGREGATE BASE | 492 CY | $50.00 | $95.00 |
| 407E20000 NON-TRACKING TACK COAT(@ 0.09 GAL/SY) | 10,066 GAL | $2.50 | $2.75 |
| 408E10001 PRIME COAT, AS PER PLAN | 1,022 GAL | $5.00 | $5.90 |
| 609E26000 CURB, TYPE 6 | 525 FT | $39.00 | $35.00 |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 61 FT | $39.00 | $35.00 |
| 617E10100 COMPACTED AGGREGATE | 142 CY | $105 | $100 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 800 FT | $9.00 | $7.50 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 8 FT | $20.00 | $20.00 |
| 630E80100 SIGN, FLAT SHEET | 5.4 SF | $20.00 | $20.00 |
| 644E00100 EDGE LINE, 4" | 1.21 MILE | $3,000 | $3,000 |
| 644E00104 EDGE LINE, 6"(BIKE LANE) | 1.79 MILE | $3,600 | $3,600 |
| 644E00300 CENTER LINE, 4" DOUBLE YELLOW | 0.71 MILE | $4,975 | $4,975 |
| 644E00300 CENTER LINE, 4" SOLID-SKIP | 0.15 MILE | $4,500 | $4,500 |
| 644E00404 CHANNELIZING LINE, 12" | 420 FT | $2.00 | $2.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE 24" | 240 FT | $6.00 | $6.00 |
| 644E01300 LANE ARROW | 7 EACH | $100 | $100 |
| 644E00700 TRANSVERSE/DIAGONAL LINE, 6" | 742 FT | $1.65 | $1.65 |
| 644E01500 DOTTED LINE, 4" | 800 FT | $1.15 | $1.15 |
| 644E01630 BIKE LANE SYMBOL MARKING | 30 EACH | $200 | $200 |
| 644E19000 SHARED LANE MARKING(SHARROW) | 1 EACH | $200 | $200 |
| 644E30000 REMOVAL OF PAVEMENT MARKING(EXISTING LONG LINE) | 2,160 FT | $1.50 | $1.50 |
| 644E30020 REMOVAL OF PAVEMENT MARKING(EXISTING ARROW) | 9 EACH | $100 | $100 |
| 644E30020 REMOVAL OF PAVEMENT MARKING(EXISTING TRANSVERSE/DI | 216 EACH | $4.00 | $4.00 |
| 646E10000 EDGE LINE, 4" | 1.13 MILE | $2,450 | $2,450 |
| 646E10010 EDGE LINE, 6"(BIKE LANE) | 1.87 MILE | $3,100 | $3,100 |
| 646E10200 CENTER LINE, 4" DOUBLE YELLOW | 0.52 MILE | $4,675 | $4,675 |
| 646E10200 CENTER LINE, 4" SOLID-SKIP | 0.06 MILE | $4,000 | $4,000 |
| 646E10310 CHANNELIZING LINE, 12" | 250 FT | $1.65 | $1.65 |
| 646E10400 STOP LINE | 72 FT | $12.50 | $12.50 |
| 646E10600 TRANSVERSE/DIAGONAL LINE 24" | 14 FT | $15.00 | $15.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE, 6" | 1,092 FT | $3.75 | $3.75 |
| 646E20300 LANE ARROW | 13 EACH | $175 | $175 |
| 646E20502 DOTTED LINE, 4" | 200 FT | $1.25 | $1.25 |
| 646E20600 BIKE LANE SYMBOL MARKING | 26 EACH | $300 | $300 |
| AA2 644E00100 EDGE LINE, 4"(ALTERNATE 2) | 0.09 MILE | $3,300 | $3,000 |
| AA2 644E00104 EDGE LINE, 6"(BIKE LANE) (ALTERNATE 2) | 1.32 MILE | $3,960 | $3,600 |
| AA2 644E00300 CENTER LINE, 4" DOUBLE YELLOW (ALTERNATE 2) | 0.75 MILE | $5,475 | $4,975 |
| AA2 644E00300 CENTER LINE, 4" SOLID-SKIP (ALTERNATE 2) | 2.31 MILE | $4,510 | $4,100 |
| AA2 644E00404 CHANNELIZING LINE, 12"(ALTERNATE 2) | 1,320 FT | $2.20 | $2.00 |
| AA2 644E00500 STOP LINE(ALTERNATE 2) | 270 FT | $7.10 | $6.50 |
| AA2 644E00700 TRANSVERSE/DIAGONAL LINE, 24" (ALTERNATE 2) | 142 FT | $6.60 | $6.00 |
| AA2 644E00700 TRANSVERSE/DIAGONAL LINE, 6" (ALTERNATE 2) | 70 FT | $6.60 | $6.00 |
| AA2 644E01300 LANE ARROW(ALTERNATE 2) | 72 EACH | $110 | $100 |
| AA2 644E01630 BIKE LANE SYMBOL MARKING(ALTERNATE 2) | 33 EACH | $220 | $200 |
| AA2 644E19000 SHARED LANE MARKING(SHARROW) (ALTERNATE 2) | 34 EACH | $220 | $200 |
| AA2 646E10520 CROSSWALK LINE, 24"(ALTERNATE 2) | 2,072 FT | $10.75 | $9.75 |
| AA2 646E20650 SHARED LANE MARKING(SHARROW)(ALTERNATE 2) | 19 EACH | $355 | $325 |
| AB2 644E00100 EDGE LINE, 4"(ALTERNATE 2) | 2.69 MILE | $3,300 | $3,000 |
| AB2 644E00100 EDGE LINE, 4"(YELLOW) (ALTERNATE 2) | 0.59 MILE | $3,300 | $3,000 |
| AB2 644E00104 EDGE LINE, 6"(BIKE LANE) (ALTERNATE 2) | 0.17 MILE | $4,400 | $4,000 |
| AB2 644E00200 LANE LINE, 4"(ALTERNATE 2) | 2.76 MILE | $1,320 | $1,200 |
| AB2 644E00300 CENTER LINE, 4" DOUBLE YELLOW (ALTERNATE 2) | 1.11 MILE | $5,490 | $4,900 |
| AB2 644E00300 CENTER LINE, 4" SOLID-SKIP (ALTERNATE 2) | 0.17 MILE | $4,400 | $4,000 |
| AB2 644E00404 CHANNELIZING LINE, 12"(ALTERNATE 2) | 100 FT | $2.20 | $2.00 |
| AB2 644E00500 STOP LINE(ALTERNATE 2) | 60 FT | $6.60 | $6.00 |
| AB2 644E00700 TRANSVERSE/DIAGONAL LINE, 24" (ALTERNATE 2) | 74 FT | $6.60 | $6.00 |
| AB2 644E01300 LANE ARROW(ALTERNATE 2) | 16 EACH | $110 | $100 |
| AB2 644E01630 BIKE LANE SYMBOL MARKING(ALTERNATE 2) | 6 EACH | $250 | $225 |
| AB2 646E10520 CROSSWALK LINE, 24"(ALTERNATE 2) | 255 FT | $13.20 | $12.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $650 | $650 |
| 614E20550 WORK ZONE LANE LINE, CLASS III, 4", 642 PAINT | 5.52 MILE | $525 | $525 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT, 4" DO | 6.19 MILE | $895 | $895 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT, 4" SO | 5.38 MILE | $875 | $875 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 10.24 MILE | $475 | $475 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT(YELL | 1.18 MILE | $475 | $475 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT(BIKE | 10.32 MILE | $595 | $595 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 4,180 FT | $0.50 | $0.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 804 FT | $3.00 | $3.00 |
| 614E27250 WORK ZONE CROSSWALK LINE, CLASS III, 12", 642 PAIN | 4,654 FT | $2.35 | $2.35 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 216 EACH | $38.50 | $38.50 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $2,500 | $9,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $25,000 | $34,550 |
| 619E16020 FIELD OFFICE, TYPE C | 6 MNTH | $3,600 | $2,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 4,660 CY | $225 | $1.05M | 24% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)(TRANSVERSE) | 1,632 CY | $400 | $653k | 15% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $449,841 | $450k | 10% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(1.5") | 111,841 SY | $2.35 | $263k | 6% |
| 452E12011 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 2,950 SY | $87 | $257k | 6% |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442)(LONGITUDINAL) | 700 CY | $330 | $231k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $210,000 | $210k | 5% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 103 EACH | $1,540 | $159k | 4% |
| 253E02000 PAVEMENT REPAIR(FULL DEPTH FLEXIBLE) (TRANSVERSE) | 163 CY | $700 | $114k | 3% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 91 EACH | $715 | $65k | 2% |