ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 45 more items below.
| Item | Quantity | R1John R Jurgensen Company | R2Barrett Paving Materials INC | % of bid |
|---|---|---|---|---|
| 253E01000 PAVEMENT REPAIR | 565 SY | $261 | $150 | 15% |
| 609E24511 CURB, TYPE 4-C, AS PER PLAN | 4,844 FT | $25.47 | $22.00 | 12% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 515 CY | $236 | $230 | 12% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $77,207 | $119,500 | 8% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 238 CY | $236 | $245 | 6% |
| 203E10000 EXCAVATION | 711 CY | $72.20 | $80.00 | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 92 CY | $465 | $420 | 4% |
| 202E32500 CURB AND GUTTER REMOVED | 4,305 FT | $9.79 | $8.50 | 4% |
| 304E20000 AGGREGATE BASE | 272 CY | $151 | $125 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | 4% |
| 611E98690 CATCH BASIN, MISC.: TYPE D (DOUBLE) CATCH BASIN | 6 EACH | $5,930 | $8,150 | 4% |
| 690E12150 SPECIAL - ASPHALT REJUVENATING AGENT | 731 GAL | $42.41 | $43.10 | 3% |
| 611E98690 CATCH BASIN, MISC.: TYPE D CATCH BASIN | 8 EACH | $3,824 | $5,425 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, VARIABLE DEPTH | 11,241 SY | $2.42 | $2.80 | 3% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 185 CY | $132 | $100 | 2% |
| 611E04400 12" CONDUIT, TYPE B | 97 FT | $248 | $155 | 2% |
| 204E13000 EXCAVATION OF SUBGRADE | 185 CY | $120 | $50.00 | 2% |
| 452E10011 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 235 SY | $90.08 | $85.00 | 2% |
| 202E23000 PAVEMENT REMOVED, (CONCRETE) | 327 SY | $54.44 | $65.00 | 2% |
| 452E13011 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 163 SY | $107 | $100 | 2% |
| Item | Quantity | R1John R Jurgensen Company | R2Barrett Paving Materials INC |
|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,501 | $5,000 |
| 202E30000 WALK REMOVED | 1,505 SF | $3.27 | $3.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 107 FT | $52.34 | $40.00 |
| 202E58100 CATCH BASIN REMOVED | 15 EACH | $616 | $700 |
| 204E10000 SUBGRADE COMPACTION | 1,624 SY | $4.84 | $5.00 |
| 204E51000 GEOGRID | 555 SY | $8.14 | $5.00 |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 28 SF | $26.42 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $10.00 |
| 659E00300 TOPSOIL | 503 CY | $4.61 | $75.00 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 4,005 SY | $1.75 | $1.80 |
| 659E14000 REPAIR SEEDING AND MULCHING | 200 SY | $1.00 | $1.75 |
| 659E15000 INTER-SEEDING | 200 SY | $0.01 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.54 TON | $1,500 | $915 |
| 659E31000 LIME | 0.83 ACRE | $200 | $100 |
| 659E35000 WATER | 21.6 MGAL | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 |
| 611E05900 15" CONDUIT, TYPE B | 10 FT | $401 | $185 |
| 611E98690 CATCH BASIN, MISC.: TYPE 1A CATCH BASIN | 1 EACH | $7,031 | $7,000 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 20 EACH | $629 | $1,200 |
| 254E01600 PATCHING PLANED SURFACE | 565 SY | $4.90 | $10.00 |
| 407E20000 NON-TRACKING TACK COAT | 1,110 GAL | $5.00 | $3.50 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 28 CY | $190 | $165 |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 4 FT | $91.86 | $35.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 15 EACH | $595 | $685 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 192 FT | $15.50 | $15.50 |
| 630E80100 SIGN, FLAT SHEET | 98 SF | $16.00 | $16.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH | $15.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $45.00 | $45.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $20.00 | $20.00 |
| 644E00100 EDGE LINE, 4" | 0.45 MILE | $3,900 | $3,900 |
| 644E00300 CENTER LINE | 0.86 MILE | $7,700 | $7,700 |
| 644E00400 CHANNELIZING LINE, 8" | 420 FT | $1.95 | $1.95 |
| 644E00500 STOP LINE | 74 FT | $7.80 | $8.00 |
| 644E00620 CROSSWALK LINE, 12" | 373 FT | $3.90 | $4.00 |
| 644E00630 CROSSWALK LINE, 24" | 370 FT | $7.80 | $8.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 26 FT | $7.40 | $7.50 |
| 644E00900 ISLAND MARKING | 80 SF | $5.50 | $5.50 |
| 644E01110 SCHOOL SYMBOL MARKING, 96" | 1 EACH | $665 | $680 |
| 644E01300 LANE ARROW | 23 EACH | $120 | $125 |
| 644E01500 DOTTED LINE, 4" | 112 FT | $1.80 | $1.85 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,571 | $14,126 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,313 | $25,000 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.02 MILE | $8,356 | $8,400 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 1.02 MILE | $4,180 | $4,200 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 18 EACH | $100 | $100 |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 2.04 MILE | $2,549 | $2,550 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 253E01000 PAVEMENT REPAIR | 565 SY | $260.59 | $147k | 13% |
| 609E24511 CURB, TYPE 4-C, AS PER PLAN | 4,844 FT | $25.47 | $123k | 11% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 515 CY | $235.59 | $121k | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $77,207 | $77k | 7% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 238 CY | $235.92 | $56k | 5% |
| 203E10000 EXCAVATION | 711 CY | $72.2 | $51k | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 92 CY | $464.91 | $43k | 4% |
| 202E32500 CURB AND GUTTER REMOVED | 4,305 FT | $9.79 | $42k | 4% |
| 304E20000 AGGREGATE BASE | 272 CY | $151.18 | $41k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |