| Item | Quantity | R1Ohio Concrete Maintenance LLC | R2Stanley Miller Construction Company | R3Madex Construction CO | R4Bcc Ohio INC | R5Eclipse CO LLC | R6R C Construction Company And Son INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN (144" C | 124 FT | $200 | $220 | $282 | $268 | $303 | $300 | 20% |
| 659E00300 TOPSOIL | 203 CY | $75.00 | $62.00 | $33.03 | $90.89 | $40.00 | $55.00 | 12% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 101 CY | $100 | $213 |
| Item | Quantity | R1Ohio Concrete Maintenance LLC | R2Stanley Miller Construction Company | R3Madex Construction CO | R4Bcc Ohio INC | R5Eclipse CO LLC | R6R C Construction Company And Son INC |
|---|---|---|---|---|---|---|---|
| 659E14000 REPAIR SEEDING AND MULCHING | 92 SY | $5.00 | $1.00 | $2.62 | $2.37 | $1.80 | $0.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.26 TON | $1,000 | $800 | $1,447 | $1,313 | $920 | $2,000 |
| 659E31000 LIME | 0.38 ACRE | $1,000 | $150 | $174 | $158 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $179 |
| $249 |
| $142 |
| $175 |
| 8% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $6,800 | $6,671 | $2,102 | $8,559 | $25,000 | 8% |
| 659E10000 SEEDING AND MULCHING | 1,830 SY | $5.00 | $2.75 | $2.62 | $2.37 | $2.30 | $10.00 | 7% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $8,000 | $7,200 | $6,780 | $4,515 | $35,000 | $25,000 | 6% |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $2,100 | $250 | $502 | $2,549 | $687 | $500 | 5% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 51 SF | $100 | $100 | $178 | $120 | $342 | $500 | 4% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 124 FT | $38.00 | $25.00 | $31.78 | $16.54 | $50.00 | $175 | 4% |
| 601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE C WITH A | 10 CY | $450 | $480 | $523 | $527 | $232 | $500 | 4% |
| 690E98400 SPECIAL - MISC.: WORK INVOLVING ASBESTOS CONTAINI | 1 LS | $4,000 | $1,000 | $1,505 | $1.05 | $528 | $50,000 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $2,500 | $4,139 | $1,851 | $2,643 | $20,000 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $3,000 | $2,850 | $3,550 | $1,872 | $1,790 | $10,000 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,500 | $5,250 | $1,659 | $1,872 | $8,000 | $3,500 | 2% |
| 601E11000 RIPRAP, TYPE D | 51 SY | $40.00 | $225 | $382 | $350 | $175 | $250 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $2,000 | $5,000 | $5,635 | $6,692 | $15,687 | $25,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $6,000 | $2,270 | $3,060 | $2,137 | $10,000 | 1% |
| 202E98300 REMOVAL MISC.: RIPRAP REMOVED | 41 SY | $25.00 | $55.00 | $41.88 | $45.66 | $56.00 | $95.00 | 1% |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $500 | $50.00 | $179 | $158 | $132 | $50.00 | 1% |
| $166 |
| $2,000 |
| 659E35000 WATER | 11 MGAL | $10.00 | $1.00 | $1.16 | $1.05 | $1.00 | $1.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN (144" C | 124 FT | $200 | $25k | 20% |
| 659E00300 TOPSOIL | 203 CY | $75 | $15k | 12% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 101 CY | $100 | $10k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 8% |
| 659E10000 SEEDING AND MULCHING | 1,830 SY | $5 | $9k | 7% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $8,000 | $8k | 6% |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $2,100 | $6k | 5% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 51 SF | $100 | $5k | 4% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1 | $5k | 4% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 124 FT | $38 | $5k | 4% |