MOE-Sign Flatsheet FY2025
MOE County · est $1.1M
Bid dateThursday, August 8—
MOE County · est $1.1M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 52,291 FT | $8.8 | $460k |
ODOT bid tab line items with each bidder’s unit price. Top 17items by winning bid’s extended amount.
| Item | Quantity | R1M P Dory CO | R2Cleveland Barricading Systems LLC | R3Lake Erie Construction Company | R4American Roadway Logistics | % of bid |
|---|---|---|---|---|---|---|
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 52,291 FT | $8.80 | $7.95 | $12.00 | $10.00 | 46% |
| 630E80100 SIGN, FLAT SHEET | 22,825.4 SF | $13.80 | $14.70 | $15.00 | $22.50 | 32% |
| 630E08600 SIGN POST REFLECTOR | 1,977 EACH | $35.00 | $22.85 | $40.00 | $25.00 | 7% |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 5,091 FT | $7.80 | $7.25 | $11.00 | $8.25 | 4% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3,528 EACH | $10.00 | $23.55 | $20.00 | $25.00 | 4% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4,205 EACH | $8.00 | $11.45 | $10.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $25.00 |
| 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $133,000 | $21,530 | $300,000 | 1% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $40,000 | $32,850 | $250,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $4,498 | $7,700 | $17,500 | 1% |
| 630E80600 SIGN, DOUBLE FACED, MILE MARKER | 190 EACH | $32.00 | $20.65 | $95.00 | $50.00 | 1% |
| 630E04101 GROUND MOUNTED SUPPORT, NO. 4 POST, AS PER PLAN | 197 FT | $18.50 | $9.00 | $15.30 | $27.50 | 0% |
| 630E08005 ONE WAY SUPPORT, NO. 3 POST, AS PER PLAN | 198 FT | $12.25 | $16.00 | $14.00 | $22.50 | 0% |
| 630E80101 SIGN, FLAT SHEET, AS PER PLAN | 77 SF | $18.60 | $17.75 | $21.70 | $100 | 0% |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 35 EACH | $40.00 | $50.50 | $65.00 | $100 | 0% |
| 630E85001 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE, AS PER | 21 EACH | $40.00 | $75.00 | $32.00 | $50.00 | 0% |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 42 FT | $16.50 | $11.85 | $16.00 | $27.50 | 0% |
| 630E82000 SIGN BACKING ASSEMBLY | 4 EACH | $150 | $158 | $195 | $225 | 0% |
| 46% |
| 630E80100 SIGN, FLAT SHEET | 22,825.4 SF | $13.8 | $315k | 32% |
| 630E08600 SIGN POST REFLECTOR | 1,977 EACH | $35 | $69k | 7% |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 5,091 FT | $7.8 | $40k | 4% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3,528 EACH | $10 | $35k | 4% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4,205 EACH | $8 | $34k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $10k | 1% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $8k | 1% |
| 630E80600 SIGN, DOUBLE FACED, MILE MARKER | 190 EACH | $32 | $6k | 1% |