ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 39 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Shelly Company | R3Karvo Companies INC | % of bid |
|---|---|---|---|---|---|
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, | 5,186 CY | $208 | $215 | $235 | 34% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1, | 3,983 CY | $175 | $175 | $225 | 22% |
| 253E02000 PAVEMENT REPAIR | 825 CY | $340 | $235 | $400 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $209,491 | $252,500 | $217,532 | 7% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 2 | 143,896 SY | $1.00 | $1.50 | $2.00 | 5% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR | 235 CY | $445 | $335 | $400 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 |
| Item | Quantity | R1Shelly & Sands INC | R2Shelly Company | R3Karvo Companies INC |
|---|---|---|---|---|
| 202E00201 RAILROAD CROSSING REMOVED, AS PER PLAN | 1 LS | $10,000 | $4,000 | $5,000 |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 108 SY | $35.00 | $28.00 | $55.00 |
| 202E30000 WALK REMOVED | 171 SF | $15.00 | $16.50 | $35.00 |
| 202E32001 CURB REMOVED, AS PER PLAN | 33 FT | $25.00 | $24.00 | $150 |
| 204E10000 SUBGRADE COMPACTION | 108 SY | $5.00 | $1.50 | $1.00 |
| 607E98000 FENCE, MISC.: TEMPORARY ORANGE CONSTRUCTION FENCE |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $99,000 |
| 3% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), | 108 CY | $790 | $500 | $700 | 3% |
| 202E23500 WEARING COURSE REMOVED | 4,640 SY | $15.00 | $19.00 | $20.00 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 605 CY | $100 | $65.00 | $135 | 2% |
| 617E20001 SHOULDER PREPARATION, AS PER PLAN | 17,405 SY | $2.75 | $0.50 | $1.00 | 2% |
| 646E10010 EDGE LINE, 6" | 15.24 MILE | $2,900 | $3,255 | $2,900 | 1% |
| 646E10200 CENTER LINE | 8.53 MILE | $4,250 | $3,633 | $4,250 | 1% |
| 621E00100 RPM | 853 EACH | $37.50 | $37.50 | $38.50 | 1% |
| 407E10000 TACK COAT | 15,178 GAL | $2.00 | $3.25 | $2.75 | 1% |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1, | 81 CY | $320 | $215 | $385 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 7,046 GAL | $3.50 | $5.00 | $5.50 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 25.59 MILE | $950 | $995 | $1,000 | 1% |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 14.94 MILE | $1,500 | $1,690 | $1,275 | 1% |
| 874E21000 LONGITUDINAL JOINT PREPARATION | 5.63 MILE | $3,750 | $7,100 | $4,000 | 1% |
| 136 FT |
| $12.00 |
| $5.00 |
| $1.00 |
| 608E52000 CURB RAMP | 171 SF | $35.00 | $45.00 | $50.00 |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 34 SF | $37.50 | $45.00 | $135 |
| 623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE | 2 EACH | $50.00 | $1,700 | $1,750 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 3 EACH | $585 | $350 | $500 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 7 EACH | $480 | $450 | $600 |
| 659E98000 SEEDING, MISC.: CURB RAMP GRADING RESTORATION | 4 SY | $300 | $60.00 | $25.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 825 FT | $20.00 | $7.50 | $35.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $1,500 | $2,000 | $1,175 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 76 FT | $10.00 | $7.00 | $8.00 |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 1 | 178 SY | $12.00 | $6.50 | $1.00 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, | 28 CY | $250 | $305 | $400 |
| 304E20000 AGGREGATE BASE | 18 CY | $100 | $120 | $130 |
| 407E20000 NON-TRACKING TACK COAT | 5,468 GAL | $3.05 | $3.00 | $2.75 |
| 618E43000 RUMBLE STRIPES, CENTER LINE | 5.63 MILE | $1,215 | $1,215 | $1,215 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 853 EACH | $5.00 | $6.50 | $1.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $90.00 | $120 | $20.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $90.00 | $125 | $25.00 |
| 646E10000 EDGE LINE, 4" | 0.5 MILE | $5,000 | $2,800 | $5,000 |
| 646E10400 STOP LINE | 180 FT | $15.00 | $13.50 | $15.00 |
| 646E10510 CROSSWALK LINE, 12" | 979 FT | $6.00 | $6.00 | $6.00 |
| 646E10520 CROSSWALK LINE, 24" | 168 FT | $12.50 | $13.00 | $12.50 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 210 FT | $12.50 | $10.00 | $12.50 |
| 646E10900 HANDICAP SYMBOL MARKING | 3 EACH | $225 | $150 | $225 |
| 646E20200 PARKING LOT STALL MARKING | 784 FT | $4.25 | $4.90 | $4.25 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 60 HOUR | $85.00 | $100 | $100 |
| 614E12460 WORK ZONE MARKING SIGN | 66 EACH | $60.00 | $85.00 | $60.00 |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 25.59 MILE | $750 | $800 | $600 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 540 FT | $3.00 | $7.00 | $4.00 |
| 846E00111 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM, A | 34 CF | $575 | $575 | $575 |
| 846E00111 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM, A | 26 CF | $575 | $575 | $575 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $2,000 | $2,000 | $5,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,000 | $16,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, | 5,186 CY | $208 | $1.08M | 32% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1, | 3,983 CY | $175 | $697k | 21% |
| 253E02000 PAVEMENT REPAIR | 825 CY | $340 | $281k | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $209,491 | $209k | 6% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 2 | 143,896 SY | $1 | $144k | 4% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR | 235 CY | $445 | $105k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 3% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), | 108 CY | $790 | $85k | 3% |
| 202E23500 WEARING COURSE REMOVED | 4,640 SY | $15 | $70k | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 605 CY | $100 | $61k | 2% |