GEA-SR 87-12.13 Replace
GEA County · est $1.7M
Bid dateThursday, November 14—
GEA County · est $1.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 72 more items below.
| Item | Quantity | R1Matt Winters Excavation LLC | R2Marucci & Gaffney Excavating CO | R3Shelly & Sands INC | R4Union Industrial Contractors INC | R5Ruhlin Company | % of bid |
|---|---|---|---|---|---|---|---|
| 515E15010 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 6 EACH | $51,000 | $33,000 | $42,700 | $48,500 | $50,000 | 26% |
| 511E34444 CLASS QC2 CONCRETE, BRIDGE DECK | 145 CY | $825 | $1,200 | $1,900 | $1,450 | $1,150 | 10% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 46,547 LB | $2.00 | $1.60 | $1.74 | $1.75 | $2.39 | 8% |
| 526E15000 REINFORCED CONCRETE APPROACH SLABS (T=13") | 184 SY | $450 | $429 | $394 | $450 | $575 | 7% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 80 FT | $875 | $998 | $600 | $1,050 | $1,912 | 6% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING |
| Item | Quantity | R1Matt Winters Excavation LLC | R2Marucci & Gaffney Excavating CO | R3Shelly & Sands INC | R4Union Industrial Contractors INC | R5Ruhlin Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,500 | $10,000 | $11,500 | $20,000 | $95,000 |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 118 FT | $10.00 | $40.00 | $37.00 | $25.00 | $40.00 |
| 202E38000 GUARDRAIL REMOVED | 572 FT | $3.00 | $2.00 | $2.90 | $2.00 | $15.00 |
| 203E10000 EXCAVATION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 71 CY |
| $819 |
| $900 |
| $1,500 |
| $950 |
| $1,600 |
| 5% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $45,000 | $43,000 | $72,000 | $45,000 | $55,000 | 4% |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 35 CY | $1,200 | $1,000 | $1,600 | $1,250 | $1,175 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $40,000 | $40,000 | $115,000 | 3% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $39,833 | $200,000 | $61,000 | $167,000 | $165,000 | 3% |
| 302E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 138 CY | $255 | $340 | $273 | $340 | $340 | 3% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $33,500 | $47,000 | $40,500 | $50,000 | $74,000 | 3% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 215 SY | $150 | $96.50 | $150 | $175 | $125 | 3% |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 34 CY | $900 | $425 | $456 | $425 | $425 | 3% |
| 507E00101 STEEL PILES HP10X42, FURNISHED, AS PER PLAN | 560 FT | $50.00 | $46.00 | $24.94 | $32.50 | $65.00 | 2% |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 274 CY | $100 | $70.00 | $155 | $215 | $215 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $25,000 | $54,000 | $20,700 | $35,000 | $50,000 | 2% |
| 622E41110 PORTABLE BARRIER, ANCHORED | 940 FT | $26.00 | $30.00 | $32.00 | $35.00 | $45.00 | 2% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (46 CY | $425 | $350 | $295 | $350 | $350 | 2% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 35 CF | $550 | $628 | $800 | $600 | $593 | 2% |
| 240 CY |
| $25.00 |
| $60.00 |
| $35.00 |
| $55.00 |
| $80.00 |
| 203E20000 EMBANKMENT | 134 CY | $40.00 | $50.00 | $70.00 | $115 | $100 |
| 204E10000 SUBGRADE COMPACTION | 1,058 SY | $9.00 | $3.00 | $5.00 | $3.50 | $3.50 |
| 204E45000 PROOF ROLLING | 1 HOUR | $350 | $80.00 | $250 | $150 | $450 |
| 606E15050 GUARDRAIL, TYPE MGS | 288 FT | $23.00 | $22.00 | $22.50 | $22.00 | $28.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,500 | $2,480 | $2,500 | $2,480 | $3,100 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,400 | $1,395 | $1,250 | $1,395 | $1,700 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,450 | $2,420 | $2,700 | $2,420 | $2,900 |
| 623E40900 MONUMENT, MISC.: #5 REBAR X 30" LONG | 1 EACH | $125 | $3,000 | $68.00 | $2,100 | $830 |
| 202E23000 PAVEMENT REMOVED | 741 SY | $20.00 | $12.00 | $16.00 | $16.50 | $30.00 |
| 202E23500 WEARING COURSE REMOVED | 115 SY | $20.00 | $5.00 | $12.50 | $20.00 | $50.00 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT U | 23 SY | $140 | $100 | $73.00 | $160 | $286 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 704 SY | $4.75 | $10.00 | $5.00 | $3.00 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 70 SY | $2.00 | $0.27 | $2.50 | $4.00 | $4.00 |
| 659E35000 WATER | 4 MGAL | $1.00 | $0.27 | $1.00 | $4.00 | $5.00 |
| 832E30000 EROSION CONTROL | 1,400 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.92 CY | $2,500 | $2,000 | $5,300 | $2,000 | $3,500 |
| 605E31100 AGGREGATE DRAINS | 58 FT | $51.00 | $20.00 | $28.00 | $25.00 | $45.00 |
| 611E10600 24" CONDUIT, TYPE C | 65 FT | $140 | $134 | $190 | $125 | $200 |
| 611E12100 27" CONDUIT, TYPE C | 65 FT | $150 | $143 | $202 | $155 | $225 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $3,700 | $2,248 | $3,600 | $2,000 | $7,000 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $4,600 | $3,162 | $5,400 | $5,500 | $8,500 |
| 304E20000 AGGREGATE BASE | 171 CY | $110 | $115 | $160 | $135 | $125 |
| 407E20000 NON-TRACKING TACK COAT | 81 GAL | $3.50 | $3.00 | $3.05 | $3.00 | $3.00 |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $430 | $425 | $654 | $425 | $425 |
| 441E70700 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (5 CY | $425 | $350 | $391 | $350 | $350 |
| 609E24510 CURB, TYPE 4-C | 72 FT | $38.00 | $70.00 | $68.00 | $55.00 | $61.00 |
| 617E10100 COMPACTED AGGREGATE | 15 CY | $120 | $200 | $180 | $200 | $200 |
| 621E00100 RPM | 10 EACH | $205 | $353 | $200 | $450 | $353 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 10 EACH | $20.00 | $10.00 | $20.00 | $100 | $10.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 45 FT | $22.00 | $33.00 | $16.00 | $21.00 | $21.00 |
| 630E80100 SIGN, FLAT SHEET | 18 SF | $26.00 | $36.00 | $20.00 | $25.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 8 EACH | $15.00 | $16.55 | $25.00 | $10.00 | $10.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $20.00 | $22.06 | $25.00 | $15.00 | $15.00 |
| 646E10010 EDGE LINE, 6" | 0.3 MILE | $7,600 | $8,555 | $11,800 | $7,500 | $8,555 |
| 646E10200 CENTER LINE | 0.35 MILE | $9,600 | $6,560 | $12,200 | $9,500 | $6,560 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 50 CY | $90.00 | $30.00 | $125 | $145 | $150 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $90.00 | $40.00 | $110 | $75.00 | $85.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 80 FT | $2.25 | $2.16 | $1.80 | $5.00 | $2.16 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,300 | $2,222 | $2,300 | $3,200 | $2,221 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 4 EACH | $3,600 | $1,750 | $2,200 | $12,000 | $1,909 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $165 | $80.00 | $300 | $350 | $770 |
| 614E13310 BARRIER REFLECTOR, TYPE 1(BI-DIRECTIONAL) | 11 EACH | $15.00 | $12.20 | $8.00 | $25.00 | $12.17 |
| 614E13360 OBJECT MARKER, TWO WAY | 11 EACH | $25.00 | $19.20 | $24.00 | $50.00 | $19.12 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $1,000 | $1,100 | $1,000 | $1,100 | $1,097 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.36 MILE | $5,500 | $5,000 | $4,800 | $4,500 | $4,695 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.3 MILE | $5,500 | $2,500 | $4,700 | $4,500 | $2,475 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.56 MILE | $4,000 | $3,660 | $3,600 | $3,500 | $2,655 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.35 MILE | $4,000 | $3,300 | $3,550 | $3,500 | $3,285 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 46 FT | $6.00 | $10.00 | $10.00 | $5.00 | $10.00 |
| 616E10000 WATER | 52 MGAL | $10.00 | $0.01 | $40.00 | $15.00 | $55.00 |
| 202E22900 APPROACH SLAB REMOVED | 109 SY | $95.00 | $25.00 | $27.00 | $80.00 | $100 |
| 503E21100 UNCLASSIFIED EXCAVATION | 214 CY | $50.00 | $80.00 | $185 | $175 | $250 |
| 509E30020 NO. 4 DEFORMED GFRP REINFORCEMENT | 4,000 FT | $2.00 | $1.70 | $2.58 | $1.35 | $2.21 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 236 SY | $75.00 | $40.00 | $93.00 | $45.00 | $95.00 |
| 512E33000 TYPE 2 WATERPROOFING | 4 SY | $165 | $100 | $172 | $300 | $160 |
| 515E20000 INTERMEDIATE DIAPHRAGMS | 5 EACH | $2,500 | $3,900 | $4,000 | $2,500 | $5,400 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 99 SF | $7.00 | $10.00 | $5.00 | $15.00 | $4.50 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 83 SF | $8.00 | $15.00 | $7.00 | $20.00 | $23.54 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 56 SF | $15.00 | $19.00 | $12.00 | $30.00 | $23.25 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 336 SF | $15.00 | $40.00 | $14.00 | $15.00 | $18.00 |
| 516E44201 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 12 EACH | $1,400 | $1,300 | $1,846 | $1,500 | $3,000 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 67 CY | $160 | $125 | $160 | $150 | $200 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 104 FT | $16.00 | $10.00 | $9.00 | $20.00 | $22.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 40 FT | $15.00 | $10.00 | $9.00 | $25.00 | $48.00 |
| 526E90010 TYPE A INSTALLATION | 83 FT | $125 | $200 | $320 | $225 | $280 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,000 | $10,000 | $10,100 | $20,000 | $13,650 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 6 MNTH | $120 | $1,000 | $4,600 | $2,200 | $3,176 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $19,000 | $24,500 | $22,000 | $33,740 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E15010 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 6 EACH | $51,000 | $306k | 20% |
| 511E34444 CLASS QC2 CONCRETE, BRIDGE DECK | 145 CY | $825 | $120k | 8% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 46,547 LB | $2 | $93k | 6% |
| 526E15000 REINFORCED CONCRETE APPROACH SLABS (T=13") | 184 SY | $450 | $83k | 5% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 80 FT | $875 | $70k | 5% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 71 CY | $819 | $58k | 4% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $45,000 | $45k | 3% |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 35 CY | $1,200 | $42k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $39,833 | $40k | 3% |