HAM-US 50-33.70
HAM County · est $0.6M
Bid dateThursday, October 31—
HAM County · est $0.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 2 more items below.
| Item | Quantity | R1Bcc Ohio INC | % of bid |
|---|---|---|---|
| 511E81100 CONCRETE, MISC.: CULVERT LINING WITH CLASS QC1 CON | 459 FT | $187 | 26% |
| 602E97000 MASONRY, MISC.: STONE MASONRY REPAIRS | 1,021 SF | $59.63 | 18% |
| 511E47011 CLASS QC1 CONCRETE, CULVERT, AS PER PLAN | 9 CY | $3,391 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $30,377 | 9% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 120 SF | $152 | 5% |
| 511E71100 CONCRETE, MISC.: CULVERT LINING WITH CLASS QC1 CON | 23 CY | $572 | 4% |
| 202E98000 REMOVAL MISC.: REMOVAL OF HARDENED PIPE DISCHARGE | 1 LS | $11,412 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,553 | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN (CF | 1 LS | $9,782 | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN (SF | 1 LS | $9,782 | 3% |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 139 FT | $68.17 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,424 | 3% |
| 607E98000 FENCE, MISC.: WOOD FENCE | 90 FT | $91.88 | 2% |
| 509E26000 GALVANIZED STEEL REINFORCEMENT | 1,364 LB | $5.45 | 2% |
| 510E10001 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT, AS | 171 EACH | $35.25 | 2% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 200 SY | $23.94 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,530 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,128 | 1% |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | 0% |
| 659E20000 COMMERCIAL FERTILIZER | 0.03 TON | $2,048 | 0% |
| Item | Quantity | R1Bcc Ohio INC |
|---|---|---|
| 659E31000 LIME | 0.04 ACRE | $263 |
| 659E35000 WATER | 1 MGAL | $1.58 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E81100 CONCRETE, MISC.: CULVERT LINING WITH CLASS QC1 CON | 459 FT | $186.54 | $86k | 26% |
| 602E97000 MASONRY, MISC.: STONE MASONRY REPAIRS | 1,021 SF | $59.63 | $61k | 18% |
| 511E47011 CLASS QC1 CONCRETE, CULVERT, AS PER PLAN | 9 CY | $3,391 | $31k | 9% |
| 624E10000 MOBILIZATION | 1 LS | $30,377 | $30k | 9% |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 120 SF | $151.5 | $18k | 5% |
| 511E71100 CONCRETE, MISC.: CULVERT LINING WITH CLASS QC1 CON | 23 CY | $571.5 | $13k | 4% |
| 202E98000 REMOVAL MISC.: REMOVAL OF HARDENED PIPE DISCHARGE | 1 LS | $11,412 | $11k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,553 | $11k | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN (CF | 1 LS | $9,782 | $10k | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN (SF | 1 LS | $9,782 | $10k | 3% |