HOL-SR 515-00.00 (PART 1 AND PART 2)
HOL County · est $7.8M
Bid dateThursday, January 16—
HOL County · est $7.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 116 more items below.
| Item | Quantity | R1Shelly Company | R2Kokosing Construction Company INC | R3Karvo Companies INC | R4Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (8976 CY | $155 | $210 | $165 | $190 | 28% |
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 3,017 CY | $230 | $225 | $235 | $250 | 14% |
| 827E11000 CEMENT | 2,804 TON | $195 | $195 | $180 | $180 | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $476,500 | $524,160 | $335,000 | $330,000 | 10% |
| 827E20000 FULL DEPTH RECLAIMED BASE COURSE, 12" DEEP | 79,683 SY | $3.75 | $3.75 | $5.15 | $5.15 | 6% |
| 827E10000 PAVEMENT REMOVED | 79,683 SY | $3.50 | $3.50 |
| Item | Quantity | R1Shelly Company | R2Kokosing Construction Company INC | R3Karvo Companies INC | R4Shelly & Sands INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,500 | $2,340 | $2,340 | $10,000 |
| 202E23000 PAVEMENT REMOVED | 95 SY | $100 | $80.00 | $75.00 | $30.00 |
| 202E38000 GUARDRAIL REMOVED | 1,950 FT | $2.00 | $2.00 | $2.00 | $2.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 24 CY | $63.00 | $63.00 | $63.00 | $65.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $6.00 |
| $4.50 |
| 6% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 2,000 HOUR | $100 | $80.00 | $75.00 | $90.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $315,000 | $400,000 | $320,000 | 4% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 810 CY | $150 | $150 | $200 | $325 | 2% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $650 | $275 | $375 | $460 | 2% |
| 204E13000 EXCAVATION OF SUBGRADE | 1,995 CY | $50.00 | $15.00 | $25.00 | $22.00 | 2% |
| 827E12000 CURING COAT | 79,683 SY | $1.15 | $1.15 | $1.00 | $1.00 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 1,378 CY | $65.00 | $60.00 | $68.00 | $48.00 | 2% |
| 202E23500 WEARING COURSE REMOVED | 4,768 SY | $17.00 | $5.00 | $10.00 | $15.00 | 2% |
| 304E20000 AGGREGATE BASE | 1,995 CY | $40.00 | $40.00 | $80.00 | $73.00 | 2% |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 10.63 MILE | $5,200 | $150 | $2,000 | $1,200 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $50,000 | $75,000 | $75,000 | $52,000 | 1% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (5 | 6,214 SY | $7.00 | $7.00 | $7.00 | $8.00 | 1% |
| 611E53000 38" X 60" CONDUIT, TYPE A, 706.04 | 52 FT | $750 | $750 | $750 | $900 | 1% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (84 CY | $450 | $380 | $165 | $190 | 1% |
| 204E50000 GEOTEXTILE FABRIC | 3,390 SY | $5.00 | $2.00 | $1.00 | $0.60 |
| 209E60500 LINEAR GRADING | 10.63 MILE | $1,650 | $7,000 | $2,000 | $3,000 |
| 606E13000 GUARDRAIL, TYPE 5 | 300 FT | $18.00 | $18.00 | $18.00 | $19.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 1,775 FT | $18.00 | $18.00 | $18.00 | $19.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016 OR NCHRP 35 | 12 EACH | $2,350 | $2,350 | $2,350 | $2,500 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 4 EACH | $1,100 | $1,100 | $1,100 | $1,100 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 12 EACH | $1,150 | $1,150 | $1,150 | $1,200 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 10 EACH | $200 | $300 | $400 | $250 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $125 | $125 | $125 | $130 |
| 659E10000 SEEDING AND MULCHING | 22,000 SY | $0.70 | $0.69 | $0.69 | $0.70 |
| 659E14000 REPAIR SEEDING AND MULCHING | 1,100 SY | $0.80 | $0.80 | $0.80 | $0.80 |
| 659E20000 COMMERCIAL FERTILIZER | 2.97 TON | $895 | $898 | $898 | $900 |
| 659E31000 LIME | 4.55 ACRE | $155 | $155 | $155 | $160 |
| 659E35000 WATER | 119 MGAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 407E10000 TACK COAT | 12,170 GAL | $3.00 | $2.30 | $2.75 | $3.50 |
| 408E10001 PRIME COAT, AS PER PLAN | 4,958 GAL | $5.00 | $4.45 | $5.75 | $5.00 |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (8 CY | $500 | $800 | $350 | $195 |
| 441E70800 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (2 CY | $2,200 | $1,300 | $500 | $350 |
| 827E21000 MIXTURE DESIGN FOR FULL DEPTH RECLAIMED BASE | 1 LS | $15,000 | $15,000 | $30,000 | $24,000 |
| 827E22000 CORRECTIVE MATERIAL | 405 TON | $33.00 | $40.00 | $34.25 | $34.25 |
| 827E23000 COVER AGGREGATE | 608 TON | $32.00 | $40.00 | $21.75 | $43.52 |
| 827E30000 JUST-IN-TIME TRAINING | 1 LS | $1,500 | $1,000 | $1,750 | $1,750 |
| 621E00100 RPM | 755 EACH | $35.00 | $35.00 | $37.00 | $38.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 739 EACH | $6.15 | $4.00 | $1.00 | $8.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 6 EACH | $13.00 | $13.00 | $13.00 | $13.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 40 EACH | $13.00 | $13.00 | $13.00 | $13.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 84 FT | $13.00 | $13.00 | $13.00 | $14.00 |
| 630E80100 SIGN, FLAT SHEET | 18 SF | $20.00 | $20.00 | $20.00 | $21.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 7 EACH | $15.00 | $15.00 | $15.00 | $16.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $15.00 | $15.00 | $15.00 | $16.00 |
| 646E10010 EDGE LINE, 6" | 10.98 MILE | $2,750 | $2,750 | $2,750 | $2,900 |
| 646E10200 CENTER LINE | 5.53 MILE | $3,950 | $3,950 | $3,950 | $4,200 |
| 646E10300 CHANNELIZING LINE, 8" | 220 FT | $1.00 | $1.00 | $1.00 | $1.00 |
| 646E10400 STOP LINE | 57 FT | $12.00 | $12.00 | $12.00 | $12.00 |
| 646E10520 CROSSWALK LINE, 24" | 144 FT | $12.00 | $12.00 | $12.00 | $12.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 60 FT | $12.00 | $12.00 | $12.00 | $12.00 |
| 646E20300 LANE ARROW | 4 EACH | $175 | $175 | $175 | $180 |
| 646E20504 DOTTED LINE, 6" | 198 FT | $1.00 | $1.00 | $1.00 | $1.00 |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 96 FT | $20.00 | $20.00 | $20.00 | $20.00 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $5,400 | $5,387 | $5,387 | $5,700 |
| 202E23500 WEARING COURSE REMOVED | 289 SY | $16.00 | $30.00 | $35.00 | $10.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 64 SY | $39.25 | $39.21 | $39.21 | $42.00 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 14 FT | $80.90 | $80.87 | $80.87 | $86.00 |
| 512E33010 TYPE 3 WATERPROOFING | 196 SY | $52.30 | $52.28 | $52.28 | $56.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 25 SY | $19.30 | $19.28 | $19.28 | $21.00 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 112.5 FT | $101 | $101 | $101 | $108 |
| 519E00100 SPECIAL - COMPOSITE FIBER WRAP SYSTEM | 82 SF | $201 | $201 | $201 | $214 |
| 530E01300 SPECIAL - STRUCTURES (KEYWAY GROUT REPAIR) | 358 FT | $14.95 | $14.92 | $14.92 | $16.00 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $10,395 | $10,395 | $10,395 | $10,000 |
| 843E50001 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 20 SF | $148 | $148 | $148 | $158 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 45 CF | $525 | $525 | $525 | $560 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $2,000 | $1,953 | $1,953 | $2,000 |
| 202E23500 WEARING COURSE REMOVED | 96 SY | $45.00 | $80.00 | $15.00 | $1.50 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 55 SY | $38.10 | $38.10 | $38.10 | $40.00 |
| 512E33010 TYPE 3 WATERPROOFING | 114 SY | $52.30 | $52.28 | $52.28 | $56.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 55 SY | $21.65 | $21.62 | $21.62 | $23.00 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 62.5 FT | $101 | $101 | $101 | $108 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $10,395 | $10,395 | $10,395 | $10,000 |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $3,300 | $3,228 | $3,228 | $3,400 |
| 202E23500 WEARING COURSE REMOVED | 304 SY | $14.95 | $25.00 | $10.00 | $1.50 |
| 512E33010 TYPE 3 WATERPROOFING | 223 SY | $52.30 | $52.28 | $52.28 | $56.00 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 150 FT | $101 | $101 | $101 | $108 |
| 519E12200 PATCHING CONCRETE BRIDGE DECK - TYPE A | 5 SY | $725 | $725 | $725 | $774 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $10,395 | $10,395 | $10,395 | $10,000 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 37 CF | $529 | $529 | $529 | $564 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 50 CY | $70.00 | $90.00 | $200 | $85.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $5,250 | $5,250 | $5,250 | $6,000 |
| 614E12460 WORK ZONE MARKING SIGN | 25 EACH | $55.00 | $55.00 | $55.00 | $60.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $800 | $800 | $800 | $1,100 |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 16.93 MILE | $500 | $50.00 | $500 | $530 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 16.93 MILE | $1,050 | $525 | $1,050 | $1,100 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 880 FT | $0.60 | $0.30 | $0.60 | $0.60 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 213 FT | $3.00 | $1.50 | $3.00 | $3.00 |
| 616E10000 WATER | 300 MGAL | $10.00 | $1.00 | $1.00 | $65.00 |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,170 | $1,170 | $1,170 | $6,000 |
| 202E11000 STRUCTURE REMOVED | 1 LS | $8,100 | $8,100 | $8,100 | $10,000 |
| 202E20010 HEADWALL REMOVED | 2 EACH | $750 | $750 | $750 | $1,000 |
| 202E23000 PAVEMENT REMOVED | 46 SY | $10.05 | $10.05 | $10.05 | $24.00 |
| 203E10000 EXCAVATION | 21 CY | $23.40 | $23.40 | $23.40 | $55.00 |
| 203E20000 EMBANKMENT | 67 CY | $23.40 | $23.40 | $23.40 | $55.00 |
| 204E50000 GEOTEXTILE FABRIC | 3 SY | $20.55 | $20.55 | $20.55 | $180 |
| 606E15050 GUARDRAIL, TYPE MGS | 75 FT | $18.00 | $18.00 | $18.00 | $19.00 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 337.5 FT | $21.00 | $21.00 | $21.00 | $22.00 |
| 606E17350 GUARDRAIL, TYPE MGS, 25' LONG-SPAN | 25 FT | $25.00 | $25.00 | $25.00 | $26.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016 OR NCHRP 35 | 3 EACH | $2,350 | $2,350 | $2,350 | $2,500 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 3 EACH | $1,100 | $1,100 | $1,100 | $1,200 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 23 CY | $166 | $166 | $166 | $325 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $158 | $125 | $158 | $130 |
| 659E00300 TOPSOIL | 68 CY | $102 | $102 | $102 | $50.00 |
| 659E10000 SEEDING AND MULCHING | 31 SY | $70.05 | $70.04 | $70.04 | $75.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 31 SY | $12.80 | $12.80 | $12.80 | $14.00 |
| 659E15000 INTER-SEEDING | 31 SY | $12.80 | $12.80 | $12.80 | $14.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.09 TON | $898 | $898 | $898 | $950 |
| 659E31000 LIME | 0.13 ACRE | $155 | $155 | $155 | $165 |
| 659E35000 WATER | 3 MGAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 21,260 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 13.2 CY | $2,252 | $2,252 | $2,252 | $2,000 |
| 304E20000 AGGREGATE BASE | 6 CY | $342 | $342 | $342 | $52.00 |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 321 SY | $35.00 | $20.00 | $85.00 | $26.00 |
| 422E25000 EMULSION, CHIP SEAL | 119 GAL | $5.00 | $4.45 | $50.00 | $17.00 |
| 617E10100 COMPACTED AGGREGATE, TYPE A | 100 CY | $70.00 | $60.00 | $100 | $250 |
| 617E25000 WATER | 2 MGAL | $10.00 | $1.00 | $1.00 | $65.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.2 MILE | $2,500 | $2,500 | $2,500 | $2,600 |
| 642E00300 CENTER LINE, TYPE 1 | 0.1 MILE | $5,000 | $5,000 | $5,000 | $5,400 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 204 CY | $150 | $150 | $200 | $325 |
| 616E10000 WATER | 5 MGAL | $10.00 | $1.00 | $1.00 | $75.00 |
| 100E51200 DEPARTMENT'S SHARE OF THE DISPUTE RESOLUTION ADVIS | 19,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $25,000 | $32,000 | $75,000 | $40,000 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $15,000 | $5,000 | $15,000 | $2,500 |
| 111E10100 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 4,875 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $2,300 | $2,400 | $2,500 | $3,400 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (8976 CY | $155 | $1.39M | 24% |
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 3,017 CY | $230 | $694k | 12% |
| 827E11000 CEMENT | 2,804 TON | $195 | $547k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $476,500 | $477k | 8% |
| 827E20000 FULL DEPTH RECLAIMED BASE COURSE, 12" DEEP | 79,683 SY | $3.75 | $299k | 5% |
| 827E10000 PAVEMENT REMOVED | 79,683 SY | $3.5 | $279k | 5% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 2,000 HOUR | $100 | $200k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $200k | 3% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 810 CY | $150 | $122k | 2% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $650 | $121k | 2% |