WOO-IR 75-08.58 Weigh Station
WOO County · est $1.0M
Bid dateThursday, February 13—
WOO County · est $1.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 57 more items below.
| Item | Quantity | R1Geddis Paving & Excavating INC | R2Great Lakes Demolition Company | R3Advanced Excavating & Demolition | R4LLC Ebony Construction CO | % of bid |
|---|---|---|---|---|---|---|
| 452E15010 12" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 1,995 SY | $115 | $82.00 | $103 | $100 | 41% |
| 832E30000 EROSION CONTROL | 32,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 6% |
| 203E35110 GRANULAR MATERIAL, TYPE B | 555 CY | $52.00 | $60.00 | $64.00 | $58.00 | 5% |
| 442E22300 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 104 CY | $265 | $325 | $310 | $440 | 5% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 89 CY | $265 | $350 | $310 | $490 | 4% |
| 304E20000 AGGREGATE BASE | 334 CY | $61.00 | $60.00 |
| Item | Quantity | R1Geddis Paving & Excavating INC | R2Great Lakes Demolition Company | R3Advanced Excavating & Demolition | R4LLC Ebony Construction CO |
|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $1,000 | $100 | $5,000 | $21,000 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 72 FT | $60.00 | $20.00 | $12.00 | $44.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $500 | $450 | $650 | $518 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 12" | 45 FT | $60.00 | $25.00 | $35.00 | $74.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $73.00 |
| $89.00 |
| 4% |
| 203E35130 GRANULAR MATERIAL, TYPE D | 443 CY | $45.50 | $60.00 | $60.00 | $57.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $70,000 | $25,000 | $20,000 | 4% |
| 659E00300 TOPSOIL | 350 CY | $55.00 | $50.00 | $85.00 | $85.00 | 3% |
| 625E10490 LIGHT POLE, CONVENTIONAL, DESIGN A20B32.5 | 6 EACH | $2,924 | $3,000 | $3,397 | $3,000 | 3% |
| 204E13001 EXCAVATION OF SUBGRADE, AS PER PLAN | 997 CY | $16.00 | $20.00 | $18.00 | $21.50 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $10,500 | $15,000 | $7,400 | 3% |
| 202E23000 PAVEMENT REMOVED | 483 SY | $30.00 | $20.00 | $17.00 | $26.00 | 3% |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 902 FT | $14.50 | $17.00 | $17.25 | $18.00 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3.25" | 2,123 SY | $6.00 | $7.00 | $7.00 | $3.50 | 2% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 6 EACH | $1,750 | $1,500 | $2,046 | $1,800 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $6,500 | $15,000 | $5,200 | 2% |
| 203E10001 EXCAVATION, AS PER PLAN | 635 CY | $15.00 | $20.00 | $24.00 | $18.50 | 2% |
| 646E20200 PARKING LOT STALL MARKING | 1,846 FT | $4.95 | $3.00 | $3.00 | $3.10 | 2% |
| 625E29002 TRENCH, 24" DEEP | 902 FT | $8.25 | $10.00 | $11.00 | $8.35 | 1% |
| 203E20000 EMBANKMENT |
| 14 CY |
| $15.00 |
| $20.00 |
| $25.00 |
| $25.00 |
| 209E60200 LINEAR GRADING | 21 STA | $115 | $150 | $90.00 | $465 |
| 651E10000 TOPSOIL STOCKPILED | 220 CY | $5.00 | $15.00 | $27.00 | $25.35 |
| 652E10000 PLACING STOCKPILED TOPSOIL | 220 CY | $9.00 | $20.00 | $27.00 | $51.75 |
| 203E01890 SPECIAL - SOIL STERILANT | 6,000 SY | $0.35 | $0.80 | $0.55 | $0.75 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $755 | $80.00 | $180 | $143 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $67.00 | $200 | $60.00 | $61.00 |
| 659E10000 SEEDING AND MULCHING | 5,115 SY | $0.95 | $2.50 | $0.92 | $0.95 |
| 659E20000 COMMERCIAL FERTILIZER | 0.7 TON | $950 | $800 | $850 | $853 |
| 659E31000 LIME | 1.1 ACRE | $39.00 | $50.00 | $35.00 | $35.11 |
| 659E35000 WATER | 27.6 MGAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 62 FT | $45.00 | $15.00 | $36.00 | $14.00 |
| 611E01500 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 28 FT | $45.00 | $15.00 | $40.00 | $16.50 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $1,300 | $250 | $800 | $597 |
| 253E01000 PAVEMENT REPAIR | 54 SY | $86.00 | $85.00 | $105 | $85.00 |
| 407E10000 TACK COAT | 298 GAL | $3.00 | $4.00 | $3.00 | $2.75 |
| 617E10100 COMPACTED AGGREGATE | 38 CY | $76.50 | $75.00 | $90.00 | $130 |
| 625E00450 CONNECTION, FUSED PULL APART | 12 EACH | $188 | $125 | $164 | $195 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 21 EACH | $188 | $125 | $158 | $195 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 258 FT | $4.00 | $4.00 | $5.00 | $4.00 |
| 625E23410 NO. 12 AWG POLE AND BRACKET CABLE | 990 FT | $1.50 | $2.00 | $2.25 | $1.55 |
| 625E25500 CONDUIT, 3", 725.04 | 18 FT | $14.50 | $25.00 | $33.00 | $14.50 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 3" | 48 FT | $91.00 | $60.00 | $69.50 | $95.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 6 EACH | $528 | $450 | $513 | $550 |
| 625E30700 PULL BOX, 725.08, 18" | 3 EACH | $1,550 | $950 | $1,325 | $1,600 |
| 625E32000 GROUND ROD | 7 EACH | $475 | $250 | $326 | $490 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $3,246 | $7,500 | $7,500 | $3,450 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 920 FT | $2.50 | $2.00 | $2.00 | $2.30 |
| 625E75520 LUMINAIRE SUPPORT REMOVED | 9 EACH | $308 | $300 | $587 | $320 |
| 625E75522 LUMINAIRE SUPPORT FOUNDATION REMOVED, MIN 2FT DEPT | 9 EACH | $617 | $450 | $808 | $650 |
| 625E75550 DISTRIBUTION CABLE REMOVED | 6 FT | $308 | $2.00 | $7.00 | $320 |
| 621E00100 RPM (YELLOW/RED) | 12 EACH | $360 | $370 | $400 | $78.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 12 EACH | $42.00 | $60.00 | $40.00 | $20.00 |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 388 FT | $17.00 | $15.00 | $15.00 | $30.00 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 84 FT | $53.00 | $48.00 | $47.50 | $31.00 |
| 630E08302 GROUND MOUNTED WOODEN BOX BEAM SUPPORT, TYPE M BEA | 18 FT | $130 | $115 | $115 | $260 |
| 630E08600 SIGN POST REFLECTOR | 4 EACH | $50.50 | $45.00 | $45.00 | $26.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 4 EACH | $945 | $820 | $820 | $452 |
| 630E80100 SIGN, FLAT SHEET | 142 SF | $19.50 | $18.00 | $17.50 | $31.00 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 180 SF | $26.50 | $24.00 | $23.50 | $21.00 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 4 EACH | $1,550 | $1,500 | $1,120 | $925 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 8 EACH | $11.00 | $10.00 | $10.00 | $285 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 13 EACH | $22.50 | $20.00 | $20.00 | $290 |
| 646E10010 EDGE LINE, 6", WHITE | 0.22 MILE | $14,000 | $15,000 | $15,000 | $15,500 |
| 646E10010 EDGE LINE, 6", YELLOW | 0.24 MILE | $14,000 | $15,000 | $15,000 | $15,500 |
| 646E10310 CHANNELIZING LINE, 12" | 257 FT | $5.05 | $2.00 | $2.00 | $2.10 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 278 FT | $13.50 | $10.00 | $10.00 | $10.50 |
| 646E20320 WRONG WAY ARROW | 2 EACH | $280 | $500 | $500 | $510 |
| 646E50000 REMOVAL OF PAVEMENT MARKING | 8 EACH | $95.00 | $50.00 | $50.00 | $52.00 |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 1,472 FT | $1.70 | $2.50 | $2.50 | $3.00 |
| 614E12500 REPLACEMENT SIGN | 5 EACH | $130 | $200 | $192 | $195 |
| 614E12600 REPLACEMENT DRUM | 5 EACH | $75.00 | $60.00 | $56.00 | $57.25 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,000 | $8,500 | $16,000 | $10,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E15010 12" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 1,995 SY | $115 | $229k | 33% |
| 832E30000 EROSION CONTROL | 32,000 EACH | $1 | $32k | 5% |
| 203E35110 GRANULAR MATERIAL, TYPE B | 555 CY | $52 | $29k | 4% |
| 442E22300 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 104 CY | $265 | $28k | 4% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 89 CY | $265 | $24k | 3% |
| 304E20000 AGGREGATE BASE | 334 CY | $61 | $20k | 3% |
| 203E35130 GRANULAR MATERIAL, TYPE D | 443 CY | $45.5 | $20k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 3% |
| 659E00300 TOPSOIL | 350 CY | $55 | $19k | 3% |
| 625E10490 LIGHT POLE, CONVENTIONAL, DESIGN A20B32.5 | 6 EACH | $2,924 | $18k | 3% |