ALL-Harrod Improvements
ALL County · est $2.2M
Bid dateThursday, April 24—
ALL County · est $2.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 42 more items below.
| Item | Quantity | R1R D Jones Excavating INC | R2Fenson Contracting LLC | R3Vernon Nagel INC | R4Miller Contracting Group INC | R5Underground Utilities INC | R6Helms And Sons Excavating | % of bid |
|---|---|---|---|---|---|---|---|---|
| 204E30010 GRANULAR MATERIAL, TYPE B | 3,490 CY | $42.78 | $50.00 | $62.00 | $64.00 | $50.00 | $60.00 | 11% |
| 608E10000 4" CONCRETE WALK | 17,978 SF | $7.90 | $8.40 | $7.75 | $10.10 | $10.00 | $9.00 | 11% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 746 CY | $184 | $192 | $175 |
| Item | Quantity | R1R D Jones Excavating INC | R2Fenson Contracting LLC | R3Vernon Nagel INC | R4Miller Contracting Group INC | R5Underground Utilities INC | R6Helms And Sons Excavating |
|---|---|---|---|---|---|---|---|
| 202E32000 CURB REMOVED | 3,446 FT | $1.75 | $6.25 | $6.00 | $3.30 | $2.00 | $8.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 510 FT | $12.80 | $40.00 | $15.00 | $28.50 | $45.00 | $25.00 |
| 202E58100 CATCH BASIN REMOVED | 13 EACH | $365 | $325 | $275 | $373 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $189 |
| $185 |
| $238 |
| 11% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 627 CY | $212 | $230 | $195 | $210 | $220 | $280 | 10% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 4,555 FT | $27.00 | $24.25 | $24.00 | $26.10 | $30.00 | $29.00 | 9% |
| 304E20000 AGGREGATE BASE | 2,020 CY | $42.78 | $54.00 | $64.00 | $55.10 | $50.00 | $60.00 | 7% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (435 CY | $194 | $210 | $180 | $194 | $200 | $258 | 6% |
| 638E01711 8" WATER MAIN POLYVINYL CHLORIDE PIPE AND FITTINGS | 450 FT | $113 | $265 | $160 | $182 | $100 | $265 | 4% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,369 SF | $21.30 | $10.75 | $20.00 | $11.00 | $11.00 | $23.00 | 4% |
| 611E98180 CATCH BASIN, NO. 3A | 17 EACH | $2,450 | $3,750 | $3,500 | $2,722 | $3,400 | $3,575 | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 3,490 CY | $11.65 | $25.00 | $15.00 | $37.00 | $33.00 | $30.00 | 3% |
| 202E23000 PAVEMENT REMOVED | 10,136 SY | $4.00 | $4.25 | $12.00 | $5.20 | $25.00 | $15.00 | 3% |
| 202E30000 WALK REMOVED | 16,197 SF | $2.25 | $1.75 | $3.50 | $0.80 | $1.50 | $3.00 | 3% |
| 611E10400 24" CONDUIT, TYPE B | 736 FT | $48.60 | $87.25 | $130 | $88.40 | $224 | $133 | 3% |
| 611E04400 12" CONDUIT, TYPE B | 1,011 FT | $33.50 | $62.25 | $90.00 | $43.70 | $170 | $118 | 3% |
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 286 SY | $99.90 | $112 | $100 | $139 | $115 | $115 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,750 | $25,500 | $10,000 | $34,524 | $40,000 | $75,000 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $100,000 | $100,000 | $141,450 | $100,000 | $150,000 | 2% |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 230 SY | $82.90 | $108 | $80.00 | $116 | $95.00 | $92.00 | 1% |
| 638E04900 1" COPPER SERVICE BRANCH | 600 FT | $31.50 | $70.00 | $30.00 | $98.30 | $20.00 | $85.00 | 1% |
| $400 |
| $375 |
| 203E10000 EXCAVATION | 755.6 CY | $11.65 | $21.50 | $30.00 | $22.90 | $60.00 | $30.00 |
| 203E20000 EMBANKMENT | 82.5 CY | $7.50 | $14.00 | $30.00 | $20.60 | $30.00 | $32.00 |
| 204E10000 SUBGRADE COMPACTION | 10,984 SY | $0.75 | $1.00 | $1.00 | $1.70 | $0.50 | $2.00 |
| 204E45000 PROOF ROLLING | 6 HOUR | $185 | $150 | $350 | $238 | $230 | $150 |
| 204E50000 GEOTEXTILE FABRIC | 8,955 SY | $1.85 | $1.15 | $1.25 | $1.10 | $0.60 | $1.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE1-1/2" | 6,091 SY | $2.60 | $2.15 | $3.20 | $2.80 | $3.50 | $4.00 |
| 254E01600 PATCHING PLANED SURFACE | 122 SY | $11.00 | $20.00 | $15.00 | $15.50 | $18.00 | $18.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 8 EACH | $1,150 | $1,350 | $1,000 | $620 | $800 | $1,000 |
| 659E00300 TOPSOIL | 134 CY | $42.15 | $120 | $40.00 | $90.00 | $60.00 | $50.00 |
| 659E10000 SEEDING AND MULCHING | 3,789 SY | $1.75 | $2.50 | $3.25 | $2.00 | $10.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.51 TON | $850 | $850 | $850 | $917 | $100 | $600 |
| 659E35000 WATER | 20.5 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $110 | $4.00 |
| 832E30000 EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E05900 15" CONDUIT, TYPE B | 87 FT | $36.25 | $84.50 | $110 | $73.00 | $190 | $125 |
| 611E07400 18" CONDUIT, TYPE B | 434 FT | $43.00 | $72.75 | $125 | $66.20 | $200 | $116 |
| 611E98150 CATCH BASIN, NO. 3 | 4 EACH | $2,885 | $4,260 | $5,200 | $3,833 | $4,400 | $4,450 |
| 611E98370 CATCH BASIN, NO. 6 | 1 EACH | $3,010 | $3,400 | $3,800 | $3,047 | $3,700 | $4,350 |
| 611E98470 CATCH BASIN, NO. 2-2B | 3 EACH | $1,660 | $2,800 | $2,200 | $1,655 | $2,000 | $2,900 |
| 611E99574 MANHOLE, NO. 3 | 3 EACH | $2,560 | $4,800 | $5,300 | $3,665 | $5,500 | $4,850 |
| 407E20000 NON-TRACKING TACK COAT | 1,320 GAL | $2.50 | $3.05 | $4.00 | $5.00 | $3.00 | $3.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 11 EACH | $275 | $500 | $300 | $457 | $300 | $950 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 273.5 FT | $17.15 | $12.60 | $12.00 | $13.00 | $12.00 | $12.00 |
| 630E08520 STREET NAME SIGN SUPPORT, NO. 3 POST | 57.5 FT | $17.15 | $12.60 | $12.00 | $13.00 | $12.00 | $12.00 |
| 630E08600 SIGN POST REFLECTOR | 50 EACH | $63.15 | $42.00 | $40.00 | $43.20 | $40.00 | $40.00 |
| 630E80100 SIGN, FLAT SHEET | 131.16 SF | $19.86 | $25.25 | $24.00 | $25.90 | $24.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 33 EACH | $16.09 | $15.75 | $15.00 | $17.00 | $15.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $62.32 | $52.50 | $50.00 | $54.00 | $50.00 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 28 EACH | $21.46 | $15.75 | $15.00 | $17.00 | $15.00 | $15.00 |
| 642E00300 CENTER LINE, TYPE 1 | 0.86 MILE | $6,450 | $6,775 | $2,000 | $2,157 | $2,000 | $2,000 |
| 643E00500 STOP LINE | 158 FT | $8.80 | $9.25 | $7.00 | $7.60 | $7.00 | $7.00 |
| 643E00620 CROSSWALK LINE, 12" | 612 FT | $8.35 | $8.75 | $5.00 | $5.40 | $5.00 | $5.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 74 CY | $42.78 | $115 | $60.00 | $44.00 | $100 | $60.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,675 | $3,150 | $3,000 | $13,909 | $6,000 | $4,500 |
| 616E10000 WATER | 20 MGAL | $1.00 | $65.00 | $10.00 | $136 | $110 | $25.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,600 | $17,000 | $20,000 | $22,318 | $50,000 | $25,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,850 | $58,000 | $15,000 | $17,693 | $30,000 | $35,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $14,600 | $25,500 | $15,000 | $15,720 | $35,000 | $30,000 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $3,120 | $1,950 | $3,000 | $4,313 | $3,000 | $10,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $3,120 | $1,950 | $2,500 | $4,313 | $3,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 204E30010 GRANULAR MATERIAL, TYPE B | 3,490 CY | $42.78 | $149k | 10% |
| 608E10000 4" CONCRETE WALK | 17,978 SF | $7.9 | $142k | 9% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 746 CY | $184 | $137k | 9% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 627 CY | $212 | $133k | 9% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 4,555 FT | $27 | $123k | 8% |
| 304E20000 AGGREGATE BASE | 2,020 CY | $42.78 | $86k | 6% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (435 CY | $194 | $84k | 5% |
| 638E01711 8" WATER MAIN POLYVINYL CHLORIDE PIPE AND FITTINGS | 450 FT | $112.65 | $51k | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,369 SF | $21.3 | $50k | 3% |
| 611E98180 CATCH BASIN, NO. 3A | 17 EACH | $2,450 | $42k | 3% |