BEL-IR 70-10.08
BEL County
Bid dateThursday, July 17—
BEL County
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 10 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Lms Construction INC | R3Axis Civil Construction LLC | R4Stanley Miller Construction Company | % of bid |
|---|---|---|---|---|---|---|
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $68,000 | $62,500 | $38,000 | $60,000 | 20% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 84" CO | 284 FT | $220 | $300 | $185 | $363 | 18% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 236 CY | $158 | $200 | $235 | $300 | 11% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 940 FT | $34.00 | $25.00 | $28.00 | $67.00 | 9% |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 76 SY | $385 | $250 | $450 | $250 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $16,609 | $23,300 | $40,000 |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Lms Construction INC | R3Axis Civil Construction LLC | R4Stanley Miller Construction Company |
|---|---|---|---|---|---|
| 202E75000 FENCE REMOVED | 84 FT | $4.40 | $6.00 | $10.00 | $20.00 |
| 203E10000 EXCAVATION | 5 CY | $93.00 | $500 | $100 | $500 |
| 203E20000 EMBANKMENT | 1 CY | $575 | $1,000 | $300 | $1,000 |
| 659E14000 REPAIR SEEDING AND MULCHING | 36 SY | $5.00 | $3.00 | $4.00 | $5.00 |
| 659E20000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $65,000 |
| 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $16,000 | $10,000 | $45,000 | $14,222 | 5% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 15 CY | $1,015 | $150 | $240 | $200 | 4% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 284 FT | $32.00 | $190 | $90.00 | $337 | 3% |
| 619E16000 FIELD OFFICE, TYPE A | 2 MNTH | $4,000 | $1,500 | $2,800 | $3,000 | 2% |
| 614E12200 SPECIAL - WORK ZONE GUARDRAIL | 100 FT | $74.55 | $35.00 | $78.00 | $100 | 2% |
| 607E15000 FENCE, TYPE 47 | 117 FT | $62.00 | $35.00 | $49.50 | $65.00 | 2% |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $3,525 | $2,300 | $3,200 | $5,000 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,600 | $4,000 | $35,000 | $35,000 | 2% |
| 659E00300 TOPSOIL | 80 CY | $80.00 | $10.00 | $90.00 | $100 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,015 | $14,500 | $5,000 | $12,000 | 1% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 659E10000 SEEDING AND MULCHING | 717 SY | $5.00 | $3.00 | $4.00 | $10.00 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $500 | $3,500 | $22,000 | 1% |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $375 | $50.00 | $150 | $150 | 0% |
| 0.1 TON |
| $1,600 |
| $3,000 |
| $1,250 |
| $800 |
| 659E31000 LIME | 0.15 ACRE | $200 | $3,000 | $150 | $150 |
| 659E35000 WATER | 5 MGAL | $1.00 | $10.00 | $1.00 | $1.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, (ONE-WAY) | 18 EACH | $25.00 | $20.00 | $20.00 | $35.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 18 EACH | $38.00 | $20.00 | $27.00 | $50.00 |
| 616E10000 WATER | 5 MGAL | $12.50 | $10.00 | $1.00 | $1.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $68,000 | $68k | 19% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN, 84" CO | 284 FT | $220 | $62k | 18% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 236 CY | $158 | $37k | 11% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 940 FT | $34 | $32k | 9% |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 76 SY | $385 | $29k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $16,609 | $17k | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $16,000 | $16k | 5% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 15 CY | $1,015 | $15k | 4% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 284 FT | $32 | $9k | 3% |
| 619E16000 FIELD OFFICE, TYPE A | 2 MNTH | $4,000 | $8k | 2% |