BEL-US 40-23.26
BEL County · est $19M
Bid dateThursday, April 24—
BEL County · est $19M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 146 more items below.
| Item | Quantity | R1Beaver Excavating Company | % of bid |
|---|---|---|---|
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $4,000,000 | 30% |
| 515E12010 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 260 EACH | $7,500 | 15% |
| 624E10000 MOBILIZATION | 1 LS | $850,000 | 6% |
| 516E46900 BEARING DEVICE, MISC.:ELASTOMERIC BEARING WITH LOA | 1,760 EACH | $455 | 6% |
| 511E53012 CLASS QC2 CONCRETE, MISC.:BRIDGE DECK (PARAPET) WI | 274 CY | $2,150 | 4% |
| 511E31612 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 713 CY | $800 | 4% |
| 530E00400 SPECIAL - STRUCTURESPIER FLOORBEAM SHORING | 3 EACH | $180,000 | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 323,582 LB | $1.65 | 4% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 12,574 SY | $42.00 | 4% |
| 519E11600 SPECIAL - PATCHING CONCRETE STRUCTURETYPE 1 REPAIR | 2,658 SF | $185 | 4% |
| 844E20000 GALVANIC ANODE PROTECTION | 4,570 EACH | $94.00 | 3% |
| AA2 511E34413 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE, AS | 138 CY | $3,000 | 3% |
| 516E11210 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 467 FT | $650 | 2% |
| 625E25920 CONDUIT, MISC.: AT&T 4" CONDUIT | 3,090 FT | $75.00 | 2% |
| 515E12010 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 30 EACH | $7,500 | 2% |
| 515E12010 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 30 EACH | $7,500 | 2% |
| 511E41510 CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS | 66 CY | $3,025 | 1% |
| 515E12000 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 26 EACH | $7,500 | 1% |
| 519E11600 SPECIAL - PATCHING CONCRETE STRUCTURETYPE 2 REPAIR | 565 SF | $275 | 1% |
| 511E53010 CLASS QC1 CONCRETE, MISC.:MOMENT SLAB | 140 CY | $1,075 | 1% |
| Item | Quantity | R1Beaver Excavating Company |
|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $82,500 |
| 202E23000 PAVEMENT REMOVED | 1,738 SY | $25.00 |
| 202E30000 WALK REMOVED | 31 SF | $10.00 |
| 202E30700 CONCRETE BARRIER REMOVED | 20 FT | $65.00 |
| 202E32000 CURB REMOVED | 76 FT | $11.00 |
| 202E32600 GUTTER REMOVED | 204 FT | $9.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 60 FT | $55.00 |
| 202E38000 GUARDRAIL REMOVED | 225 FT | $3.50 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 2 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $250 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 2 EACH | $135 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $365 |
| 203E10000 EXCAVATION | 480 CY | $40.00 |
| 203E20000 EMBANKMENT | 24 CY | $52.00 |
| 204E10000 SUBGRADE COMPACTION | 1,981 SY | $5.50 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 93.7 FT | $55.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E(MASH 2016) | 1 EACH | $2,700 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,350 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 1 EACH | $2,750 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $550 |
| 608E10000 4" CONCRETE WALK | 35 SF | $50.00 |
| 622E90200 BARRIER, MISC.:BARRIER TRANSITION NORTH | 1 EACH | $9,500 |
| 622E90200 BARRIER, MISC.:BARRIER TRANSITION SOUTH | 1 EACH | $7,500 |
| 601E21100 SLOPE PROTECTION, MISC.:GROUT FILLED FABRIC MAT | 109 SY | $550 |
| 601E38400 PAVED GUTTER, TYPE 2 | 192 FT | $65.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $125 |
| 659E00300 TOPSOIL | 69 CY | $110 |
| 659E10000 SEEDING AND MULCHING | 618 SY | $8.52 |
| 659E14000 REPAIR SEEDING AND MULCHING | 31 SY | $0.80 |
| 659E15000 INTER-SEEDING | 31 SY | $0.80 |
| 659E20000 COMMERCIAL FERTILIZER | 0.09 TON | $891 |
| 659E31000 LIME | 0.13 ACRE | $155 |
| 659E35000 WATER | 3 MGAL | $1.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $7,500 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $20,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $15,000 |
| 832E30000 EROSION CONTROL | 35,000 EACH | $1.00 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 470 FT | $35.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 35 FT | $55.00 |
| 611E04400 12" CONDUIT, TYPE B | 50 FT | $144 |
| 611E98370 CATCH BASIN, NO. 6 | 2 EACH | $3,550 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 2 EACH | $1,045 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $1,035 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $585 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 50 LB | $4.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(T=3") | 587 SY | $16.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(T=4") | 136 SY | $16.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 270 FT | $3.50 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 246 CY | $300 |
| 304E20000 AGGREGATE BASE | 341 CY | $140 |
| 305E12010 8" CONCRETE BASE, CLASS QC 1P | 694 SY | $135 |
| 407E13900 TACK COAT, 702.13 | 310 GAL | $4.50 |
| 408E10001 PRIME COAT, AS PER PLAN | 34 GAL | $20.00 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 86 CY | $500 |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (197 CY | $360 |
| 609E16000 CURB, TYPE 2-B | 28 FT | $90.00 |
| 609E24500 CURB, TYPE 4-B | 18 FT | $98.00 |
| 609E26000 CURB, TYPE 6 | 129 FT | $70.00 |
| 617E10100 COMPACTED AGGREGATE | 5 CY | $460 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 39 FT | $24.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 13.5 FT | $25.00 |
| 630E80100 SIGN, FLAT SHEET | 19.8 SF | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 5 EACH | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3 EACH | $25.00 |
| 646E10010 EDGE LINE, 6" | 0.8 MILE | $11,250 |
| 646E10110 LANE LINE, 6" | 0.02 MILE | $9,690 |
| 646E10200 CENTER LINE | 0.3 MILE | $16,200 |
| 646E10400 STOP LINE | 21 FT | $12.00 |
| 646E10510 CROSSWALK LINE, 12" | 68 FT | $7.50 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 322 FT | $7.00 |
| 646E20600 BIKE LANE SYMBOL MARKING | 5 EACH | $310 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 8 EACH | $10,000 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,350 |
| 614E12420 DETOUR SIGNING | 1 LS | $15,000 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $400 |
| 614E13310 BARRIER REFLECTOR, TYPE 1(ONE WAY) | 123 EACH | $20.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 123 EACH | $22.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 36 SNMT | $1,500 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.67 MILE | $14,500 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 1.38 MILE | $9,950 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 42 FT | $12.00 |
| 616E10000 WATER | 2 MGAL | $175 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,635 FT | $25.00 |
| 690E98400 SPECIAL - WORK INVOLVING ASBESTOS CONTAINING MATER | 1 LS | $100 |
| 202E22900 APPROACH SLAB REMOVED | 184 SY | $45.00 |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $35,000 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 500 LB | $80.00 |
| 509E27000 CHROMIUM STEEL REINFORCEMENT | 16,475 LB | $3.35 |
| 509E30020 NO. 4 DEFORMED GFRP REINFORCEMENT | 11,611 FT | $2.25 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 112 EACH | $37.00 |
| 511E33412 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 44 CY | $3,025 |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 23 CY | $2,955 |
| 511E51512 CLASS QC2 CONCRETE WITH QC/QA, SIDEWALK | 99 CY | $620 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 435 SY | $18.00 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 793 FT | $150 |
| 515E12000 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 3 EACH | $7,500 |
| 515E12000 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 2 EACH | $7,500 |
| 515E12000 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 3 EACH | $7,500 |
| 515E12010 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 20 EACH | $7,500 |
| 515E12040 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $20,000 |
| 515E12040 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $20,000 |
| 515E12040 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $20,000 |
| 515E12040 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $20,000 |
| 515E12040 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $20,000 |
| 515E12040 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $20,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 3 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 1 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 2 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 2 EACH | $15,000 |
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 10 EACH | $15,000 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 89 SF | $8.00 |
| 516E41100 1/8" PREFORMED BEARING PAD, TYPE CDP | 440 EACH | $75.00 |
| 516E42000 ELASTOMERIC BEARING PAD, MISC.:16" x 18" PLAIN ELA | 39 EACH | $200 |
| 516E42600 ELASTOMERIC BEARING PAD, MISC.:2" x 6" PLAIN ELAST | 33 FT | $140 |
| 518E12000 SCUPPERS, INCLUDING SUPPORTS | 8 EACH | $3,000 |
| 519E00100 SPECIAL - COMPOSITE FIBER WRAP SYSTEM | 1,609 SF | $75.00 |
| 526E15011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 96 SY | $630 |
| 526E25011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 115 SY | $650 |
| 526E90010 TYPE A INSTALLATION | 106 FT | $200 |
| 530E00200 SPECIAL - STRUCTURESARCH SPANS ERECTION ENGINEERIN | 1 LS | $70,000 |
| 601E27001 DUMPED ROCK FILL, TYPE C, AS PER PLAN | 18 CY | $230 |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 304 CY | $140 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $150,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 |
| 619E16010 FIELD OFFICE, TYPE B | 18 MNTH | $3,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $70,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $4,000,000 | $4.00M | 24% |
| 515E12010 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 260 EACH | $7,500 | $1.95M | 11% |
| 624E10000 MOBILIZATION | 1 LS | $850,000 | $850k | 5% |
| 516E46900 BEARING DEVICE, MISC.:ELASTOMERIC BEARING WITH LOA | 1,760 EACH | $455 | $801k | 5% |
| 511E53012 CLASS QC2 CONCRETE, MISC.:BRIDGE DECK (PARAPET) WI | 274 CY | $2,150 | $589k | 3% |
| 511E31612 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 713 CY | $800 | $570k | 3% |
| 530E00400 SPECIAL - STRUCTURESPIER FLOORBEAM SHORING | 3 EACH | $180,000 | $540k | 3% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 323,582 LB | $1.65 | $534k | 3% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 12,574 SY | $42 | $528k | 3% |
| 519E11600 SPECIAL - PATCHING CONCRETE STRUCTURETYPE 1 REPAIR | 2,658 SF | $185 | $492k | 3% |