POR-SR 82/SR 306-02.37/00.00
POR County · est $2.6M
Bid dateThursday, February 19—
POR County · est $2.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 41 more items below.
| Item | Quantity | R1Geauga Highway CO | R2Karvo Companies INC | R3Ronyak Paving INC | R4Shelly Company | R5Phillips Paving LLC | % of bid |
|---|---|---|---|---|---|---|---|
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (3175 CY | $200 | $165 | $158 | $160 | $190 | 38% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2.5") | 91,424 SY | $3.37 | $1.80 | $2.00 | $2.00 | $2.00 | 19% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $128,000 | $120,939 | $120,000 | $140,500 | $215,000 | 8% |
| 251E01010 PARTIAL DEPTH PAVEMENT REPAIR (441) | 167 CY | $650 | $375 | $535 | $500 | $365 | 7% |
| 253E02000 PAVEMENT REPAIR | 134 CY | $600 | $425 | $425 | $500 | $365 | 5% |
| 407E20000 NON-TRACKING TACK COAT | 13,717 GAL |
| Item | Quantity | R1Geauga Highway CO | R2Karvo Companies INC | R3Ronyak Paving INC | R4Shelly Company | R5Phillips Paving LLC |
|---|---|---|---|---|---|---|
| 202E23500 WEARING COURSE REMOVED | 26 SY | $45.00 | $15.00 | $55.00 | $45.00 | $3.00 |
| 202E98100 REMOVAL MISC.: BARRIER REFLECTOR | 51 EACH | $10.00 | $5.00 | $5.00 | $15.00 | $10.00 |
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 23 CY | $80.00 | $25.00 | $30.00 | $60.00 | $25.00 |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 6 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $3.50 |
| $2.30 |
| $2.00 |
| $2.75 |
| $2.00 |
| 3% |
| 856E10000 BRIDGE DECK WATERPROOFING ASPHALT CONCRETE | 32 CY | $1,400 | $1,095 | $850 | $1,000 | $1,000 | 3% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 317 CY | $120 | $115 | $125 | $90.00 | $95.00 | 2% |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 6 MILE | $6,000 | $1,000 | $500 | $800 | $250 | 2% |
| 646E10010 EDGE LINE, 6" | 10.35 MILE | $3,118 | $3,118 | $3,118 | $3,118 | $3,118 | 2% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 17 EACH | $1,780 | $1,550 | $1,550 | $1,550 | $1,550 | 2% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 31 CF | $750 | $552 | $575 | $585 | $600 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 24 SNMT | $950 | $850 | $850 | $850 | $850 | 1% |
| 646E10200 CENTER LINE | 5.55 MILE | $3,900 | $3,900 | $3,900 | $3,900 | $3,900 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 4,554 GAL | $4.50 | $4.50 | $2.00 | $5.00 | $2.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,500 | $22,880 | $15,174 | $8,000 | $50,000 | 1% |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 28 CY | $550 | $185 | $550 | $250 | $350 | 1% |
| 209E60200 LINEAR GRADING | 137 STA | $110 | $50.00 | $25.00 | $55.00 | $25.00 | 1% |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 1,845 FT | $7.45 | $7.45 | $7.45 | $7.45 | $7.45 | 1% |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 11.1 MILE | $995 | $995 | $995 | $995 | $995 | 1% |
| $800 |
| $1,400 |
| $1,300 |
| $1,400 |
| $1,750 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $8,500 | $679 | $1,000 | $7,500 | $2,500 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 8 EACH | $1,200 | $1,500 | $1,200 | $1,500 | $3,000 |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 23 CY | $100 | $25.00 | $40.00 | $60.00 | $75.00 |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 3,248 CY | — | $184 | $190 | $192 | $200 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $600 | $185 | $1,000 | $550 | $1,250 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 1 EACH | $1,000 | $1,500 | $1,000 | $1,500 | $2,500 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 63 EACH | $22.50 | $22.50 | $22.50 | $22.50 | $22.50 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $20.00 | $17.50 | $17.50 | $17.50 | $17.50 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 2 SF | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $150 | $15.00 | $15.00 | $15.00 | $15.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $100 | $15.00 | $15.00 | $15.00 | $15.00 |
| 646E10300 CHANNELIZING LINE, 8" | 2,350 FT | $1.62 | $1.62 | $1.62 | $1.65 | $1.62 |
| 646E10400 STOP LINE | 243 FT | $11.50 | $11.50 | $11.50 | $11.50 | $11.50 |
| 646E10520 CROSSWALK LINE, 24" | 518 FT | $11.50 | $11.50 | $11.50 | $11.50 | $11.50 |
| 646E10800 ISLAND MARKING | 161 SF | $6.55 | $6.55 | $6.55 | $6.55 | $6.55 |
| 646E20110 SCHOOL SYMBOL MARKING, 96" | 2 EACH | $650 | $650 | $650 | $650 | $650 |
| 646E20300 LANE ARROW | 59 EACH | $160 | $160 | $160 | $160 | $160 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $100 | $125 | $125 | $120 | $75.00 |
| 614E12460 WORK ZONE MARKING SIGN | 20 EACH | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $150 | $500 | $550 | $125 | $500 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 5.55 MILE | $895 | $895 | $895 | $895 | $895 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 10.35 MILE | $595 | $595 | $595 | $595 | $595 |
| 614E23000 WORK ZONE CHANNELIZING LINE, CLASS I, 8" | 4,700 FT | $0.58 | $0.58 | $0.58 | $0.60 | $0.58 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 2,350 FT | $0.52 | $0.52 | $0.52 | $0.55 | $0.52 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 486 FT | $3.20 | $3.20 | $3.20 | $3.20 | $3.20 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 243 FT | $2.95 | $2.95 | $2.95 | $2.95 | $2.95 |
| 202E23500 WEARING COURSE REMOVED (T = 3") | 554 SY | $12.50 | $3.50 | $25.00 | $15.00 | $8.00 |
| 202E23500 WEARING COURSE REMOVED (T = 4") | 122 SY | $14.00 | $10.50 | $50.00 | $15.00 | $10.00 |
| 407E13900 TACK COAT, 702.13 | 54 GAL | $18.00 | $2.30 | $25.00 | $10.00 | $5.00 |
| 407E20000 NON-TRACKING TACK COAT | 41 GAL | $18.00 | $2.30 | $25.00 | $2.75 | $2.00 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 78 FT | $35.00 | $28.75 | $28.62 | $30.00 | $30.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 340 FT | $20.00 | $17.50 | $17.29 | $15.00 | $18.00 |
| 519E10000 PATCHING CONCRETE BRIDGE DECK OVERLAY WITH MICRO-S | 7 SY | $500 | $1,076 | $1,076 | $1,000 | $1,100 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $1,250 | $3,000 | $1,500 | $4,000 | $1,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $2,500 | $5,780 | $5,000 | $2,500 |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $125,000 | $117,125 | $100,000 | $168,150 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (3175 CY | $200 | $635k | 36% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2.5") | 91,424 SY | $3.37 | $308k | 17% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $128,000 | $128k | 7% |
| 251E01010 PARTIAL DEPTH PAVEMENT REPAIR (441) | 167 CY | $650 | $109k | 6% |
| 253E02000 PAVEMENT REPAIR | 134 CY | $600 | $80k | 4% |
| 407E20000 NON-TRACKING TACK COAT | 13,717 GAL | $3.5 | $48k | 3% |
| 856E10000 BRIDGE DECK WATERPROOFING ASPHALT CONCRETE | 32 CY | $1,400 | $45k | 3% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 317 CY | $120 | $38k | 2% |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 6 MILE | $6,000 | $36k | 2% |
| 646E10010 EDGE LINE, 6" | 10.35 MILE | $3,118 | $32k | 2% |