Figure 0.1 · BRIEFING
BID #268005 · ODOTRESULT · awarded Apr 9

MED-IR 71 Rest Areas TP

MED County · est $5.5M

Bid dateThursday, April 9
Awarded toGREAT LAKES CONSTRUCTION CO$5.04M
read → connected → answeredcassandri

Project scope

Bid form · ODOT

123ITEMS
  • Signals & Lighting13%
  • Removal & Demolition12%
  • Earthwork10%
  • Drainage10%
  • Structures / Bridge8%
  • Erosion & Landscaping7%
  • Other40%

Top items by winning bid

ItemQtyUnit priceExtended%
301E56000 ASPHALT CONCRETE BASE, PG64-22, (449)5,619 CY$160$899k18%
442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE2,333 CY$206$481k10%
304E20000 AGGREGATE BASE6,256 CY$70$438k9%
442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A (1,399 CY$225$315k6%
203E10000 EXCAVATION13,458 CY$20.3$273k5%
624E10000 MOBILIZATION Section 12 - INCIDENTALS - Totals Awd $424,700.00 2 $430,353.50 3 $468,000.001 LS$251,000$251k5%
605E06000 4" BASE PIPE UNDERDRAINS16,950 FT$12.25$208k4%
202E23000 PAVEMENT REMOVED20,688 SY$9$186k4%
206E10500 CEMENT927 TON$190$176k3%
609E28000 CURB, TYPE 74,947 FT$27$134k3%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 103 more items below.

Rank 1Great Lakes Construction CO$5.04MRank 2Kokosing Construction Company INC$5.43MRank 3Karvo Companies INC$5.53M
ItemQuantityR1Great Lakes Construction COR2Kokosing Construction Company INCR3Karvo Companies INC
301E56000 ASPHALT CONCRETE BASE, PG64-22, (449)5,619 CY$160$190$180
442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE2,333 CY$206$263$235
304E20000 AGGREGATE BASE6,256 CY$70.00$75.00$80.00
442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A (1,399 CY$225$305$285
203E10000 EXCAVATION13,458 CY$20.30$21.00$20.00
624E10000 MOBILIZATION Section 12 - INCIDENTALS - Totals Awd $424,700.00 2 $430,353.50 3 $468,000.001 LS$251,000$270,000$200,000
605E06000 4" BASE PIPE UNDERDRAINS16,950 FT$12.25$11.00$12.00
202E23000 PAVEMENT REMOVED20,688 SY$9.00$9.00$20.50
206E10500 CEMENT927 TON$190$185$199
609E28000 CURB, TYPE 74,947 FT$27.00$25.00$18.00
206E15020 CEMENT STABILIZED SUBGRADE, 14 INCHES DEEP35,817 SY$3.31$4.80$2.50
659E00300 TOPSOIL2,891 CY$40.00$17.50$10.00
832E30000 EROSION CONTROL94,398 EACH$1.00$1.00$1.00
614E11000 MAINTAINING TRAFFIC1 LS$86,000$68,554$25,000
611E05900 15" CONDUIT, TYPE B743 FT$110$125$75.00
203E20000 EMBANKMENT6,291 CY$10.50$2.40$12.00
611E98180 CATCH BASIN, NO. 3A11 EACH$5,100$4,425$5,000
625E26262 LUMINAIRE, HIGH MAST, SOLID STATE (LED), HMLED4_P336 EACH$1,379$1,200$1,373
201E11001 CLEARING AND GRUBBING, AS PER PLAN1 LS$46,750$31,570$50,000
601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT403 SY$115$85.00$50.00
Show all 123 line items
ItemQuantityR1Great Lakes Construction COR2Kokosing Construction Company INCR3Karvo Companies INC
202E30000 WALK REMOVED13,676 SF$1.20$2.25$1.75
202E32000 CURB REMOVED5,486 FT$1.65$3.15$8.50
202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER404 FT$16.50$14.00$22.00
202E38000 GUARDRAIL REMOVED1,509 FT$2.00$2.00$2.00
202E58000 MANHOLE REMOVED4 EACH$700$1,100$500
202E58100 CATCH BASIN REMOVED5 EACH$700$750$500
202E66000 SPECIAL - DRILLED WATER WELL ABANDONED2 EACH$4,795$1,750$750
202E75000 FENCE REMOVED63 FT$5.00$5.00$7.00
202E98000 REMOVAL MISC.: GROUND MOUNTED SIGNS AND POST SUPPO1 LS$1,300$1,500$1,575
202E98000 REMOVAL MISC.: SANITARY PUMP STATION1 LS$13,000$9,500$6,500
202E98100 REMOVAL MISC.: BOULDER1 EACH$200$150$500
202E98100 REMOVAL MISC.: CONCRETE PICNIC TABLE27 EACH$100$150$100
202E98100 REMOVAL MISC.: DRINKING FOUNTAIN1 EACH$250$350$250
202E98100 REMOVAL MISC.: FLAG POLE2 EACH$500$1,000$250
202E98100 REMOVAL MISC.: GRILL9 EACH$400$125$100
202E98100 REMOVAL MISC.: NEWSPAPER BOXES1 EACH$250$650$225
202E98100 REMOVAL MISC.: VENDING MACHINE3 EACH$500$725$150
202E98100 REMOVAL MISC.: WOOD POST1 EACH$100$32.00$250
202E98400 REMOVAL MISC.: CONCRETE PAD4,972 SF$2.00$2.00$2.50
204E10000 SUBGRADE COMPACTION102 SY$5.00$12.50$3.00
204E45000 PROOF ROLLING17 HOUR$400$160$250
206E11000 CURING COAT35,817 SY$1.20$1.20$1.10
606E15050 GUARDRAIL, TYPE MGS837.5 FT$21.60$21.60$21.60
606E26100 ANCHOR ASSEMBLY, TYPE E2 EACH$2,075$2,075$2,075
606E26500 ANCHOR ASSEMBLY, TYPE T2 EACH$850$850$850
607E98000 FENCE, MISC.: DUMPSTER SCREEN WALL100 FT$192$192$192
623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R1 LS$3,300$4,000$5,000
623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND1 LS$3,300$4,000$5,000
690E50600 SPECIAL - BOLLARD Section 1 - ROADWAY - Totals Awd $1,058,585.67 2 $1,063,657.30 3 $1,309,557.209 EACH$720$720$500
601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT8 SY$120$180$200
601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER2 CY$515$450$800
659E00100 SOIL ANALYSIS TEST2 EACH$70.00$135$70.00
659E00500 SEEDING AND MULCHING, CLASS 119,299 SY$1.10$0.79$1.10
659E14000 REPAIR SEEDING AND MULCHING922 SY$1.10$0.80$1.10
659E15000 INTER-SEEDING922 SY$0.80$0.80$0.80
659E20000 COMMERCIAL FERTILIZER2.57 TON$850$939$850
659E31000 LIME3.81 ACRE$35.00$158$35.00
659E35000 WATER102 MGAL$1.00$1.00$1.00
670E00500 SLOPE EROSION PROTECTION7,595 SY$1.80$1.32$1.80
670E00720 DITCH EROSION PROTECTION MAT, TYPE B324 SY$1.80$1.49$1.80
832E15000 STORM WATER POLLUTION PREVENTION PLAN1 LS$3,400$3,200$5,000
832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS1 LS$8,000$6,420$15,000
832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA1 LS$10,000$500$15,000
836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING Section 2 - EROSION CONTROL - Totals Awd $319,807.75 2 $222,585.33 3 $221,692.7548 SY$5.00$5.49$5.00
602E20000 CONCRETE MASONRY0.6 CY$3,400$2,500$2,000
611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET306 FT$48.00$35.00$15.00
611E99710 PRECAST REINFORCED CONCRETE OUTLET Section 3 - DRAINAGE - Totals Awd $364,195.50 2 $342,410.00 3 $321,715.004 EACH$500$550$450
407E10000 TACK COAT4,030 GAL$2.50$1.50$2.40
452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P268 SY$75.00$60.00$75.00
452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P102 SY$135$110$100
609E98100 CURB, MISC.: CURB, TYPE 7 SNOW TURNOUT4 EACH$3,000$2,500$2,750
609E98100 CURB, MISC.: CURB, TYPE 7 TURNOUT Section 4 - PAVEMENT - Totals Awd $2,359,647.00 2 $2,767,904.00 3 $2,610,088.0028 EACH$1,350$850$400
202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT (8" DIA.)346 FT$30.00$8.50$30.00
611E99654 MANHOLE ADJUSTED TO GRADE Section 5 - SANITARY SEWER - Totals Awd $13,630.00 2 $7,191.00 3 $15,380.005 EACH$650$850$1,000
611E00400 4" CONDUIT, TYPE E240 FT$6.82$18.00$6.79
625E00450 CONNECTION, FUSED PULL APART32 EACH$149$220$149
625E00480 CONNECTION, UNFUSED PERMANENT36 EACH$84.61$175$84.29
625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN (CONVE7 EACH$837$1,920$834
625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN (LIGHT9 EACH$1,048$3,750$1,044
625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP7 EACH$2,036$2,650$2,029
625E15000 LIGHT TOWER FOUNDATION, 36" X 15' DEEP9 EACH$4,599$5,150$4,582
625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE9,585 FT$4.43$4.50$4.41
625E23400 NO. 10 AWG POLE AND BRACKET CABLE1,302 FT$1.22$2.20$1.22
625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C1,525 FT$17.30$25.00$17.24
625E25504 CONDUIT, 3", 725.0512,845 FT$11.60$10.00$11.56
625E26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), NVN-AF7 EACH$496$385$494
625E29002 TRENCH, 24" DEEP4,370 FT$9.32$9.00$9.29
625E30706 PULL BOX, 725.08, 24"12 EACH$1,433$2,015$1,427
625E32000 GROUND ROD25 EACH$169$390$168
625E34000 POWER SERVICE1 EACH$3,714$7,000$3,700
625E34450 CONTROL CENTER CABINET, COMPLETE1 EACH$8,522$6,000$8,490
625E36010 UNDERGROUND WARNING MARKING TAPE4,370 FT$0.79$0.35$0.79
625E39000 TEMPORARY LIGHTING1 LS$31,156$10,000$31,040
625E75351 LIGHT TOWER REMOVED, AS PER PLAN8 EACH$955$1,500$951
625E75400 LIGHT POLE REMOVED14 EACH$427$1,450$425
625E75507 LUMINAIRE REMOVED, AS PER PLAN25 EACH$93.71$130$93.36
625E75540 LIGHT TOWER FOUNDATION REMOVED8 EACH$524$2,100$522
625E76000 ARC FLASH CALCULATIONS AND LABEL (MED-122872)2 EACH$2,084$1,500$2,076
625E98000 LIGHTING, MISC.: TEST EXISTING CIRCUIT2 EACH$407$2,450$405
625E75500 LIGHT POLE FOUNDATION REMOVED Section 6 - LIGHTING - Totals Awd $375,933.86 2 $456,896.40 3 $398,414.4114 EACH$350$760$2,053
630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN246 FT$12.25$15.00$15.00
630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST73 FT$27.25$17.00$17.00
630E07000 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W8X1895 FT$46.00$70.00$70.00
630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X1298 FT$33.00$56.50$56.50
630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION8 EACH$765$725$725
630E80100 SIGN, FLAT SHEET114 SF$18.80$19.00$19.00
630E81200 SIGN ERECTED, EXTRUSHEET456 SF$25.10$26.00$26.00
630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION8 EACH$1,400$1,275$1,275
630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL10 EACH$29.20$10.00$10.00
630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL4 EACH$185$265$265
630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA12 EACH$26.00$20.00$20.00
630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT4 EACH$350$220$220
644E00100 EDGE LINE, 4"0.97 MILE$4,000$4,000$4,000
644E01360 WRONG WAY ARROW14 EACH$325$325$2,275
644E01200 PARKING LOT STALL MARKING Section 7 - TRAFFIC CONTROL - Totals Awd $65,561.65 2 $68,722.10 3 $96,022.109,454 FT$1.15$1.15$1.15
202E56000 BUILDING DEMOLISHED (NB 1 STORY BRICK)1 LS$24,125$30,624$50,000
202E56000 BUILDING DEMOLISHED (NB WOOD SHED)1 LS$3,000$5,000$7,500
202E56000 BUILDING DEMOLISHED (SB 1 STORY BRICK)1 LS$20,750$30,624$25,000
202E56000 BUILDING DEMOLISHED (SB WOOD SHED) Section 8 - BUILDING DEMOLITION - Totals Awd $50,875.00 2 $71,247.00 3 $87,500.001 LS$3,000$5,000$5,000
616E10000 WATER Section 9 - MAINTENANCE OF TRAFFIC - Totals Awd $2,340.00 2 $3,900.00 3 $39.0039 MGAL$60.00$100$1.00
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$40,000$20,000$25,000
619E16020 FIELD OFFICE, TYPE C6 MNTH$4,200$2,800$3,000
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$22,500$55,000$200,000

Project details

Description
MED-IR 71 Rest Areas TP
Type of work
Pavement

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →