WAS-SR 7-09.76
WAS County · est $1.2M
Bid dateThursday, January 25—
WAS County · est $1.2M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 20,349 SF | $8 | $163k | 15% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 19,009 SF |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 31 more items below.
| Item | Quantity | R1360 Construction Company INC | R2Kmx Painting INC | R3Panther Industrial Painting LLC | R4Apbn INC | R5Corrosion Resistance LTD | R6Elite Contractors INC | R7Ucl INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 20,349 SF | $8.00 | $8.00 | $12.00 | $10.00 | $10.85 | $9.00 | $12.00 | 17% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 19,009 SF | $8.00 | $8.00 | $12.00 | $10.00 | $10.85 | $9.00 | $12.00 | 16% |
| Item | Quantity | R1360 Construction Company INC | R2Kmx Painting INC | R3Panther Industrial Painting LLC | R4Apbn INC | R5Corrosion Resistance LTD | R6Elite Contractors INC | R7Ucl INC |
|---|---|---|---|---|---|---|---|---|
| 614E12336 WORK ZONE IMPACT ATTENUATOR (UNIDIRECTIONAL) | 2 EACH | $2,100 | $4,300 | $500 | $2,100 | $3,145 | $1,500 | $2,500 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $500 | $4,000 | $1,000 | $5,000 | $3,500 | $40,000 | $18,500 |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 10,110 SF |
| $10.00 |
| $7.00 |
| $12.00 |
| $10.00 |
| $15.25 |
| $10.00 |
| $12.50 |
| 11% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 9,469 SF | $8.00 | $8.00 | $12.00 | $9.00 | $8.50 | $11.00 | $12.00 | 8% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,083 SF | $8.00 | $8.00 | $12.00 | $9.00 | $8.60 | $11.00 | $12.00 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $60,000 | $50,000 | $70,500 | $20,000 | $100,000 | $180,000 | 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 20,349 SF | $2.00 | $2.00 | $1.00 | $2.00 | $1.75 | $2.00 | $2.50 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 20,349 SF | $2.00 | $2.00 | $1.00 | $1.00 | $1.75 | $2.00 | $2.00 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 19,009 SF | $2.00 | $2.00 | $1.00 | $2.00 | $1.75 | $2.00 | $2.50 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 19,009 SF | $2.00 | $2.00 | $1.00 | $1.00 | $1.75 | $2.00 | $2.00 | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 20,349 SF | $1.00 | $1.50 | $1.00 | $1.00 | $2.00 | $2.00 | $2.00 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 10,110 SF | $2.00 | $2.00 | $1.00 | $2.00 | $1.75 | $1.75 | $2.50 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 10,110 SF | $2.00 | $2.00 | $1.00 | $1.00 | $2.00 | $1.75 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 10,110 SF | $2.00 | $1.00 | $1.00 | $1.00 | $2.75 | $1.75 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 19,009 SF | $1.00 | $1.50 | $1.00 | $1.00 | $2.00 | $2.00 | $2.00 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 9,469 SF | $2.00 | $2.00 | $1.00 | $2.00 | $1.75 | $1.75 | $2.50 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 9,469 SF | $2.00 | $2.00 | $1.00 | $1.00 | $1.75 | $1.75 | $2.00 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 8,083 SF | $2.00 | $2.00 | $1.00 | $2.00 | $1.50 | $1.75 | $2.50 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 8,083 SF | $2.00 | $2.00 | $1.00 | $1.00 | $2.50 | $1.75 | $2.00 | 2% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $15,000 | $60,000 | $20,000 | $50,000 | $37,000 | $20,000 | $30,000 | 2% |
| 50 SY |
| $100 |
| $100 |
| $10.00 |
| $50.00 |
| $178 |
| $100 |
| $250 |
| 622E41000 PORTABLE BARRIER, 32" | 560 FT | $24.00 | $24.00 | $1.00 | $25.00 | $27.00 | $30.00 | $40.00 |
| 513E10200 STRUCTURAL STEEL MEMBERS, LEVEL UF | 25 LB | $40.00 | $40.00 | $35.00 | $37.75 | $37.75 | $40.00 | $32.00 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 8,083 SF | $1.00 | $2.00 | $1.00 | $1.00 | $2.50 | $1.75 | $2.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 13 MNHR | $100 | $100 | $200 | $100 | $55.00 | $100 | $85.00 |
| 514E10000 FINAL INSPECTION REPAIR | 7 EACH | $150 | $200 | $200 | $250 | $225 | $150 | $250 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 6 EACH | $500 | $1,000 | $900 | $955 | $965 | $500 | $865 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $5,000 | $3,000 | $3,000 | $3,000 | $7,500 | $3,000 |
| 513E10200 STRUCTURAL STEEL MEMBERS, LEVEL UF | 212 LB | $25.00 | $10.00 | $35.00 | $15.66 | $15.70 | $25.00 | $9.91 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 9,469 SF | $1.00 | $2.00 | $1.00 | $1.00 | $2.00 | $1.75 | $2.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 15 MNHR | $100 | $100 | $200 | $100 | $55.00 | $100 | $85.00 |
| 514E10000 FINAL INSPECTION REPAIR | 9 EACH | $150 | $200 | $200 | $250 | $225 | $150 | $250 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 3 EACH | $500 | $700 | $700 | $760 | $760 | $500 | $670 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $2,000 | $1,500 | $1,500 | $1,500 | $7,500 | $1,500 |
| 513E10200 STRUCTURAL STEEL MEMBERS, LEVEL UF | 225 LB | $25.00 | $15.00 | $15.00 | $17.35 | $17.50 | $25.00 | $11.60 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 32 MNHR | $100 | $100 | $200 | $100 | $55.00 | $100 | $85.00 |
| 514E10000 FINAL INSPECTION REPAIR | 19 EACH | $150 | $200 | $200 | $250 | $225 | $150 | $250 |
| 513E10200 STRUCTURAL STEEL MEMBERS, LEVEL UF | 233 LB | $25.00 | $17.00 | $18.00 | $20.67 | $20.75 | $25.00 | $14.92 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 30 MNHR | $100 | $100 | $200 | $100 | $55.00 | $100 | $85.00 |
| 514E10000 FINAL INSPECTION REPAIR | 18 EACH | $150 | $200 | $200 | $250 | $225 | $150 | $250 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 20 EACH | $500 | $700 | $600 | $690 | $690 | $500 | $600 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $12,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 17 MNHR | $100 | $100 | $200 | $100 | $55.00 | $100 | $85.00 |
| 514E10000 FINAL INSPECTION REPAIR | 11 EACH | $150 | $200 | $100 | $250 | $225 | $150 | $250 |
| 516E31000 JOINT SEALER | 72 FT | $100 | $280 | $10.00 | $100 | $32.00 | $50.00 | $250 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 8 EACH | $500 | $700 | $700 | $740 | $740 | $650 | $650 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $6,000 | $4,000 | $4,000 | $4,000 | $7,500 | $40,000 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $5,000 | $10,000 | $5,000 | $15,000 | $11,400 | $20,000 | $45,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $12,000 | $10,000 | $13,000 | $13,500 | $20,000 | $17,500 |
| $8 |
| $152k |
| 14% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 10,110 SF | $10 | $101k | 9% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 9,469 SF | $8 | $76k | 7% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,083 SF | $8 | $65k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $50k | 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 20,349 SF | $2 | $41k | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 20,349 SF | $2 | $41k | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 19,009 SF | $2 | $38k | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 19,009 SF | $2 | $38k | 3% |