BUT-PM/RPM FY2018
BUT County · est $2.8M
Bid dateThursday, April 5—
BUT County · est $2.8M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 642E00094 EDGE LINE, 6" | 1,969.72 MILE | $525 | $1.03M | 35% |
| 642E00290 CENTER LINE | 707.72 MILE | $500 | $354k | 12% |
| 621E00300 |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 10 more items below.
| Item | Quantity | R1A & A Safety INC | R2Dura Mark INC | R3Aero-mark INC | R4Oglesby Construction INC | % of bid |
|---|---|---|---|---|---|---|
| 642E00094 EDGE LINE, 6" | 1,969.72 MILE | $525 | $519 | $585 | $563 | 35% |
| 642E00290 CENTER LINE | 707.72 MILE | $500 | $585 | $675 | $586 | 12% |
| 621E00300 RPM REFLECTOR | 68,317 EACH | $4.46 | $4.00 | $4.00 | $4.20 | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $203,513 | $172,275 | $62,000 | $155,724 | 7% |
| 642E00090 EDGE LINE, 4" | 465.88 MILE | $375 | $385 | $465 | $400 | 6% |
| 642E00690 TRANSVERSE/DIAGONAL LINE | 106,821 FT | $1.30 | $1.35 | $1.29 | $1.55 | 5% |
| Item | Quantity | R1A & A Safety INC | R2Dura Mark INC | R3Aero-mark INC | R4Oglesby Construction INC |
|---|---|---|---|---|---|
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2,000 EACH | $5.00 | $12.00 | $12.00 | $12.60 |
| 642E00910 ISLAND MARKING | 5,513 SF | $1.05 | $2.00 | $1.00 | $1.35 |
| 642E00990 RAILROAD SYMBOL MARKING | 24 EACH | $200 | $185 | $185 | $195 |
| 642E01108 SCHOOL SYMBOL MARKING, 96" | 41 EACH | $200 | $185 | $185 | $195 |
| 642E20800 YIELD LINE | 80 FT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 343,393 FT |
| $0.40 |
| $0.35 |
| $0.50 |
| $0.43 |
| 5% |
| 642E00194 LANE LINE, 6" | 536.53 MILE | $225 | $240 | $335 | $260 | 4% |
| 642E01290 LANE ARROW | 2,386 EACH | $45.00 | $50.00 | $40.00 | $61.00 | 4% |
| 642E00490 STOP LINE | 31,435 FT | $2.25 | $2.25 | $2.25 | $3.10 | 2% |
| 642E00390 CHANNELIZING LINE, 8" | 139,887 FT | $0.35 | $0.35 | $0.35 | $0.39 | 2% |
| 642E00190 LANE LINE, 4" | 247.38 MILE | $165 | $180 | $275 | $225 | 1% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $140,000 | $40,000 | $68,000 | 1% |
| 642E00590 CROSSWALK LINE | 24,396 FT | $1.50 | $1.50 | $1.40 | $1.75 | 1% |
| 621E00100 RPM | 2,000 EACH | $17.00 | $29.00 | $29.00 | $30.00 | 1% |
| 644E01500 DOTTED LINE, 4" | 20,489 FT | $1.00 | $1.50 | $0.96 | $1.50 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $19,101 | $19,500 | $16,502 | $21,000 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 300 HOUR | $60.00 | $60.00 | $65.00 | $60.00 | 1% |
| 642E01408 WORD ON PAVEMENT, 96" | 226 EACH | $55.00 | $60.00 | $50.00 | $80.00 | 0% |
| 642E00720 CHEVRON MARKING, TYPE 1 | 8,594 FT | $1.30 | $1.35 | $1.29 | $2.20 | 0% |
| $4.25 |
| $4.00 |
| $5.78 |
| $11.00 |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 1,000 FT | $1.00 | $2.00 | $2.50 | $2.20 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 10 EACH | $50.00 | $75.00 | $100 | $65.00 |
| 642E50010 PAVEMENT MARKING, MISC.:SUPPLEMENTAL WORK REQUESTS | 50 EACH | $100 | $100 | $100 | $100 |
| 644E01350 LANE REDUCTION ARROW | 6 EACH | $965 | $500 | $703 | $600 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 1 SNMT | $100 | $1,000 | $3,000 | $1,000 |
| 68,317 EACH |
| $4.46 |
| $305k |
| 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $203,513 | $204k | 7% |
| 642E00090 EDGE LINE, 4" | 465.88 MILE | $375 | $175k | 6% |
| 642E00690 TRANSVERSE/DIAGONAL LINE | 106,821 FT | $1.3 | $139k | 5% |
| 642E00394 CHANNELIZING LINE, 12" | 343,393 FT | $0.4 | $137k | 5% |
| 642E00194 LANE LINE, 6" | 536.53 MILE | $225 | $121k | 4% |
| 642E01290 LANE ARROW | 2,386 EACH | $45 | $107k | 4% |
| 642E00490 STOP LINE | 31,435 FT | $2.25 | $71k | 2% |