LAW-SR 522-1.38
LAW County · est $0.3M
Bid dateThursday, April 19—
LAW County · est $0.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 40 more items below.
| Item | Quantity | R1Axis Civil Construction LLC | R2Allard Excavation LLC | R3Shelly & Sands INC | R4Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|
| 611E94920 8' X 7' CONDUIT, TYPE A, 706.05 | 72 FT | $1,175 | $1,080 | $1,150 | $1,059 | 29% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 110 CY | $225 | $200 | $200 | $231 | 8% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 19 CY | $1,200 | $605 | $1,260 | $1,364 | 8% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 84 CY | $250 | $182 | $182 | $280 |
| Item | Quantity | R1Axis Civil Construction LLC | R2Allard Excavation LLC | R3Shelly & Sands INC | R4Eclipse CO LLC |
|---|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 313 FT | $3.50 | $2.70 | $1.60 | $6.00 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 2 EACH | $200 | $109 | $225 | $452 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 4 EACH | $200 | $109 | $85.00 | $452 |
| 202E53100 MAILBOX REMOVED | 1 EACH | $50.00 | $50.00 | $85.00 | $91.50 |
| 203E10000 EXCAVATION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 624E10000 MOBILIZATION | 1 LS | $16,000 | $49,600 | $10,000 | $16,000 | 5% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 37 CY | $425 | $461 | $725 | $540 | 5% |
| 203E20000 EMBANKMENT | 788 CY | $18.00 | $7.44 | $9.50 | $13.50 | 5% |
| 304E20000 AGGREGATE BASE | 134 CY | $100 | $55.98 | $65.00 | $68.00 | 5% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $10,500 | $3,200 | $12,211 | $4,268 | 4% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $10,000 | $6,914 | $13,264 | $4,313 | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 4,612 LB | $2.00 | $1.58 | $1.60 | $1.50 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,500 | $4,100 | $3,500 | $13,084 | 3% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $8,500 | $1,955 | $14,790 | $3,678 | 3% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 77 CY | $90.00 | $59.57 | $95.00 | $96.00 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $6,650 | $6,650 | $7,100 | $9,660 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $6,210 | $7,150 | $7,500 | 2% |
| 202E23000 PAVEMENT REMOVED | 377 SY | $12.00 | $6.21 | $12.00 | $10.50 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 50 CY | $90.00 | $230 | $230 | $231 | 2% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $90.00 | $230 | $275 | $187 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,500 | $11,386 | $3,150 | $17,200 | 2% |
| 225 CY |
| $18.00 |
| $14.46 |
| $15.00 |
| $13.50 |
| 204E10000 SUBGRADE COMPACTION | 1,017 SY | $2.00 | $2.18 | $3.50 | $2.50 |
| 606E15050 GUARDRAIL, TYPE MGS | 138 FT | $22.30 | $32.22 | $29.40 | $23.50 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 1 EACH | $2,935 | $1,990 | $2,235 | $3,084 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,000 | $850 | $875 | $1,051 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $180 | $150 | $150 | $142 |
| 659E10000 SEEDING AND MULCHING | 3,164 SY | $1.07 | $2.44 | $1.10 | $2.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 158 SY | $1.00 | $0.05 | $1.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.43 TON | $1,500 | $450 | $1,500 | $788 |
| 659E31000 LIME | 0.65 ACRE | $120 | $30.00 | $120 | $210 |
| 659E35000 WATER | 17.1 MGAL | $1.00 | $2.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 81 FT | $12.00 | $19.16 | $15.00 | $14.50 |
| 611E06400 15" CONDUIT, TYPE D | 30 FT | $50.00 | $48.82 | $55.00 | $69.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 56 FT | $5.00 | $7.19 | $12.00 | $9.50 |
| 407E10000 TACK COAT | 225 GAL | $5.00 | $2.00 | $2.00 | $7.00 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 41 CY | $80.00 | $63.12 | $85.00 | $77.50 |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (18 CY | $225 | $200 | $200 | $414 |
| 621E00100 RPM | 12 EACH | $80.00 | $300 | $300 | $526 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 6 EACH | $33.70 | $10.15 | $20.00 | $45.50 |
| 626E00112 BARRIER REFLECTOR, TYPE 3, (BIDIRECTIONAL) | 3 EACH | $19.00 | $7.00 | $7.00 | $20.00 |
| 642E00094 EDGE LINE, 6" | 0.19 MILE | $5,050 | $5,050 | $5,050 | $5,306 |
| 642E00290 CENTER LINE | 0.1 MILE | $9,250 | $9,250 | $9,250 | $9,719 |
| 253E01000 PAVEMENT REPAIR | 150 SY | $25.00 | $96.00 | $96.00 | $83.00 |
| 407E10000 TACK COAT | 50 GAL | $3.49 | $2.00 | $2.00 | $7.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 32 HOUR | $60.00 | $80.00 | $67.00 | $68.50 |
| 616E10000 WATER | 1 MGAL | $1.00 | $1.00 | $35.00 | $34.00 |
| 617E10100 COMPACTED AGGREGATE | 25 CY | $45.00 | $42.43 | $50.00 | $77.50 |
| 617E25000 WATER | 2 MGAL | $1.00 | $1.00 | $35.00 | $68.50 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 2 CY | $1,000 | $3,153 | $900 | $1,453 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 60 SY | $36.00 | $27.79 | $35.00 | $42.50 |
| 512E33000 TYPE 2 WATERPROOFING | 228 SY | $16.00 | $13.36 | $22.50 | $21.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 50 SF | $3.00 | $2.93 | $2.50 | $11.50 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 27 CY | $120 | $58.54 | $120 | $116 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,000 | $5,808 | $6,000 | $8,500 |
| 619E16000 FIELD OFFICE, TYPE A | 2 MNTH | $750 | $1,380 | $2,900 | $700 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E94920 8' X 7' CONDUIT, TYPE A, 706.05 | 72 FT | $1,175 | $85k | 24% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 110 CY | $225 | $25k | 7% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 19 CY | $1,200 | $23k | 6% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 84 CY | $250 | $21k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $16,000 | $16k | 4% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 37 CY | $425 | $16k | 4% |
| 203E20000 EMBANKMENT | 788 CY | $18 | $14k | 4% |
| 304E20000 AGGREGATE BASE | 134 CY | $100 | $13k | 4% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $10,500 | $11k | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $10,000 | $10k | 3% |