MEG-SR 124-55.890
MEG County · est $2.3M
Bid dateThursday, April 19—
MEG County · est $2.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 64 more items below.
| Item | Quantity | R1Elite Contractors INC | R2Panther Industrial Painting LLC | R3Eagle Industrial Painting LLC | R4Euro Paint LLC | R5Apbn INC | R6360 Construction Company INC | R7Kmx Painting INC | R8Corrosion Resistance LTD | R9M & J Construction CO Of Pinellas County | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 25,739 SF | $6.20 | $8.00 | $6.11 | $6.00 | $6.00 | $7.00 | $8.00 | $8.25 | $8.00 | 15% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 17,416 SF |
| Item | Quantity | R1Elite Contractors INC | R2Panther Industrial Painting LLC | R3Eagle Industrial Painting LLC | R4Euro Paint LLC | R5Apbn INC | R6360 Construction Company INC | R7Kmx Painting INC | R8Corrosion Resistance LTD | R9M & J Construction CO Of Pinellas County |
|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $1,000 | $3,000 | $7,000 | $2,150 | $1,000 | $5,000 | $1,500 | $10,000 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 3,500 SY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $6.20 |
| $8.00 |
| $5.11 |
| $6.50 |
| $8.00 |
| $7.00 |
| $8.00 |
| $10.50 |
| $8.00 |
| 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 17,178 SF | $6.20 | $8.00 | $5.11 | $6.00 | $8.00 | $7.00 | $8.00 | $10.25 | $8.00 | 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 16,641 SF | $6.20 | $8.00 | $6.10 | $6.50 | $8.50 | $7.00 | $8.00 | $10.50 | $8.00 | 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 16,641 SF | $6.20 | $8.00 | $5.10 | $6.00 | $8.50 | $7.00 | $8.00 | $12.50 | $8.00 | 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,546 SF | $7.40 | $8.00 | $6.25 | $6.00 | $9.50 | $7.00 | $9.00 | $15.50 | $8.00 | 6% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,546 SF | $7.40 | $8.00 | $6.25 | $6.00 | $9.50 | $7.00 | $9.00 | $15.00 | $8.00 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $75,000 | $90,000 | $50,000 | $50,000 | $20,000 | $120,000 | $30,000 | $160,880 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 25,739 SF | $1.50 | $1.00 | $1.17 | $1.80 | $1.00 | $2.00 | $2.00 | $1.00 | $1.00 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 25,739 SF | $1.50 | $1.00 | $1.32 | $1.80 | $1.00 | $2.00 | $1.00 | $1.00 | $1.50 | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 25,739 SF | $1.25 | $1.00 | $1.35 | $1.80 | $1.00 | $1.00 | $1.00 | $1.00 | $1.50 | 3% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 17,416 SF | $1.50 | $1.00 | $1.17 | $1.80 | $2.00 | $2.00 | $2.00 | $1.00 | $1.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 17,416 SF | $1.50 | $1.00 | $1.32 | $1.80 | $2.00 | $2.00 | $1.00 | $1.25 | $1.50 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 17,178 SF | $1.50 | $1.00 | $1.17 | $1.80 | $2.00 | $2.00 | $2.00 | $1.00 | $1.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 17,178 SF | $1.50 | $1.00 | $1.32 | $1.80 | $2.00 | $2.00 | $1.00 | $1.25 | $1.50 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $25,000 | $20,000 | $23,000 | $20,000 | $18,500 | $20,000 | $20,000 | $20,000 | $20,000 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 16,641 SF | $1.50 | $1.00 | $1.25 | $1.80 | $2.00 | $2.00 | $2.00 | $1.00 | $1.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 16,641 SF | $1.50 | $1.00 | $1.35 | $1.80 | $2.00 | $2.00 | $1.00 | $1.25 | $1.50 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 16,641 SF | $1.50 | $1.00 | $1.25 | $1.80 | $2.00 | $2.00 | $2.00 | $1.00 | $1.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 16,641 SF | $1.50 | $1.00 | $1.35 | $1.80 | $2.00 | $2.00 | $1.00 | $1.00 | $1.50 | 2% |
| $1.00 |
| $1.00 |
| $2.00 |
| $2.75 |
| $1.00 |
| $2.75 |
| $0.50 |
| $2.81 |
| $3.12 |
| 642E00094 EDGE LINE, 6" | 0.29 MILE | $1.00 | $100 | $2,600 | $4,910 | $1.00 | $4,910 | $500 | $4,910 | $3,042 |
| 642E00194 LANE LINE, 6" | 2.56 MILE | $1.00 | $100 | $1,000 | $4,795 | $1.00 | $4,795 | $100 | $4,795 | $1,170 |
| 642E00290 CENTER LINE | 0.15 MILE | $1.00 | $100 | $4,600 | $5,010 | $1.00 | $5,010 | $500 | $5,010 | $5,382 |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 2 EACH | $1.00 | $100 | $6,000 | $2,100 | $1,000 | $2,100 | $100 | $2,100 | $2,691 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $1.00 | $100 | $5,000 | $10,000 | $20,000 | $5,000 | $100 | $5,000 | $5,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, 1 WAY | 21 EACH | $1.00 | $1.00 | $45.00 | $7.00 | $7.00 | $7.00 | $1.00 | $7.00 | $14.04 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 13 EACH | $1.00 | $1.00 | $45.00 | $8.00 | $7.00 | $8.00 | $1.00 | $8.00 | $14.04 |
| 614E13350 OBJECT MARKER, ONE WAY | 21 EACH | $1.00 | $1.00 | $45.00 | $11.00 | $7.00 | $11.00 | $1.00 | $11.00 | $19.89 |
| 614E13360 OBJECT MARKER, TWO WAY | 13 EACH | $1.00 | $1.00 | $45.00 | $13.00 | $7.00 | $13.00 | $1.00 | $13.00 | $19.89 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.06 MILE | $1.00 | $1.00 | $10,250 | $2,940 | $2,000 | $2,940 | $100 | $2,940 | $11,993 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 2.75 MILE | $1.00 | $1.00 | $1,300 | $2,795 | $1.00 | $2,795 | $100 | $2,795 | $1,521 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 4,320 FT | $1.00 | $0.10 | $0.60 | $0.50 | $0.10 | $0.50 | $0.10 | $0.50 | $0.71 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 30 FT | $1.00 | $1.00 | $13.00 | $2.50 | $15.00 | $2.50 | $1.00 | $2.50 | $15.21 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $1.00 | $500 | $15,000 | $10,000 | $4,000 | $100 | $100 | $3,500 | $1,000 |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 68 SY | $1.00 | $10.00 | $750 | $366 | $250 | $20.00 | $1.00 | $135 | $282 |
| 622E41000 PORTABLE BARRIER, 32" | 480 FT | $1.00 | $1.00 | $37.41 | $24.00 | $20.00 | $24.00 | $1.00 | $24.00 | $39.78 |
| 622E41020 PORTABLE BARRIER, 32", BRIDGE MOUNTED | 280 FT | $1.00 | $1.00 | $30.89 | $25.00 | $20.00 | $25.00 | $1.00 | $25.00 | $42.12 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 19 MNHR | $150 | $200 | $180 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 11 EACH | $150 | $100 | $180 | $300 | $100 | $100 | $200 | $225 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 16 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $300 | $484 | $970 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $5,000 | $5,000 | $12,000 | $5,000 | $5,000 | $5,000 | $6,000 | $12,000 | $14,040 |
| 518E12700 SCUPPER, VERTICAL EXTENSION | 16 EACH | $300 | $300 | $300 | $300 | $300 | $300 | $350 | $350 | $544 |
| 513E10200 STRUCTURAL STEEL MEMBERS, LEVEL UF | 41 LB | $36.50 | $36.50 | $25.00 | $36.50 | $36.50 | $36.50 | $40.00 | $40.00 | $46.80 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 17,416 SF | $1.25 | $1.00 | $1.35 | $1.80 | $1.00 | $2.00 | $1.00 | $1.25 | $1.50 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 26 MNHR | $150 | $200 | $180 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 17 EACH | $150 | $100 | $180 | $300 | $100 | $100 | $200 | $200 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 30 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $270 | $450 | $941 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $7,500 | $18,000 | $7,500 | $7,500 | $7,500 | $8,000 | $18,000 | $21,060 |
| 518E12700 SCUPPER, VERTICAL EXTENSION | 6 EACH | $300 | $300 | $300 | $300 | $300 | $300 | $320 | $385 | $544 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 17,178 SF | $1.25 | $1.00 | $1.35 | $1.80 | $1.00 | $2.00 | $1.00 | $1.25 | $1.50 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 26 MNHR | $150 | $200 | $180 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 17 EACH | $150 | $100 | $180 | $300 | $100 | $100 | $200 | $200 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 30 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $300 | $450 | $707 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $7,500 | $12,000 | $7,500 | $7,500 | $7,500 | $7,700 | $12,000 | $14,040 |
| 518E12700 SCUPPER, VERTICAL EXTENSION | 7 EACH | $300 | $300 | $300 | $300 | $300 | $300 | $400 | $385 | $544 |
| 513E21000 TRIMMING OF BEAM END | 5 EACH | $400 | $400 | $150 | $400 | $400 | $400 | $500 | $150 | $176 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 16,641 SF | $1.25 | $1.00 | $1.40 | $1.80 | $2.00 | $2.00 | $1.00 | $1.25 | $1.50 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 25 MNHR | $150 | $200 | $180 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 15 EACH | $150 | $100 | $180 | $300 | $100 | $100 | $200 | $200 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 30 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $270 | $450 | $765 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $7,500 | $15,000 | $7,500 | $7,500 | $7,500 | $7,500 | $15,000 | $17,550 |
| 513E21000 TRIMMING OF BEAM END | 5 EACH | $400 | $400 | $150 | $400 | $400 | $400 | $500 | $150 | $176 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 16,641 SF | $1.25 | $1.00 | $1.40 | $1.80 | $2.00 | $2.00 | $1.00 | $1.00 | $1.50 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 25 MNHR | $150 | $200 | $150 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 15 EACH | $150 | $100 | $150 | $300 | $100 | $100 | $200 | $200 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 30 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $270 | $450 | $765 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $7,500 | $7,500 | $15,000 | $7,500 | $7,500 | $7,500 | $7,500 | $15,000 | $17,550 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 8,546 SF | $1.75 | $1.00 | $1.80 | $1.80 | $2.00 | $2.00 | $2.00 | $1.50 | $1.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 8,546 SF | $1.75 | $1.00 | $1.60 | $1.80 | $2.00 | $2.00 | $2.00 | $1.50 | $1.50 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 8,546 SF | $1.45 | $1.00 | $1.80 | $1.80 | $1.00 | $2.00 | $2.00 | $1.50 | $1.50 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 14 MNHR | $150 | $200 | $180 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 8 EACH | $150 | $100 | $180 | $300 | $100 | $100 | $200 | $250 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 20 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $270 | $450 | $707 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $5,000 | $5,000 | $9,000 | $5,000 | $5,000 | $5,000 | $6,000 | $9,000 | $10,530 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 8,546 SF | $1.75 | $1.00 | $1.80 | $1.80 | $2.00 | $2.00 | $2.00 | $1.25 | $1.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 8,546 SF | $1.75 | $1.00 | $1.60 | $1.80 | $2.00 | $2.00 | $2.00 | $1.25 | $1.50 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 8,546 SF | $1.45 | $1.00 | $1.80 | $1.80 | $1.00 | $2.00 | $2.00 | $1.25 | $1.50 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 14 MNHR | $150 | $200 | $180 | $45.00 | $100 | $120 | $100 | $35.00 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 8 EACH | $150 | $100 | $180 | $300 | $100 | $100 | $200 | $250 | $350 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 20 EACH | $250 | $250 | $400 | $250 | $250 | $250 | $300 | $450 | $707 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $5,000 | $5,000 | $9,000 | $5,000 | $5,000 | $3,000 | $6,000 | $9,000 | $10,530 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $75,000 | $30,000 | $42,340 | $58,185 | $90,000 | $110,000 | $66,000 | $146,397 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 25,739 SF | $6.2 | $160k | 11% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 17,416 SF | $6.2 | $108k | 8% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 17,178 SF | $6.2 | $107k | 7% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 16,641 SF | $6.2 | $103k | 7% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 16,641 SF | $6.2 | $103k | 7% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,546 SF | $7.4 | $63k | 4% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,546 SF | $7.4 | $63k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 25,739 SF | $1.5 | $39k | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 25,739 SF | $1.5 | $39k | 3% |