LOG-SR 235-22.00
LOG County · est $0.7M
Bid dateThursday, October 11—
LOG County · est $0.7M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 48 more items below.
| Item | Quantity | R1Eagle Bridge CO | R2Complete General Construction Company | R3Armstrong Steel Erectors INC | R4R & I Construction INC | % of bid |
|---|---|---|---|---|---|---|
| 511E32212 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 175 CY | $1,000 | $800 | $760 | $1,000 | 28% |
| 507E00751 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 575 FT | $88.00 | $78.00 | $77.50 | $75.00 | 8% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 49,486 LB | $0.90 | $1.00 | $0.93 | $1.50 | 7% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 61 CY | $725 | $700 | $700 | $600 |
| Item | Quantity | R1Eagle Bridge CO | R2Complete General Construction Company | R3Armstrong Steel Erectors INC | R4R & I Construction INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $4,500 | $18,000 | $7,500 | $5,000 |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 373 SY | $12.00 | $12.00 | $5.00 | $7.15 |
| 202E23500 WEARING COURSE REMOVED | 125 SY | $7.00 | $12.00 | $15.00 | $13.75 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 48 FT | $7.00 | $40.00 | $20.00 | $1.00 |
| 202E38001 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $40,000 | $18,000 | $50,000 | $15,000 | 6% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 720 FT | $45.00 | $35.00 | $28.00 | $40.00 | 5% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $32,000 | $28,000 | $70,000 | $75,000 | 5% |
| 526E15011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 152 SY | $210 | $240 | $275 | $225 | 5% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 180 FT | $143 | $155 | $148 | $168 | 4% |
| 511E42510 CLASS QC1 CONCRETE, PIER CAP | 14 CY | $1,750 | $1,450 | $1,750 | $1,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $20,000 | $35,000 | 3% |
| 203E10000 EXCAVATION | 904 CY | $20.00 | $25.00 | $10.00 | $7.00 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $17,500 | $20,000 | $7,500 | $20,000 | 3% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $17,500 | $10,000 | $21,000 | $20,000 | 3% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 191 CY | $60.00 | $90.00 | $87.50 | $75.00 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $10,000 | $10,000 | $12,500 | $6,400 | 2% |
| 523E20000 DYNAMIC LOAD TESTING | 2 EACH | $5,000 | $4,500 | $4,000 | $2,915 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,000 | $7,000 | $9,500 | $9,000 | 1% |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $1,929 | $1,985 | $1,985 | $2,000 | 1% |
| 832E30000 EROSION CONTROL | 7,600 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 394 FT |
| $2.00 |
| $2.00 |
| $2.00 |
| $1.00 |
| 202E38500 BRIDGE RAILING REMOVED | 88 FT | $9.00 | $3.50 | $3.50 | $2.00 |
| 202E98100 REMOVAL MISC.: SHEET PILE WALL | 1 EACH | $500 | $7,500 | $760 | $1,500 |
| 203E20000 EMBANKMENT | 86 CY | $32.00 | $20.00 | $32.50 | $10.00 |
| 204E10000 SUBGRADE COMPACTION | 204 SY | $8.00 | $3.00 | $5.50 | $1.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 225 FT | $17.44 | $19.20 | $19.20 | $19.50 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE EROADWAY | 3 EACH | $2,085 | $2,195 | $2,195 | $2,000 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $712 | $865 | $865 | $1,000 |
| 601E20010 CRUSHED AGGREGATE SLOPE PROTECTION | 2 CY | $165 | $250 | $100 | $50.00 |
| 659E10000 SEEDING AND MULCHING | 651 SY | $5.00 | $2.30 | $2.30 | $2.00 |
| 659E10100 SEEDING AND MULCHING FOR WILDLIFE | 804 SY | $5.00 | $2.80 | $2.80 | $2.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 73 SY | $3.00 | $0.50 | $0.50 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.2 TON | $1,250 | $610 | $610 | $500 |
| 659E35000 WATER | 8 MGAL | $10.00 | $1.00 | $350 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 23 FT | $22.00 | $18.00 | $35.00 | $10.00 |
| 611E06100 15" CONDUIT, TYPE C | 60 FT | $45.00 | $80.00 | $60.00 | $27.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 1 1/2" DEPTH | 312 SY | $20.05 | $20.00 | $15.00 | $13.75 |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 12 CY | $351 | $350 | $500 | $425 |
| 304E20000 AGGREGATE BASE | 32 CY | $100 | $85.00 | $70.00 | $50.00 |
| 407E10000 TACK COAT | 31 GAL | $6.01 | $6.00 | $1.00 | $4.50 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 15 CY | $411 | $410 | $500 | $450 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 4 EACH | $10.00 | $40.00 | $30.00 | $10.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 11 EACH | $10.02 | $7.00 | $7.00 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 22 FT | $11.03 | $17.50 | $17.50 | $8.00 |
| 630E80101 SIGN, FLAT SHEET, AS PER PLAN | 2 SF | $140 | $185 | $185 | $25.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $85.20 | $65.00 | $65.00 | $16.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $20.05 | $10.00 | $10.00 | $16.00 |
| 646E10010 EDGE LINE, 6" | 0.11 MILE | $15,033 | $22,380 | $15,000 | $14,999 |
| 646E10200 CENTER LINE | 0.06 MILE | $25,057 | $37,301 | $25,000 | $24,999 |
| 616E10000 WATER | 2 MGAL | $10.00 | $65.00 | $300 | $1.00 |
| 507E00500 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 640 FT | $5.00 | $30.00 | $15.25 | $5.00 |
| 507E00700 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 525 FT | $7.00 | $45.00 | $15.25 | $5.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 124 SY | $25.00 | $25.00 | $25.00 | $30.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 56 SF | $5.00 | $9.00 | $4.00 | $4.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 77 SF | $6.00 | $9.00 | $5.00 | $4.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 97 FT | $28.00 | $40.00 | $28.00 | $20.00 |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 68 FT | $12.00 | $28.00 | $27.50 | $10.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 46 CY | $85.00 | $110 | $85.00 | $70.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 204 FT | $12.00 | $14.50 | $15.00 | $10.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 109 FT | $8.00 | $9.00 | $8.50 | $8.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 54 FT | $10.00 | $14.00 | $12.50 | $8.00 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $2,500 | $5,000 | $2,500 | $4,000 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $1,750 | $2,000 | $2,500 | $500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $5,000 | $5,000 | $2,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E32212 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 175 CY | $1,000 | $175k | 24% |
| 507E00751 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 575 FT | $88 | $51k | 7% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 49,486 LB | $0.9 | $45k | 6% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 61 CY | $725 | $44k | 6% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $40,000 | $40k | 6% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 720 FT | $45 | $32k | 4% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $32,000 | $32k | 4% |
| 526E15011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 152 SY | $210 | $32k | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 180 FT | $142.83 | $26k | 4% |
| 511E42510 CLASS QC1 CONCRETE, PIER CAP | 14 CY | $1,750 | $25k | 3% |