WOO-IR 280-Bridge Painting
WOO County · est $2.0M
Bid dateThursday, December 13—
WOO County · est $2.0M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 29,089 SF | $6 | $175k | 14% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 25,524 SF | $6 | $153k |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 16 more items below.
| Item | Quantity | R1Industrial Painting & Rigging INC | R2Apbn INC | R3Corrosion Resistance LTD | R4Elite Contractors INC | R5Panther Industrial Painting LLC | R6Saffo Contractors INC | R7Kmx Painting INC | R8360 Construction Company INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 29,089 SF | $6.00 | $8.75 | $7.00 | $6.80 | $10.00 | $6.00 | $9.00 | $10.00 | 16% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 25,524 SF | $6.00 | $8.75 | $6.75 | $6.80 |
| Item | Quantity | R1Industrial Painting & Rigging INC | R2Apbn INC | R3Corrosion Resistance LTD | R4Elite Contractors INC | R5Panther Industrial Painting LLC | R6Saffo Contractors INC | R7Kmx Painting INC | R8360 Construction Company INC |
|---|---|---|---|---|---|---|---|---|---|
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 150 HOUR | $90.00 | $20.00 | $85.00 | $100 | $30.00 | $75.00 | $50.00 | $65.00 |
| 614E12500 REPLACEMENT SIGN | 5 EACH | $240 | $50.00 | $150 | $200 | $200 | $50.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $10.00 |
| $6.00 |
| $9.00 |
| $10.00 |
| 14% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 25,128 SF | $6.00 | $8.75 | $6.00 | $6.80 | $10.00 | $6.00 | $10.00 | $10.00 | 14% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 20,328 SF | $6.00 | $8.75 | $6.00 | $6.80 | $10.00 | $6.00 | $9.00 | $10.00 | 11% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 18,560 SF | $6.00 | $8.75 | $8.00 | $6.80 | $10.00 | $6.00 | $10.00 | $10.00 | 10% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $25,000 | $25,000 | $100,000 | $150,000 | $200,000 | $180,000 | $100,000 | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $29,591 | $16,000 | $25,000 | $20,000 | $30,000 | $21,000 | $26,000 | $30,000 | 3% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 29,089 SF | $1.00 | $1.00 | $1.40 | $2.00 | $1.00 | $5.00 | $2.00 | $4.00 | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 29,089 SF | $1.00 | $1.00 | $2.00 | $2.00 | $1.00 | $1.50 | $2.00 | $2.00 | 3% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 29,089 SF | $1.00 | $1.00 | $2.00 | $2.00 | $1.00 | $1.50 | $1.00 | $1.00 | 3% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 25,524 SF | $1.00 | $1.00 | $1.55 | $2.00 | $1.00 | $5.00 | $2.00 | $4.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 25,524 SF | $1.00 | $1.00 | $2.50 | $2.00 | $1.00 | $1.50 | $2.00 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 25,524 SF | $1.00 | $1.00 | $2.30 | $2.00 | $1.00 | $1.50 | $2.00 | $1.00 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 25,128 SF | $1.00 | $1.00 | $1.55 | $2.00 | $1.00 | $5.00 | $2.00 | $4.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 25,128 SF | $1.00 | $1.00 | $2.50 | $2.00 | $1.00 | $1.50 | $2.00 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 25,128 SF | $1.00 | $1.00 | $2.30 | $2.00 | $1.00 | $1.50 | $2.00 | $1.00 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $25,000 | $25,000 | $85,000 | $90,000 | $120,000 | $168,000 | $100,000 | $225,000 | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 20,328 SF | $1.00 | $1.00 | $1.85 | $2.00 | $1.00 | $5.00 | $2.00 | $4.00 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 20,328 SF | $1.00 | $1.00 | $2.75 | $2.00 | $1.00 | $1.50 | $2.00 | $2.00 | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 20,328 SF | $1.00 | $1.00 | $2.75 | $2.00 | $1.00 | $1.50 | $1.50 | $1.00 | 2% |
| $100 |
| $150 |
| 614E12600 REPLACEMENT DRUM | 20 EACH | $60.00 | $50.00 | $60.00 | $50.00 | $10.00 | $25.00 | $20.00 | $60.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 30 MNHR | $80.00 | $100 | $40.00 | $100 | $200 | $75.00 | $100 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 17 EACH | $200 | $200 | $320 | $200 | $200 | $100 | $200 | $200 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 28 MNHR | $80.00 | $100 | $40.00 | $100 | $200 | $75.00 | $100 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 16 EACH | $200 | $200 | $320 | $200 | $200 | $100 | $200 | $200 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 18,560 SF | $1.00 | $1.00 | $2.00 | $2.00 | $1.00 | $5.00 | $2.00 | $4.00 |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 18,560 SF | $1.00 | $1.00 | $3.40 | $2.00 | $1.00 | $1.50 | $2.00 | $2.00 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 18,560 SF | $1.00 | $1.00 | $3.00 | $2.00 | $1.00 | $1.50 | $2.00 | $1.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 22 MNHR | $80.00 | $100 | $40.00 | $100 | $200 | $75.00 | $100 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 13 EACH | $200 | $200 | $320 | $200 | $200 | $100 | $200 | $200 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 31 MNHR | $80.00 | $100 | $40.00 | $100 | $200 | $75.00 | $100 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 18 EACH | $200 | $200 | $320 | $200 | $200 | $100 | $200 | $200 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 25 MNHR | $80.00 | $100 | $40.00 | $100 | $200 | $75.00 | $100 | $120 |
| 514E10000 FINAL INSPECTION REPAIR | 14 EACH | $200 | $200 | $320 | $200 | $200 | $100 | $200 | $200 |
| 13% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 25,128 SF | $6 | $151k | 12% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 20,328 SF | $6 | $122k | 10% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 18,560 SF | $6 | $111k | 9% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $50k | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $29,591 | $30k | 2% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 29,089 SF | $1 | $29k | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 29,089 SF | $1 | $29k | 2% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 29,089 SF | $1 | $29k | 2% |