HAM-IR 75-03.84
HAM County · est $80M
Bid dateFriday, June 8—
HAM County · est $80M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 12%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 41 more items below.
| Item | Quantity | R1Walsh Construction Company II LLC | R2Kokosing Construction Company INC | R3Great Lakes Construction CO | % of bid |
|---|---|---|---|---|---|
| 530E99040 SPECIAL - STRUCTURES HAM-74-1908R | 1 LS | $9,577,993 | $9,200,000 | $11,000,000 | 12% |
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $9,550,000 | $10,700,000 | $12,000,000 | 12% |
| 530E99040 SPECIAL - STRUCTURES HAM-74-1908S | 1 LS | $7,250,000 | $4,000,000 | $8,000,000 | 9% |
| 530E99040 SPECIAL - STRUCTURESHAM-75-0440 | 1 LS | $6,800,000 | $4,250,000 | $8,500,000 | 8% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $6,433,001 |
| Item | Quantity | R1Walsh Construction Company II LLC | R2Kokosing Construction Company INC | R3Great Lakes Construction CO |
|---|---|---|---|---|
| 690E20080 SPECIAL - SUBSURFACE INVESTIGATIONS | 1 LS | $165,000 | $196,000 | $300,000 |
| 690E21000 SPECIAL - Ground Improvements | 1 LS | $500,000 | $90,000 | $1.00 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $200,000 | $170,000 | $400,000 |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $750,000 | $80,000 | $300,000 |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 300,000 EACH | $1.00 | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $9,300,000 |
| $13,370,000 |
| 8% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $5,800,000 | $6,000,000 | $1,000,000 | 7% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $5,495,779 | $6,500,000 | $6,700,000 | 7% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $4,900,000 | $7,300,000 | $8,000,000 | 6% |
| 530E99050 SPECIAL - RETAINING WALL | 1 LS | $4,500,000 | $7,600,000 | $8,000,000 | 6% |
| 530E99040 SPECIAL - STRUCTURESHAM-74-1852 | 1 LS | $2,500,000 | $1,300,000 | $1,800,000 | 3% |
| 611E97800 SPECIAL - DRAINAGE MSD CSO 21 | 1 LS | $2,400,000 | $1,450,000 | $2,300,000 | 3% |
| 530E99040 SPECIAL - STRUCTURESHAM-74-1840 | 1 LS | $2,300,000 | $1,500,000 | $2,000,000 | 3% |
| 530E99040 SPECIAL - STRUCTURESHAM-74-1892 | 1 LS | $2,300,000 | $1,200,000 | $2,200,000 | 3% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $2,000,000 | $2,000,000 | $2,000,000 | 2% |
| 625E99000 SPECIAL - LIGHTING | 1 LS | $1,900,000 | $1,400,000 | $1,700,000 | 2% |
| 690E20260 SPECIAL - TRAFFIC SURVEILLANCE | 1 LS | $1,800,000 | $1,000,000 | $1,100,000 | 2% |
| 690E21000 SPECIAL - Chemically Stabilized subgrade | 1 LS | $1,550,000 | $1,785,000 | $2,000,000 | 2% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $1,200,000 | $5,425,000 | $7,000,000 | 1% |
| 690E21000 SPECIAL - Traffic Control | 1 LS | $900,000 | $1,030,000 | $1,000,000 | 1% |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $850,000 | $400,000 | $1,200,000 | 1% |
| $1.00 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $100,000 | $75,000 | $30,000 |
| 690E98600 SPECIAL - Drainage System Cleaning, 36" and Under | 200 HOUR | $780 | $400 | $350 |
| 690E98600 SPECIAL - Drainage System Cleaning, over 36" | 100 HOUR | $825 | $400 | $350 |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN1.5 | 10,000 SY | $3.00 | $5.00 | $3.00 |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 1,700 CY | $195 | $195 | $195 |
| 450E99000 SPECIAL - RIGID PAVEMENT | 1 LS | $160,000 | $235,000 | $170,000 |
| 690E21000 SPECIAL - Access Road | 1 LS | $80,000 | $80,000 | $185,000 |
| 690E21000 SPECIAL - Subgrade Treatment | 1 LS | $20,678 | $20,000 | $120,000 |
| 251E01020 PARTIAL DEPTH PAVEMENT REPAIR (442), (3 INCHES) | 4,500 SY | $45.00 | $33.00 | $45.00 |
| 252E01000 FULL DEPTH RIGID PAVEMENT REMOVAL AND FLEXIBLE REP | 4,800 SY | $170 | $130 | $170 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 21,000 FT | $3.00 | $4.50 | $2.00 |
| 690E21000 SPECIAL - Landscaping and Bioretention cell | 1 LS | $90,000 | $300,000 | $400,000 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $500 | $1,000 | $900 |
| 690E21000 SPECIAL - AIR EMISSION AND RUNOFF CONTROL | 1 LS | $52,500 | $19,500 | $10,000 |
| 690E21000 SPECIAL - SITE SPECIFIC HEALTH AND SAFETY PLAN | 1 LS | $22,500 | $5,000 | $4,000 |
| 690E65000 SPECIAL - WORK INVOLVING NON-REGULATED MATERIALS | 1,500 TON | $49.50 | $55.00 | $40.00 |
| 690E65002 SPECIAL - WORK INVOLVING HAZARDOUS WASTE | 1,500 TON | $110 | $115 | $40.00 |
| 690E65010 SPECIAL - WORK INVOLVING SOLID WASTE | 1,500 TON | $58.00 | $65.00 | $40.00 |
| 690E71050 SPECIAL - ASBESTOS INSPECTION | 1 EACH | $2,500 | $16,000 | $10,000 |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 |
| 690E21000 SPECIAL -MISC.: GCWW | 1 LS | $12,000 | $15,000 | $15,000 |
| 690E65016 SPECIAL - WORK INVOLVING PETROLEUM CONTAMINATED SO | 750 TON | $43.50 | $50.00 | $55.00 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 380 FT | $122 | $135 | $50.00 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 900 SF | $122 | $50.00 | $125 |
| 530E99040 SPECIAL - STRUCTURESHAM-52-2044 | 1 LS | $75,000 | $50,000 | $35,000 |
| 107E99000 SPECIAL - UTILITY COORDINATION | 1 LS | $275,000 | $125,000 | $100,000 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $125,000 | $900,000 | $100,000 |
| 690E20220 SPECIAL - CONSTRUCTION PLANS | 1 LS | $650,000 | $1,000,000 | $300,000 |
| 100E50100 DEPARTMENT'S SHARE OF THE DISPUTE RESOLUTION BOARD | 1 LS | $217,000 | $217,000 | $217,000 |
| 100E99010 SPECIAL - PROFESSIONAL LIABILITY INSURANCE | 1 LS | $100,000 | $25,000 | $25,000 |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $520,000 | $600,000 | $990,000 |
| 108E99000 SPECIAL - CPM PROGRESS SCHEDULE | 1 LS | $100,000 | $25,000 | $20,000 |
| 111E10000 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 1 LS | $7,750 | $7,750 | $7,750 |
| 690E21000 SPECIAL -FIELD OFFICE | 1 LS | $20,000 | $300,000 | $20,000 |
| 690E98400 SPECIAL -CONSULTANT FOR CONCRETE QUALITY CONTROL I | 1 LS | $100,000 | $140,000 | $140,000 |
| 100E99000 SPECIAL - PREMIUM ON RAILROAD'S PROTECTIVE PUBLIC | 1 LS | $15,000 | $20,000 | $20,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 530E99040 SPECIAL - STRUCTURES HAM-74-1908R | 1 LS | $9,577,993 | $9.58M | 11% |
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $9,550,000 | $9.55M | 11% |
| 530E99040 SPECIAL - STRUCTURES HAM-74-1908S | 1 LS | $7,250,000 | $7.25M | 8% |
| 530E99040 SPECIAL - STRUCTURESHAM-75-0440 | 1 LS | $6,800,000 | $6.80M | 8% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $6,433,001 | $6.43M | 7% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $5,800,000 | $5.80M | 7% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $5,495,779 | $5.50M | 6% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $4,900,000 | $4.90M | 6% |
| 530E99050 SPECIAL - RETAINING WALL | 1 LS | $4,500,000 | $4.50M | 5% |
| 530E99040 SPECIAL - STRUCTURESHAM-74-1852 | 1 LS | $2,500,000 | $2.50M | 3% |