HEN-Elm St Brdg Replace
HEN County · est $0.5M
Bid dateThursday, March 12—
HEN County · est $0.5M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 46 more items below.
| Item | Quantity | R1R G Zachrich Construction INC | R2Miller Bros Const INC | R3Vernon Nagel INC | % of bid |
|---|---|---|---|---|---|
| 515E12030 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 9 EACH | $10,200 | $10,800 | $12,500 | 22% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $50,000 | $45,000 | $22,000 | 12% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 53 CY | $750 | $900 | $1,200 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $20,000 | $20,000 | 7% |
| 511E43511 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING, AS | 74 CY | $386 | $625 |
| Item | Quantity | R1R G Zachrich Construction INC | R2Miller Bros Const INC | R3Vernon Nagel INC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,500 | $1,500 | $2,500 |
| 202E23000 PAVEMENT REMOVED | 217 SY | $10.13 | $10.00 | $15.00 |
| 202E30000 WALK REMOVED | 742 SF | $1.99 | $2.00 | $3.00 |
| 203E10000 EXCAVATION | 138 CY | $12.50 | $20.00 | $15.00 |
| 203E20000 EMBANKMENT | 121 CY | $11.87 | $20.00 | $15.00 |
| 204E10000 SUBGRADE COMPACTION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $600 |
| 7% |
| 526E10000 REINFORCED CONCRETE APPROACH SLABS (T=12") | 114 SY | $242 | $285 | $285 | 6% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $25,000 | $10,000 | $18,000 | 6% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 770 FT | $28.00 | $45.00 | $32.00 | 5% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 14,274 LB | $1.30 | $1.60 | $1.10 | 4% |
| 517E75120 RAILING (CONCRETE PARAPET WITH TWIN STEEL TUBE RAI | 92 FT | $160 | $225 | $250 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $10,000 | $16,000 | $10,000 | 2% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 18 CY | $500 | $385 | $500 | 2% |
| 608E10000 4" CONCRETE WALK | 1,259 SF | $7.00 | $6.50 | $9.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,640 | $4,000 | $7,000 | 2% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 20 CF | $419 | $420 | $450 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,000 | $6,500 | $6,000 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 13 CY | $550 | $410 | $550 | 2% |
| 526E90010 TYPE A INSTALLATION | 68 FT | $100 | $140 | $110 | 2% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 138 CY | $46.00 | $80.00 | $110 | 1% |
| 518E21230 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 1 LS | $5,000 | $5,000 | $5,000 | 1% |
| 301 SY |
| $2.24 |
| $2.00 |
| $1.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 10 CY | $17.84 | $20.00 | $18.00 |
| 204E21000 GRANULAR EMBANKMENT | 10 CY | $40.32 | $40.00 | $40.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $206 | $150 | $200 |
| 204E50000 GEOTEXTILE FABRIC | 30 SY | $1.77 | $3.00 | $1.25 |
| 606E15050 GUARDRAIL, TYPE MGS | 87.5 FT | $31.84 | $31.84 | $16.50 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 4 EACH | $635 | $635 | $1,500 |
| 608E13000 6" CONCRETE WALK | 92 SF | $8.00 | $8.00 | $12.00 |
| 608E53020 DETECTABLE WARNING | 8 SF | $50.00 | $27.00 | $27.00 |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 26 CY | $35.00 | $50.00 | $25.00 |
| 659E10000 SEEDING AND MULCHING | 285 SY | $8.75 | $6.00 | $8.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.03 TON | $600 | $450 | $500 |
| 659E31000 LIME | 0.05 ACRE | $30.00 | $10.00 | $90.00 |
| 659E35000 WATER | 1.3 MGAL | $1.00 | $10.00 | $1.00 |
| 832E30000 EROSION CONTROL | 2,500 EACH | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.2 CY | $2,500 | $2,600 | $3,500 |
| 611E00900 6" CONDUIT, TYPE B, FOR DRAINAGE CONNECTION | 50 FT | $10.00 | $5.00 | $15.00 |
| 611E01500 6" CONDUIT, TYPE F, FOR DRAINAGE CONNECTION | 50 FT | $10.00 | $5.00 | $13.00 |
| 611E04600 12" CONDUIT, TYPE C | 63 FT | $67.00 | $40.00 | $40.00 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,790 | $1,700 | $1,600 |
| 304E20000 AGGREGATE BASE | 47 CY | $76.00 | $65.00 | $75.00 |
| 407E20000 NON-TRACKING TACK COAT | 20 GAL | $1.00 | $2.00 | $1.00 |
| 452E10010 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 29 SY | $72.00 | $75.00 | $90.00 |
| 609E26000 CURB, TYPE 6 | 60 FT | $40.00 | $23.00 | $30.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $750 | $850 | $800 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $15.00 | $30.00 | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $15.00 | $40.00 | $25.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $58.86 | $40.00 | $65.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $3,500 | $1,000 | $2,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $1,000 | $1.00 | $2,000 |
| 507E00500 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 700 FT | $2.00 | $12.00 | $6.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 59 SY | $9.19 | $10.00 | $10.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 135 SY | $22.97 | $22.00 | $22.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 36 SF | $6.07 | $6.00 | $300 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 78 FT | $33.19 | $28.00 | $38.00 |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 36 EACH | $75.00 | $60.00 | $100 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 106 FT | $10.00 | $8.00 | $80.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 48 FT | $10.00 | $20.00 | $8.00 |
| 523E20000 DYNAMIC LOAD TESTING | 1 EACH | $3,000 | $4,000 | $2,000 |
| 530E14000 SPECIAL - STRUCTURAL SURVEY AND MONITORING OF VIBR | 1 LS | $4,800 | $13,500 | $6,800 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,000 | $4,500 | $3,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12030 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 9 EACH | $10,200 | $92k | 19% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $50,000 | $50k | 10% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 53 CY | $750 | $40k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 6% |
| 511E43511 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING, AS | 74 CY | $386 | $29k | 6% |
| 526E10000 REINFORCED CONCRETE APPROACH SLABS (T=12") | 114 SY | $241.5 | $28k | 6% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $25,000 | $25k | 5% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 770 FT | $28 | $22k | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 14,274 LB | $1.3 | $19k | 4% |
| 517E75120 RAILING (CONCRETE PARAPET WITH TWIN STEEL TUBE RAI | 92 FT | $160 | $15k | 3% |