MOT-SR 741-06.60
MOT County · est $0.5M
Bid dateThursday, March 12—
MOT County · est $0.5M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 37 more items below.
| Item | Quantity | R1Eagle Bridge CO | R2Complete General Construction Company | R3Brumbaugh Construction INC | R4Becdir Construction Company | % of bid |
|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,011 SF | $12.53 | $14.00 | $14.00 | $12.00 | 18% |
| 511E43210 CLASS QC1 CONCRETE, PIER | 82 CY | $800 | $1,400 | $900 | $1,650 | 12% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $45,000 | $22,000 | $50,000 | $140,000 | 8% |
| 511E71100 CONCRETE, MISC.:PUMPED SELF CONSOLIDATING CONCRETE | 27 CY | $1,500 | $1,400 | $1,500 |
| Item | Quantity | R1Eagle Bridge CO | R2Complete General Construction Company | R3Brumbaugh Construction INC | R4Becdir Construction Company |
|---|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 113 FT | $5.00 | $2.00 | $14.00 | $10.50 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 1 EACH | $200 | $225 | $550 | $450 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 1 EACH | $200 | $95.00 | $400 | $315 |
| 202E98300 REMOVAL MISC.:ROCK CHANNEL PROTECTION REMOVED | 29 SY | $40.00 | $30.00 | $40.00 | $70.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $2,400 |
| 7% |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 3,229 LB | $10.00 | $7.00 | $8.00 | $11.00 | 6% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $30,000 | $13,500 | $14,000 | $27,000 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $40,000 | $40,000 | $37,000 | 5% |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 161 SY | $180 | $130 | $125 | $235 | 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 8,011 SF | $3.51 | $3.00 | $3.00 | $5.00 | 5% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $25,000 | $64,000 | $75,000 | $50,000 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 8,011 SF | $3.11 | $2.50 | $2.50 | $2.50 | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 8,011 SF | $3.01 | $2.50 | $2.50 | $2.20 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $46,222 | $20,000 | 4% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $12,500 | $900 | $7,000 | $12,000 | 2% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 8,536 LB | $1.25 | $1.25 | $1.25 | $1.65 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $7,000 | $40,000 | $20,000 | 2% |
| 511E34448 CLASS QC2 CONCRETE, BRIDGE DECK (PARAPET) | 2 CY | $4,000 | $1,700 | $3,000 | $1,500 | 1% |
| 203E10000 EXCAVATION | 151 CY | $50.00 | $30.00 | $30.00 | $88.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,500 | $8,000 | $20,000 | $8,000 | 1% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 322 SY | $20.00 | $20.00 | $30.00 | $32.00 | 1% |
| 27 CY |
| $70.00 |
| $35.00 |
| $30.00 |
| $115 |
| 606E15050 GUARDRAIL, TYPE MGS | 87.5 FT | $30.50 | $27.60 | $31.00 | $32.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E(MASH 2016) | 1 EACH | $2,385 | $2,520 | $2,400 | $2,500 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 1 EACH | $1,900 | $2,260 | $1,900 | $2,000 |
| 659E00300 TOPSOIL | 388 CY | $10.00 | $30.00 | $35.00 | $50.00 |
| 659E10000 SEEDING AND MULCHING | 3,494 SY | $1.50 | $1.65 | $1.50 | $1.80 |
| 659E14000 REPAIR SEEDING AND MULCHING | 175 SY | $1.50 | $1.00 | $2.00 | $1.85 |
| 659E15000 INTER-SEEDING | 175 SY | $1.50 | $0.01 | $2.00 | $1.85 |
| 659E20000 COMMERCIAL FERTILIZER | 0.47 TON | $1,250 | $500 | $650 | $800 |
| 659E31000 LIME | 0.72 ACRE | $10.00 | $200 | $5.00 | $100 |
| 659E35000 WATER | 19 MGAL | $10.00 | $1.00 | $5.00 | $10.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 3 EACH | $9.50 | $8.00 | $30.00 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 12.5 FT | $27.00 | $28.00 | $27.00 | $29.00 |
| 630E80100 SIGN, FLAT SHEET | 3 SF | $60.00 | $45.00 | $60.00 | $63.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH | $60.00 | $10.00 | $100 | $63.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $85.00 | $15.00 | $200 | $90.00 |
| 644E00204 LANE LINE, 6" | 0.14 MILE | $13,436 | $13,405 | $13,400 | $22,200 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 60 HOUR | $75.00 | $85.00 | $75.00 | $93.00 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 0.14 MILE | $7,000 | $6,120 | $6,125 | $22,600 |
| 614E24202 WORK ZONE DOTTED LINE, CLASS I, 6", 642 PAINT | 300 FT | $2.00 | $2.15 | $2.15 | $5.50 |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2 SY | $2,000 | $1,800 | $600 | $1,165 |
| 304E20000 AGGREGATE BASE | 1 CY | $500 | $450 | $100 | $500 |
| 509E10001 EPOXY COATED REINFORCING STEEL, AS PER PLAN | 2,561 LB | $1.25 | $1.27 | $1.40 | $1.70 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 60 EACH | $15.00 | $13.70 | $35.00 | $25.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 15 MNHR | $85.20 | $30.00 | $30.00 | $90.00 |
| 514E10000 FINAL INSPECTION REPAIR | 9 EACH | $70.16 | $150 | $150 | $105 |
| 514E27700 FIELD PAINTING, MISC.:ZINC RICH PRIMER | 118 SF | $40.09 | $60.00 | $135 | $58.00 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 10 EACH | $350 | $1,250 | $1,000 | $830 |
| 516E46900 BEARING DEVICE, MISC.: ELASTOMERIC BEARING PAD WIT | 4 EACH | $1,500 | $950 | $900 | $1,500 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 19 SF | $230 | $160 | $400 | $215 |
| 619E16000 FIELD OFFICE, TYPE A | 5 MNTH | $1,250 | $2,000 | $900 | $1,850 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $5,000 | $5,000 | $4,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 8,011 SF | $12.53 | $100k | 16% |
| 511E43210 CLASS QC1 CONCRETE, PIER | 82 CY | $800 | $66k | 10% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $45,000 | $45k | 7% |
| 511E71100 CONCRETE, MISC.:PUMPED SELF CONSOLIDATING CONCRETE | 27 CY | $1,500 | $41k | 6% |
| 513E10201 STRUCTURAL STEEL MEMBERS, LEVEL UF, AS PER PLAN | 3,229 LB | $10 | $32k | 5% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $30,000 | $30k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $30k | 5% |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 161 SY | $180 | $29k | 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 8,011 SF | $3.51 | $28k | 4% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $25,000 | $25k | 4% |