MED-SR 162-11.70
MED County · est $0.3M
Bid dateThursday, May 7—
MED County · est $0.3M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 41 more items below.
| Item | Quantity | R1Great Lakes Demolition Company | R2Adena Corporation | R3Stanley Miller Construction Company | R4Digioia-suburban Excavating LLC | R5Lockhart Concrete CO | R6Ruhlin Company | R7Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 611E53300 53" X 83" CONDUIT, TYPE A, 706.04 | 36 FT | $645 | $718 | $675 | $580 | $1,000 | $800 | $668 | 15% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 29 CY | $800 | $402 | $389 | $757 | $750 | $950 | $446 | 15% |
| 511E46010 |
| Item | Quantity | R1Great Lakes Demolition Company | R2Adena Corporation | R3Stanley Miller Construction Company | R4Digioia-suburban Excavating LLC | R5Lockhart Concrete CO | R6Ruhlin Company | R7Eclipse CO LLC |
|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,700 | $5,549 | $4,333 | $6,200 | $9,000 | $14,200 | $5,355 |
| 202E23000 PAVEMENT REMOVED | 126 SY | $20.00 | $31.41 | $14.00 | $29.25 | $12.00 | $30.00 | $21.50 |
| 202E35100 PIPE REMOVED, 24" AND UNDER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 13 CY |
| $800 |
| $605 |
| $719 |
| $757 |
| $1,000 |
| $1,500 |
| $790 |
| 7% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $7,205 | $9,834 | $6,500 | $4,000 | $7,500 | $15,000 | 7% |
| 611E13900 30" CONDUIT, TYPE D | 136 FT | $68.00 | $69.33 | $41.00 | $54.00 | $100 | $88.50 | $97.00 | 6% |
| 442E10501 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 25 CY | $330 | $357 | $389 | $354 | $300 | $425 | $368 | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 34 CY | $225 | $305 | $239 | $217 | $300 | $300 | $226 | 5% |
| 203E20000 EMBANKMENT | 282 CY | $23.00 | $15.02 | $40.00 | $31.10 | $30.00 | $14.00 | $16.00 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 5,243 LB | $1.05 | $1.53 | $1.31 | $1.00 | $1.00 | $3.25 | $3.00 | 4% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 53 CY | $95.00 | $103 | $70.00 | $102 | $125 | $110 | $123 | 3% |
| 304E20000 AGGREGATE BASE | 74 CY | $65.00 | $105 | $73.60 | $77.50 | $50.00 | $70.00 | $68.50 | 3% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,370 | $4,100 | $3,889 | $2,400 | $2,250 | $2,370 | $2,520 | 3% |
| 659E00300 TOPSOIL | 105 CY | $45.00 | $27.42 | $35.00 | $59.00 | $30.00 | $55.00 | $46.50 | 3% |
| 606E15350 GUARDRAIL, TYPE MGS WITH SOCKETED POSTS | 25 FT | $183 | $146 | $139 | $185 | $125 | $183 | $118 | 3% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 126 SY | $32.00 | $16.64 | $21.00 | $31.00 | $5.75 | $25.00 | $15.50 | 3% |
| 202E11001 STRUCTURE REMOVED, AS PER PLAN | 1 LS | $4,000 | $7,399 | $2,467 | $5,750 | $29,000 | $4,500 | $3,434 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $2,624 | $7,778 | $3,500 | $5,000 | $4,500 | $14,000 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 200 FT | $19.20 | $19.68 | $18.30 | $19.50 | $25.00 | $19.20 | $26.50 | 3% |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 4 CY | $800 | $426 | $882 | $757 | $2,000 | $975 | $1,910 | 2% |
| 203E10000 EXCAVATION | 211 CY | $15.00 | $14.19 | $22.00 | $21.75 | $20.00 | $8.50 | $29.50 | 2% |
| 44 FT |
| $10.00 |
| $4.39 |
| $6.00 |
| $16.50 |
| $10.00 |
| $5.50 |
| $29.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 61 FT | $10.00 | $4.41 | $9.00 | $18.00 | $20.00 | $5.60 | $19.00 |
| 202E38000 GUARDRAIL REMOVED | 275 FT | $1.60 | $4.98 | $2.00 | $1.75 | $3.00 | $1.60 | $3.50 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 3 EACH | $265 | $102 | $306 | $270 | $250 | $265 | $235 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 1 EACH | $105 | $152 | $139 | $107 | $250 | $105 | $235 |
| 204E10000 SUBGRADE COMPACTION | 158 SY | $2.00 | $3.62 | $1.00 | $2.25 | $2.00 | $4.00 | $3.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $985 | $1,611 | $1,528 | $1,000 | $1,100 | $985 | $1,050 |
| 601E11000 RIPRAP, TYPE D | 17 SY | $85.00 | $203 | $189 | $50.00 | $150 | $100 | $159 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $100 | $100 | $150 | $500 | $100 | $105 |
| 659E10000 SEEDING AND MULCHING | 943 SY | $1.00 | $2.74 | $7.50 | $1.25 | $1.00 | $1.30 | $3.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 47 SY | $4.00 | $1.00 | $1.00 | $13.00 | $1.00 | $3.00 | $3.50 |
| 659E15000 INTER-SEEDING | 47 SY | $4.00 | $1.00 | $3.00 | $2.05 | $1.00 | $1.00 | $3.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.13 TON | $1,000 | $2,249 | $800 | $545 | $700 | $800 | $641 |
| 659E31000 LIME | 0.19 ACRE | $553 | $970 | $100 | $47.11 | $600 | $5.00 | $78.53 |
| 659E35000 WATER | 5.22 MGAL | $9.96 | $1.00 | $1.00 | $685 | $50.00 | $1.00 | $1.00 |
| 670E00520 SLOPE EROSION PROTECTION MAT, TYPE B | 226 SY | $2.00 | $2.09 | $4.00 | $2.90 | $5.00 | $3.50 | $2.50 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 87 FT | $25.00 | $5.11 | $9.00 | $6.25 | $15.00 | $9.00 | $12.50 |
| 611E06400 15" CONDUIT, TYPE D | 60 FT | $35.00 | $28.88 | $33.50 | $34.00 | $95.00 | $68.00 | $81.50 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,500 | $1,066 | $1,587 | $1,900 | $1,500 | $2,900 | $2,153 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $1,750 | $1,569 | $1,660 | $2,000 | $2,000 | $2,900 | $2,207 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3.0") | 128 SY | $20.00 | $20.50 | $24.50 | $22.25 | $15.00 | $28.00 | $23.00 |
| 407E10000 TACK COAT | 49 GAL | $3.80 | $11.71 | $5.60 | $5.05 | $2.00 | $3.00 | $5.50 |
| 408E10001 PRIME COAT, AS PER PLAN | 54 GAL | $5.00 | $23.43 | $11.10 | $10.10 | $2.00 | $3.00 | $10.50 |
| 621E00100 RPM | 2 EACH | $985 | $1,464 | $100 | $606 | $350 | $1,173 | $1,050 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2 EACH | $50.00 | $25.00 | $50.00 | $11.00 | $150 | $5.00 | $24.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 11 EACH | $7.55 | $9.95 | $9.50 | $8.00 | $12.00 | $8.50 | $10.50 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.12 MILE | $6,975 | $8,171 | $7,750 | $5,585 | $6,000 | $6,975 | $17,850 |
| 642E00300 CENTER LINE, TYPE 1 | 0.06 MILE | $9,300 | $10,895 | $10,334 | $7,445 | $8,000 | $9,300 | $17,850 |
| 614E12420 DETOUR SIGNING | 1 LS | $2,865 | $3,356 | $3,183 | $2,700 | $3,000 | $2,865 | $6,067 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $1,000 | $1,113 | $1,056 | $950 | $1,000 | $525 | $1,040 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $2,000 | $4,048 | $4,445 | $5,580 | $5,000 | $7,000 | $19,546 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $3,000 | $4,353 | $4,045 | $8,530 | $2,000 | $16,000 | $5,669 |
| 512E33000 TYPE 2 WATERPROOFING | 44 SY | $28.00 | $38.34 | $49.00 | $26.00 | $12.00 | $87.00 | $12.50 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 42 SF | $1.00 | $4.32 | $4.00 | $1.00 | $5.00 | $15.00 | $6.50 |
| 518E21230 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 1 LS | $2,499 | $3,137 | $1,837 | $2,400 | $2,000 | $1,400 | $7,701 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,770 | $1,992 | $2,800 | $1,300 | $6,700 | $1,232 | $8,500 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $2,000 | $2,144 | $3,797 | $6,875 | $4,110 | $10,000 | $10,500 |
| 619E16000 FIELD OFFICE, TYPE A | 2 MNTH | $500 | $527 | $1,500 | $1,000 | $500 | $830 | $500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E53300 53" X 83" CONDUIT, TYPE A, 706.04 | 36 FT | $645 | $23k | 12% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 29 CY | $800 | $23k | 12% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 13 CY | $800 | $10k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 5% |
| 611E13900 30" CONDUIT, TYPE D | 136 FT | $68 | $9k | 5% |
| 442E10501 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 25 CY | $330 | $8k | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 34 CY | $225 | $8k | 4% |
| 203E20000 EMBANKMENT | 282 CY | $23 | $6k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 5,243 LB | $1.05 | $6k | 3% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 53 CY | $95 | $5k | 3% |