ASD-SR 179-04.91
ASD County · est $0.2M
Bid dateThursday, May 21—
ASD County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 22 more items below.
| Item | Quantity | R1Adena Corporation | R2Stanley Miller Construction Company | R3Shrock Premier Custom Construction | R4LLC Great Lakes Demolition Company | R5Eclipse CO LLC | R6Kelstin INC | R7Lockhart Concrete CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 611E23600 60" CONDUIT, TYPE A, 706.02, 707.33, 707.04 (0.109 | 63 FT | $453 | $431 | $524 | $700 | $400 | $750 | $500 | 22% |
| 602E20000 CONCRETE MASONRY | 28 CY | $829 | $710 | $934 | $1,060 | $1,336 | $1,200 | $700 | 18% |
| 301E46000 |
| Item | Quantity | R1Adena Corporation | R2Stanley Miller Construction Company | R3Shrock Premier Custom Construction | R4LLC Great Lakes Demolition Company | R5Eclipse CO LLC | R6Kelstin INC | R7Lockhart Concrete CO |
|---|---|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 122 SY | $15.72 | $19.31 | $15.60 | $25.00 | $15.50 | $9.00 | $10.00 |
| 202E75000 FENCE REMOVED | 196 FT | $0.77 | $2.00 | $7.54 | $10.00 | $4.50 | $3.00 | $6.00 |
| 203E10000 EXCAVATION | 87 CY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 29 CY |
| $321 |
| $300 |
| $329 |
| $286 |
| $278 |
| $295 |
| $275 |
| 7% |
| 442E10501 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 20 CY | $345 | $328 | $91.50 | $350 | $304 | $300 | $300 | 5% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $3,214 | $2,722 | $2,440 | $3,250 | $2,525 | $2,600 | $2,100 | 5% |
| 606E15050 GUARDRAIL, TYPE MGS | 212.5 FT | $25.70 | $20.56 | $24.40 | $16.50 | $19.00 | $20.00 | $18.00 | 4% |
| 202E11001 STRUCTURE REMOVED, AS PER PLAN | 1 LS | $5,374 | $13,967 | $9,479 | $12,500 | $6,500 | $7,000 | $3,500 | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $4,766 | $6,445 | $8,979 | $5,000 | $5,000 | $5,000 | $2,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $4,733 | $8,111 | $5,039 | $10,000 | $13,869 | $15,000 | $9,500 | 4% |
| 304E20000 AGGREGATE BASE | 42 CY | $105 | $106 | $10.17 | $80.00 | $88.50 | $62.50 | $50.00 | 3% |
| 203E20000 EMBANKMENT | 222 CY | $19.36 | $31.25 | $25.28 | $25.00 | $17.00 | $40.00 | $20.00 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,988 | $2,167 | $3,843 | $3,500 | $7,000 | $5,000 | $1,000 | 3% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 22 CY | $179 | $132 | $229 | $126 | $117 | $160 | $120 | 3% |
| 601E11000 RIPRAP, TYPE D | 10 SY | $350 | $323 | $336 | $200 | $193 | $50.00 | $50.00 | 3% |
| 614E12420 DETOUR SIGNING | 1 LS | $3,330 | $3,340 | $5,179 | $3,000 | $3,695 | $4,000 | $5,000 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3.0 INCH) | 122 SY | $24.61 | $22.25 | $24.40 | $25.00 | $20.50 | $25.00 | $10.00 | 2% |
| 623E38500 MONUMENT ASSEMBLY | 2 EACH | $1,496 | $1,291 | $938 | $1,325 | $1,159 | $120 | $350 | 2% |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,285 | $1,111 | $958 | $925 | $1,031 | $1,000 | $1,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,103 | $2,675 | $7,320 | $5,000 | $4,500 | $4,000 | $4,900 | 2% |
| 659E10000 SEEDING AND MULCHING | 796 SY | $2.53 | $4.82 | $8.57 | $1.50 | $4.50 | $10.00 | $1.00 | 2% |
| $19.33 |
| $27.00 |
| $18.66 |
| $20.00 |
| $25.50 |
| $50.00 |
| $20.00 |
| 204E10000 SUBGRADE COMPACTION | 139 SY | $2.21 | $1.00 | $5.27 | $3.00 | $4.00 | $5.00 | $2.00 |
| 607E98000 FENCE, MISC.: TEMPORARY FENCING | 129 FT | $5.79 | $13.00 | $4.83 | $10.00 | $35.00 | $25.00 | $900 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 2 EACH | $87.64 | $275 | $427 | $300 | $258 | $200 | $100 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $100 | $100 | $244 | $175 | $103 | $100 | $200 |
| 659E00300 TOPSOIL | 88 CY | $17.34 | $25.00 | $55.04 | $60.00 | $76.50 | $40.00 | $30.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.11 TON | $1,753 | $500 | $610 | $1,000 | $629 | $1,000 | $700 |
| 659E31000 LIME | 0.16 ACRE | $767 | $200 | $2,150 | $600 | $77.50 | $500 | $500 |
| 659E35000 WATER | 4.3 MGAL | $1.00 | $1.00 | $1.22 | $10.00 | $1.00 | $5.00 | $50.00 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 40 FT | $9.44 | $25.40 | $42.40 | $25.00 | $17.50 | $10.00 | $10.00 |
| 407E10000 TACK COAT | 35 GAL | $11.68 | $11.12 | $206 | $4.00 | $10.50 | $10.00 | $10.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 6 EACH | $11.68 | $11.12 | $15.00 | $10.00 | $10.50 | $10.00 | $12.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 23 FT | $11.39 | $16.70 | $26.84 | $7.00 | $10.00 | $30.00 | $10.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $79.46 | $65.00 | $128 | $25.00 | $70.00 | $105 | $68.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $37.97 | $25.00 | $434 | $25.00 | $51.50 | $100 | $50.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.04 MILE | $25,188 | $23,969 | $26,291 | $6,975 | $31,920 | $22,000 | $22,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.02 MILE | $33,584 | $31,934 | $35,063 | $9,300 | $32,111 | $29,000 | $30,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,431 | $1,667 | $3,715 | $5,000 | $9,500 | $5,000 | $2,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,005 | $8,218 | $5,490 | $5,000 | $8,800 | $3,500 | $3,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E23600 60" CONDUIT, TYPE A, 706.02, 707.33, 707.04 (0.109 | 63 FT | $452.97 | $29k | 20% |
| 602E20000 CONCRETE MASONRY | 28 CY | $828.82 | $23k | 16% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 29 CY | $320.74 | $9k | 6% |
| 442E10501 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 20 CY | $344.72 | $7k | 5% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $3,214 | $6k | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 212.5 FT | $25.7 | $5k | 4% |
| 202E11001 STRUCTURE REMOVED, AS PER PLAN | 1 LS | $5,374 | $5k | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $4,766 | $5k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $4,733 | $5k | 3% |
| 304E20000 AGGREGATE BASE | 42 CY | $104.78 | $4k | 3% |