BRO-CR 42A-00.28
BRO County · est $0.9M
Bid dateThursday, June 4—
BRO County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 9.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 56 more items below.
| Item | Quantity | R1Sunesis Construction CO | R2D G M INC | R3Complete General Construction Company | R4Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|
| 515E12090 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 7 EACH | $39,426 | $46,285 | $41,000 | $36,660 | 36% |
| 524E94904 DRILLED SHAFTS, 48" DIAMETER, INTO BEDROCK | 140 FT | $621 | $575 | $450 | $520 | 11% |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 98 CY | $663 | $450 | $800 | $975 | 8% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 80 CY | $694 | $800 | $850 | $1,065 |
| Item | Quantity | R1Sunesis Construction CO | R2D G M INC | R3Complete General Construction Company | R4Shelly & Sands INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $4,050 | $14,000 | $5,000 | $4,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 21 FT | $15.07 | $15.00 | $25.00 | $11.00 |
| 202E38000 GUARDRAIL REMOVED | 30 FT | $9.50 | $2.00 | $3.50 | $10.00 |
| 202E42206 ANCHOR ASSEMBLY REMOVED | 1 EACH | $450 | $250 | $145 | $325 |
| 202E53100 MAILBOX REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 156 SY | $237 | $220 | $260 | $275 | 5% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 70 CY | $464 | $400 | $575 | $590 | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 210 FT | $143 | $132 | $125 | $145 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 27,205 LB | $1.03 | $1.05 | $1.15 | $1.06 | 4% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $27,316 | $33,000 | $85,000 | $40,000 | 4% |
| 503E21100 UNCLASSIFIED EXCAVATION | 312 CY | $86.68 | $17.00 | $95.00 | $90.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $24,241 | $20,000 | $20,000 | $40,000 | 3% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 131 CY | $102 | $70.00 | $105 | $110 | 2% |
| 503E31100 ROCK EXCAVATION | 162 CY | $69.03 | $25.00 | $60.00 | $120 | 1% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $11,135 | $3,000 | $20,000 | $21,000 | 1% |
| 302E46000 ASPHALT CONCRETE BASE, PG64-22 | 49 CY | $215 | $225 | $215 | $215 | 1% |
| 304E20000 AGGREGATE BASE | 127 CY | $65.71 | $65.00 | $80.00 | $90.00 | 1% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 36 CY | $225 | $235 | $225 | $225 | 1% |
| 832E30000 EROSION CONTROL | 8,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 619E16000 FIELD OFFICE, TYPE A | 6 MNTH | $1,286 | $700 | $2,000 | $3,100 | 1% |
| 203E10000 EXCAVATION | 250 CY | $28.92 | $25.00 | $23.00 | $23.00 | 1% |
| 1 EACH |
| $25.40 |
| $50.00 |
| $20.00 |
| $120 |
| 202E98100 REMOVAL MISC.:GATE REMOVED AND RESET | 1 EACH | $900 | $1,250 | $1,480 | $1,500 |
| 203E20000 EMBANKMENT | 280 CY | $9.75 | $20.00 | $25.00 | $12.00 |
| 204E10000 SUBGRADE COMPACTION | 632 SY | $2.01 | $3.00 | $4.00 | $4.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 112.5 FT | $20.50 | $19.00 | $18.40 | $18.50 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 2 EACH | $2,150 | $1,250 | $1,185 | $1,210 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,140 | $1,000 | $990 | $810 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 3 EACH | $2,050 | $2,100 | $2,075 | $2,170 |
| 606E35003 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, AS PER PLAN | 1 EACH | $2,350 | $2,300 | $2,240 | $2,295 |
| 607E16000 FENCE REBUILT, TYPE 47 | 29 FT | $129 | $75.00 | $70.00 | $68.50 |
| 623E38500 MONUMENT ASSEMBLY | 6 EACH | $738 | $500 | $1,000 | $1,600 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $50.05 | $250 | $235 | $160 |
| 601E21060 TIED CONCRETE BLOCK MAT, TYPE 2 | 32 SY | $71.56 | $75.00 | $145 | $87.00 |
| 601E34300 ROCK CHANNEL PROTECTION, TYPE D WITHOUT FILTER | 7 CY | $90.82 | $100 | $138 | $120 |
| 659E00300 TOPSOIL | 116 CY | $22.71 | $15.00 | $35.00 | $41.00 |
| 659E10000 SEEDING AND MULCHING | 1,040 SY | $4.12 | $3.00 | $3.25 | $3.30 |
| 659E14000 REPAIR SEEDING AND MULCHING | 52 SY | $1.00 | $0.05 | $1.00 | $3.30 |
| 659E20000 COMMERCIAL FERTILIZER | 0.14 TON | $500 | $680 | $500 | $605 |
| 659E31000 LIME | 0.21 ACRE | $200 | $80.00 | $200 | $70.00 |
| 659E35000 WATER | 6 MGAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 659E40000 MOWING | 2.4 MSF | $1.00 | $100 | $1.00 | $1.00 |
| 670E00720 DITCH EROSION PROTECTION MAT, TYPE B | 135 SY | $3.25 | $4.00 | $3.25 | $3.30 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,215 | $1,500 | $2,000 | $1,215 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $1,725 | $4,000 | $4,200 | $3,700 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $5,137 | $4,000 | $4,000 | $3,810 |
| 605E31100 AGGREGATE DRAINS | 67 FT | $8.68 | $15.00 | $23.00 | $24.00 |
| 611E06400 15" CONDUIT, TYPE D | 29 FT | $49.77 | $60.00 | $88.00 | $62.00 |
| 407E10000 TACK COAT | 186 GAL | $1.85 | $1.85 | $1.85 | $1.85 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 25 CY | $113 | $100 | $140 | $122 |
| 452E12050 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 32 SY | $92.68 | $80.00 | $107 | $195 |
| 626E00112 BARRIER REFLECTOR, TYPE 3, BIDIRECTIONAL | 12 EACH | $12.00 | $8.00 | $7.50 | $22.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $30.00 | $15.00 | $30.00 | $28.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $30.00 | $15.00 | $45.00 | $28.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 15 CY | $63.92 | $40.00 | $62.00 | $80.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $65.00 | $40.00 | $85.00 | $72.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,207 | $6,000 | $4,950 | $5,000 |
| 616E10000 WATER | 1.1 MGAL | $41.46 | $1.00 | $115 | $60.00 |
| 202E23500 WEARING COURSE REMOVED | 198 SY | $15.64 | $8.00 | $24.00 | $35.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 192 SY | $25.30 | $30.00 | $25.00 | $25.00 |
| 512E33000 TYPE 2 WATERPROOFING | 11 SY | $37.26 | $25.00 | $30.00 | $61.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 42 SF | $2.93 | $25.00 | $10.00 | $11.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 84 FT | $35.74 | $37.50 | $45.00 | $26.00 |
| 516E31010 2" DEEP JOINT SEALER | 57 FT | $13.41 | $15.00 | $30.00 | $30.00 |
| 516E41100 1/8" PREFORMED BEARING PAD | 14 EACH | $8.90 | $12.00 | $118 | $16.00 |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 28 EACH | $135 | $135 | $260 | $154 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 84 CY | $73.85 | $80.00 | $85.00 | $110 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 239 FT | $14.97 | $12.00 | $16.00 | $14.50 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 125 FT | $2.47 | $15.00 | $8.00 | $7.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 50 FT | $25.78 | $15.00 | $22.00 | $7.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,562 | $18,000 | $6,000 | $5,500 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $3,242 | $18,000 | $8,000 | $6,650 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,450 | $8,000 | $5,000 | $18,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12090 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 7 EACH | $39,426 | $276k | 31% |
| 524E94904 DRILLED SHAFTS, 48" DIAMETER, INTO BEDROCK | 140 FT | $620.83 | $87k | 10% |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 98 CY | $662.84 | $65k | 7% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 80 CY | $694.35 | $56k | 6% |
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 156 SY | $237.02 | $37k | 4% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 70 CY | $463.88 | $32k | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 210 FT | $143.3 | $30k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 27,205 LB | $1.03 | $28k | 3% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $27,316 | $27k | 3% |
| 503E21100 UNCLASSIFIED EXCAVATION | 312 CY | $86.68 | $27k | 3% |