LUC-IR 475/US 23-09.54/09.63 Noisewall
LUC County · est $6.5M
Bid dateThursday, September 17—
LUC County · est $6.5M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 3.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 63 more items below.
| Item | Quantity | R1Great Lakes Construction CO | R2Kokosing Construction Company INC | R3Miller Bros Const INC | R4Complete General Construction Company | R5Beaver Excavating Company | R6E S Wagner Company | % of bid |
|---|---|---|---|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 194,324 SF | $24.80 | $25.85 | $27.50 | $26.90 | $28.45 | $29.30 | 75% |
| 622E10161 CONCRETE BARRIER, SINGLE SLOPE, TYPE D, AS PER PLA | 9,103 FT | $60.00 | $65.00 | $105 | $150 | $105 | $90.50 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $200,000 |
| Item | Quantity | R1Great Lakes Construction CO | R2Kokosing Construction Company INC | R3Miller Bros Const INC | R4Complete General Construction Company | R5Beaver Excavating Company | R6E S Wagner Company |
|---|---|---|---|---|---|---|---|
| 202E32500 CURB AND GUTTER REMOVED | 878 FT | $10.00 | $2.70 | $3.00 | $10.00 | $5.50 | $3.65 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 50 FT | $23.00 | $9.00 | $12.50 | $22.00 | $19.00 | $13.50 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 5 EACH | $145 | $145 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $200,000 |
| $200,000 |
| $200,000 |
| $200,000 |
| 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 10,300 FT | $18.00 | $7.50 | $10.00 | $25.00 | $20.00 | $12.00 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $130,000 | $77,000 | $100,000 | $75,000 | $100,000 | $207,468 | 2% |
| 203E10000 EXCAVATION | 6,313 CY | $13.00 | $10.40 | $9.00 | $20.00 | $34.00 | $18.25 | 1% |
| 832E30000 EROSION CONTROL | 76,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 203E20000 EMBANKMENT | 7,999 CY | $8.00 | $8.90 | $15.50 | $16.00 | $45.00 | $27.75 | 1% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 3,984 FT | $15.00 | $12.00 | $14.50 | $12.00 | $15.00 | $57.90 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $41,500 | $26,500 | $50,000 | $46,000 | $35,000 | $50,000 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $35,000 | $150,000 | $225,000 | $110,000 | $130,000 | $217,500 | 1% |
| 659E00300 TOPSOIL | 1,685 CY | $20.00 | $5.40 | $16.00 | $40.00 | $16.00 | $41.59 | 1% |
| 622E25000 CONCRETE BARRIER END SECTION, TYPE D | 6 EACH | $5,000 | $2,650 | $4,325 | $3,250 | $3,850 | $3,365 | 0% |
| 622E25050 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 12 EACH | $2,500 | $1,550 | $3,500 | $3,300 | $3,820 | $3,110 | 0% |
| 630E21200 OVERHEAD SIGN SUPPORT, TYPE TC-12.30, DESIGN 12 | 1 EACH | $27,450 | $27,450 | $27,450 | $27,450 | $27,450 | $30,274 | 0% |
| 253E90100 PAVEMENT REPAIR, MISC.: FULL DEPTH REPLACEMENT | 55 SY | $400 | $400 | $425 | $400 | $400 | $440 | 0% |
| 606E15050 GUARDRAIL, TYPE MGS | 887.5 FT | $18.40 | $18.40 | $18.40 | $18.40 | $18.40 | $20.29 | 0% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $13,500 | $40,000 | $34,000 | $25,000 | $25,000 | $62,500 | 0% |
| 622E10200 BARRIER TRANSITION | 3 EACH | $4,000 | $3,800 | $7,000 | $7,500 | $7,400 | $4,170 | 0% |
| 202E38000 GUARDRAIL REMOVED | 5,879 FT | $2.00 | $2.00 | $2.00 | $2.00 | $3.00 | $2.21 | 0% |
| $145 |
| $145 |
| $145 |
| $160 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 4 EACH | $100 | $100 | $100 | $100 | $100 | $110 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED, TYPE 1 | 2 EACH | $105 | $105 | $105 | $105 | $105 | $116 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED, TYPE 2 | 3 EACH | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 | $71.69 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $500 | $400 | $285 | $400 | $265 | $220 |
| 202E75000 FENCE REMOVED | 265 FT | $2.20 | $2.20 | $2.20 | $2.20 | $2.20 | $2.43 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, NCHRP 350/MASH 2016 | 2 EACH | $2,380 | $2,380 | $2,380 | $2,380 | $2,380 | $2,625 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,160 | $2,160 | $2,160 | $2,160 | $2,160 | $2,382 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 4 EACH | $640 | $640 | $640 | $640 | $640 | $706 |
| 607E23000 FENCE, TYPE CLT | 116 FT | $49.50 | $49.50 | $49.50 | $49.50 | $49.50 | $54.59 |
| 607E61201 GATE, TYPE CLT, AS PER PLAN | 1 EACH | $4,340 | $4,340 | $4,340 | $4,340 | $4,340 | $4,786 |
| 609E24510 CURB, TYPE 4-C | 56 FT | $50.00 | $55.00 | $44.00 | $42.00 | $45.00 | $40.75 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 75 SY | $85.00 | $67.50 | $52.00 | $80.00 | $93.00 | $106 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 | $44.12 |
| 659E10000 SEEDING AND MULCHING | 15,180 SY | $0.65 | $0.65 | $0.65 | $0.65 | $0.65 | $2.07 |
| 659E14000 REPAIR SEEDING AND MULCHING | 759 SY | $0.65 | $0.65 | $0.65 | $0.65 | $0.65 | $3.64 |
| 659E15000 INTER-SEEDING | 759 SY | $0.40 | $0.40 | $0.40 | $0.40 | $0.40 | $0.44 |
| 659E20000 COMMERCIAL FERTILIZER | 2.21 TON | $580 | $580 | $580 | $580 | $580 | $640 |
| 659E31000 LIME | 3.14 ACRE | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $11.03 |
| 659E35000 WATER | 84 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.10 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $5,000 | $2,350 | $2,500 | $4,000 | $2,500 | $5,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $4,250 | $7,500 | $6,500 | $6,000 | $3,500 | $12,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $7,500 | $10,900 | $10,000 | $14,000 | $13,000 | $11,500 |
| 602E20000 CONCRETE MASONRY | 0.3 CY | $2,250 | $2,200 | $1,400 | $2,300 | $1,800 | $2,884 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 200 FT | $40.00 | $30.00 | $23.00 | $15.00 | $10.00 | $24.79 |
| 611E06100 15" CONDUIT, TYPE C | 22 FT | $120 | $85.00 | $45.50 | $225 | $52.00 | $150 |
| 611E99114 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE D | 1 EACH | $10,000 | $7,000 | $8,675 | $8,000 | $8,400 | $10,000 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 12 EACH | $325 | $250 | $180 | $260 | $260 | $421 |
| 625E00450 CONNECTION, FUSED PULL APART | 4 EACH | $100 | $100 | $100 | $230 | $100 | $110 |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 200 FT | $11.50 | $11.50 | $11.50 | $28.00 | $11.50 | $12.68 |
| 625E25500 CONDUIT, 3", 725.04 | 25 FT | $22.00 | $22.00 | $22.00 | $32.00 | $22.00 | $24.26 |
| 625E29001 TRENCH, AS PER PLAN | 425 FT | $7.00 | $7.00 | $7.00 | $20.00 | $7.00 | $7.72 |
| 625E30700 PULL BOX, 725.08, 18" | 1 EACH | $1,375 | $1,375 | $1,375 | $1,400 | $1,375 | $1,516 |
| 625E32000 GROUND ROD | 1 EACH | $285 | $285 | $200 | $400 | $300 | $293 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, ONE WAY | 105 EACH | $7.20 | $7.20 | $7.20 | $7.20 | $7.20 | $7.94 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE WAY | 17 EACH | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.82 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 88 FT | $13.00 | $13.00 | $13.00 | $13.00 | $13.00 | $14.34 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 65.4 FT | $22.00 | $22.00 | $22.00 | $22.00 | $22.00 | $24.26 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 42.4 FT | $24.00 | $24.00 | $24.00 | $24.00 | $24.00 | $26.47 |
| 630E07500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X22 | 49.2 FT | $48.00 | $48.00 | $48.00 | $48.00 | $48.00 | $52.94 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 46.5 FT | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $33.09 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 10 EACH | $345 | $345 | $345 | $345 | $345 | $380 |
| 630E80100 SIGN, FLAT SHEET | 38 SF | $13.50 | $13.50 | $13.50 | $13.50 | $13.50 | $14.89 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 73 SF | $17.00 | $17.00 | $17.00 | $17.00 | $17.00 | $18.75 |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 253 SF | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 | $19.85 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 10 EACH | $845 | $845 | $845 | $845 | $845 | $932 |
| 630E84510 RIGID OVERHEAD SIGN SUPPORT FOUNDATION | 1 EACH | $7,125 | $7,125 | $7,125 | $7,125 | $7,125 | $7,858 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 6 EACH | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $11.03 |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 3 EACH | $185 | $185 | $185 | $185 | $185 | $204 |
| 630E85600 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND REERECTIO | 5 EACH | $345 | $345 | $345 | $345 | $345 | $380 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $16.54 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 5 EACH | $265 | $265 | $265 | $265 | $265 | $292 |
| 607E98000 FENCE, MISC.: TEMPORARY FENCE | 650 FT | $7.50 | $4.75 | $5.70 | $5.70 | $5.00 | $6.29 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $80.00 | $70.00 | $65.00 | $82.50 | $90.00 | $75.00 |
| 614E12336 WORK ZONE IMPACT ATTENUATOR (UNIDIRECTIONAL) | 4 EACH | $1,900 | $2,000 | $2,120 | $1,900 | $2,375 | $3,000 |
| 614E12500 REPLACEMENT SIGN | 5 EACH | $200 | $200 | $192 | $200 | $200 | $309 |
| 614E12600 REPLACEMENT DRUM | 20 EACH | $50.00 | $53.25 | $56.00 | $95.00 | $60.00 | $81.75 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE-WAY | 206 EACH | $11.00 | $11.00 | $6.00 | $11.00 | $9.00 | $6.35 |
| 614E13350 OBJECT MARKER, ONE WAY | 206 EACH | $13.00 | $13.00 | $12.00 | $13.00 | $12.00 | $11.15 |
| 616E10000 WATER | 29 MGAL | $50.00 | $75.00 | $75.00 | $60.00 | $115 | $95.00 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $1,000 | $5,000 | $500 | $4,000 | $7,000 | $12,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 194,324 SF | $24.8 | $4.82M | 73% |
| 622E10161 CONCRETE BARRIER, SINGLE SLOPE, TYPE D, AS PER PLA | 9,103 FT | $60 | $546k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $200,000 | $200k | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 10,300 FT | $18 | $185k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $130,000 | $130k | 2% |
| 203E10000 EXCAVATION | 6,313 CY | $13 | $82k | 1% |
| 832E30000 EROSION CONTROL | 76,000 EACH | $1 | $76k | 1% |
| 203E20000 EMBANKMENT | 7,999 CY | $8 | $64k | 1% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 3,984 FT | $15 | $60k | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $41,500 | $42k | 1% |