| Item | Quantity | R1Complete General Construction Company | R2Bridge Specialists INC | R3Armstrong Steel Erectors INC | R4Bcc Ohio INC | R5Eagle Bridge CO | R6Miller Bros Const INC | R7Brumbaugh Construction INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 848E20001 SURFACE PREPARATION USING HYDRODEMOLITION, AS PER | 902 SY | $60.00 | $62.00 | $52.00 | $45.20 | $77.00 | $78.50 | $65.00 | 25% |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 462.5 FT | $83.00 | $91.60 | $82.50 | $103 | $82.50 | $82.50 | $115 | 18% |
| Item | Quantity | R1Complete General Construction Company | R2Bridge Specialists INC | R3Armstrong Steel Erectors INC | R4Bcc Ohio INC | R5Eagle Bridge CO | R6Miller Bros Const INC | R7Brumbaugh Construction INC |
|---|---|---|---|---|---|---|---|---|
| 659E14000 REPAIR SEEDING AND MULCHING | 16 SY | $0.61 | $0.50 | $0.90 | $0.53 | $1.00 | $4.72 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $519 | $425 | $600 | $446 | $750 | $600 | $600 |
| 659E35000 WATER | 2 MGAL |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR |
| 902 SY |
| $42.50 |
| $46.00 |
| $46.00 |
| $61.06 |
| $68.00 |
| $83.00 |
| $55.00 |
| 18% |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 68 CY | $185 | $90.00 | $188 | $323 | $210 | $215 | $200 | 6% |
| 516E46701 RESET BEARING, AS PER PLAN | 6 EACH | $1,800 | $540 | $500 | $970 | $1,750 | $750 | $2,500 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $21,264 | $9,030 | $8,915 | $8,500 | $4,000 | $23,973 | 5% |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 559 FT | $13.50 | $14.00 | $15.00 | $10.48 | $13.00 | $18.00 | $10.00 | 3% |
| 517E76302 RAILING, MISC.: REPAIR OF COMPROMISED TOP ANCHOR | 10 EACH | $750 | $200 | $412 | $758 | $200 | $600 | $400 | 3% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,000 | $5,400 | $7,875 | $5,100 | $9,000 | $4,000 | $9,000 | 3% |
| 848E50000 HAND CHIPPING | 120 SY | $50.00 | $25.00 | $116 | $113 | $75.00 | $100 | $100 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 13 CY | $367 | $370 | $367 | $385 | $367 | $800 | $415 | 2% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $4,500 | $5,000 | $13,000 | $11,325 | $6,500 | $7,500 | $6,000 | 2% |
| 659E10000 SEEDING AND MULCHING | 318 SY | $10.37 | $8.50 | $1.40 | $8.93 | $2.50 | $4.72 | $5.00 | 2% |
| 848E50100 TEST SLAB | 1 LS | $3,000 | $2,500 | $1,800 | $968 | $1,500 | $2,500 | $1,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,500 | $5,000 | $2,072 | $3,136 | $5,000 | $3,000 | $5,000 | 1% |
| 202E23500 WEARING COURSE REMOVED | 268 SY | $8.00 | $6.00 | $6.49 | $9.64 | $7.50 | $5.00 | $22.00 | 1% |
| 646E10010 EDGE LINE, 6" | 0.13 MILE | $15,580 | $28,680 | $15,580 | $16,359 | $28,680 | $15,580 | $33,000 | 1% |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 72 FT | $25.50 | $40.50 | $25.00 | $19.02 | $22.00 | $7.50 | $25.00 | 1% |
| 848E50300 WEARING COURSE REMOVED, ASPHALT | 122 SY | $13.00 | $6.00 | $12.00 | $12.80 | $15.00 | $15.00 | $36.00 | 1% |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 0% |
| $1.22 |
| $1.00 |
| $3.00 |
| $1.05 |
| $10.00 |
| $1.00 |
| $2.00 |
| 407E10000 TACK COAT | 26 GAL | $18.00 | $18.00 | $18.00 | $18.90 | $18.00 | $1.00 | $15.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1 EACH | $181 | $50.00 | $25.00 | $48.75 | $10.00 | $25.00 | $50.00 |
| 646E10200 CENTER LINE | 0.07 MILE | $10,980 | $28,740 | $10,980 | $11,529 | $28,740 | $10,980 | $33,000 |
| 202E23501 WEARING COURSE REMOVED, AS PER PLAN | 132 SY | $6.00 | $6.00 | $6.85 | $11.84 | $7.50 | $5.00 | $27.00 |
| 509E25001 UNCOATED REINFORCING STEEL, AS PER PLAN | 100 LB | $5.00 | $3.00 | $3.50 | $6.38 | $1.50 | $5.00 | $12.00 |
| 848E50200 FULL-DEPTH REPAIR | 1 CY | $1,000 | $1,000 | $1,000 | $2,475 | $1,000 | $200 | $1,500 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1.00 | $3,500 | $16,350 | $1,502 | $3,500 | $5,000 | $2,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,000 | $1,000 | $5,000 | $2,445 | $1,000 | $1,500 | $1,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 848E20001 SURFACE PREPARATION USING HYDRODEMOLITION, AS PER | 902 SY | $60 | $54k | 24% |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 462.5 FT | $83 | $38k | 17% |
| 848E10200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 902 SY | $42.5 | $38k | 17% |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 68 CY | $185 | $13k | 6% |
| 516E46701 RESET BEARING, AS PER PLAN | 6 EACH | $1,800 | $11k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 4% |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 559 FT | $13.5 | $8k | 3% |
| 517E76302 RAILING, MISC.: REPAIR OF COMPROMISED TOP ANCHOR | 10 EACH | $750 | $8k | 3% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,000 | $7k | 3% |
| 848E50000 HAND CHIPPING | 120 SY | $50 | $6k | 3% |