D04-CHIP FY2021
D04 County · est $0.6M
Bid dateThursday, November 5—
D04 County · est $0.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1Henry W Bergman INC | R2Specialized Construction INC | R3Ronyak Paving INC | % of bid |
|---|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 49,193 GAL | $3.25 | $2.25 | $2.95 | 24% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 5,000 SY | $23.00 | $29.00 | $40.00 | 17% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 132,953 SY | $0.55 | $1.20 | $0.95 | 11% |
| 886E11000 FOG SEAL | 19,943 GAL | $3.50 | $5.00 | $2.50 | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $65,000 | $23,475 | $75,000 | 10% |
| Item | Quantity | R1Henry W Bergman INC | R2Specialized Construction INC | R3Ronyak Paving INC |
|---|---|---|---|---|
| 642E00204 LANE LINE, 6", TYPE 1 | 1.82 MILE | $500 | $495 | $495 |
| 642E00500 STOP LINE, TYPE 1 | 113 FT | $3.00 | $3.00 | $3.00 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $150 | $1,500 | $1,500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 644E30030 REMOVAL OF PAVEMENT MARKING | 22.2 MILE | $2,850 | $1,439 | $1,465 | 10% |
| 624E10000 MOBILIZATION | 1 LS | $46,000 | $22,500 | $38,335 | 7% |
| 621E00100 RPM | 519 EACH | $25.00 | $30.00 | $35.80 | 2% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 16.74 MILE | $700 | $700 | $700 | 2% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 14.8 MILE | $650 | $625 | $625 | 1% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 14.8 MILE | $550 | $500 | $500 | 1% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 416 EACH | $15.00 | $20.00 | $4.00 | 1% |
| 642E00300 CENTER LINE, TYPE 1 | 5.58 MILE | $900 | $900 | $900 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,600 | $5,000 | $6,000 | 1% |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 5.46 MILE | $550 | $525 | $525 | 0% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | 0% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,500 | $1,200 | $5,000 | 0% |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 113 FT | $20.00 | $3.10 | $2.90 | 0% |
| 614E12460 WORK ZONE MARKING SIGN | 20 EACH | $100 | $75.00 | $75.00 | 0% |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 339 FT | $3.00 | $3.00 | $3.00 | 0% |
| Item |
|---|
| Qty |
|---|
| Unit price |
|---|
| Extended |
|---|
| % |
|---|
| 422E25000 EMULSION, CHIP SEAL | 49,193 GAL | $3.25 | $160k | 24% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 5,000 SY | $23 | $115k | 17% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 132,953 SY | $0.55 | $73k | 11% |
| 886E11000 FOG SEAL | 19,943 GAL | $3.5 | $70k | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $65,000 | $65k | 10% |
| 644E30030 REMOVAL OF PAVEMENT MARKING | 22.2 MILE | $2,850 | $63k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $46,000 | $46k | 7% |
| 621E00100 RPM | 519 EACH | $25 | $13k | 2% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 16.74 MILE | $700 | $12k | 2% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 14.8 MILE | $650 | $10k | 1% |