ATH-US 50-09.45
ATH County · est $2.3M
Bid dateThursday, November 19—
ATH County · est $2.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 27 more items below.
| Item | Quantity | R1Elite Contractors INC | R2Industrial Painting & Rigging INC | R3Legend Painting INC | R4Apbn INC | R5Panther Industrial Painting LLC | R6Kmx Painting INC | R7Euro Paint LLC | R8M & J Construction CO Of Pinellas County | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 55,642 SF | $6.65 | $8.00 | $6.25 | $9.00 | $8.50 | $9.00 | $6.25 | $7.00 | 24% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 43,522 SF | $6.65 | $8.00 | $6.25 | $9.00 | $8.50 |
| Item | Quantity | R1Elite Contractors INC | R2Industrial Painting & Rigging INC | R3Legend Painting INC | R4Apbn INC | R5Panther Industrial Painting LLC | R6Kmx Painting INC | R7Euro Paint LLC | R8M & J Construction CO Of Pinellas County |
|---|---|---|---|---|---|---|---|---|---|
| 642E00104 EDGE LINE, 6", TYPE 1 | 1.32 MILE | $500 | $2,615 | $2,615 | $2,615 | $100 | $2,600 | $2,615 | $3,950 |
| 642E00204 LANE LINE, 6", TYPE 1 | 0.67 MILE | $500 | $2,280 | $2,280 | $2,280 | $500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $10.00 |
| $6.22 |
| $7.00 |
| 19% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 19,668 SF | $6.65 | $8.00 | $6.50 | $9.00 | $8.50 | $9.00 | $6.53 | $7.00 | 8% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 16,403 SF | $6.65 | $8.00 | $6.50 | $9.00 | $8.50 | $10.00 | $6.53 | $7.00 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $25,000 | $24,330 | $63,030 | $50,000 | $60,000 | $28,580 | $50,500 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 55,642 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $0.50 | $1.85 | $2.50 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 55,642 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $0.50 | $1.85 | $2.50 | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 55,642 SF | $1.15 | $1.00 | $1.00 | $1.00 | $1.00 | $0.50 | $1.85 | $2.00 | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $60,000 | $33,416 | $26,500 | $20,000 | $60,000 | $30,000 | $20,500 | $24,000 | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 43,522 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $0.50 | $1.85 | $2.50 | 3% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 43,522 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $0.50 | $1.85 | $2.50 | 3% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 43,522 SF | $1.15 | $1.00 | $1.00 | $1.00 | $1.00 | $0.50 | $1.85 | $2.00 | 3% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $40,000 | $2,250 | $40,000 | $18,500 | $44,000 | $35,000 | $35,000 | $50,600 | 3% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 19,668 SF | $1.15 | $1.00 | $2.50 | $1.00 | $1.00 | $1.00 | $3.00 | $3.00 | 1% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 19,668 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $1.00 | $3.00 | $3.00 | 1% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 19,668 SF | $1.15 | $1.00 | $1.00 | $1.00 | $1.00 | $0.50 | $3.00 | $2.00 | 1% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $21,000 | $2,250 | $20,000 | $22,500 | $22,000 | $14,000 | $13,500 | $25,300 | 1% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $35,000 | $65,000 | $55,000 | $77,461 | $170,000 | $38,000 | $100,000 | 1% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 16,403 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $1.00 | $3.00 | $3.00 | 1% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 16,403 SF | $1.15 | $1.00 | $2.00 | $1.00 | $1.00 | $1.00 | $3.00 | $3.00 | 1% |
| $2,300 |
| $2,280 |
| $3,270 |
| 614E12336 WORK ZONE IMPACT ATTENUATOR (UNIDIRECTIONAL) | 2 EACH | $1,500 | $2,000 | $1,900 | $1,900 | $1,500 | $2,000 | $1,900 | $3,450 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (1 WAY) | 57 EACH | $10.00 | $10.00 | $10.00 | $10.00 | $5.00 | $10.00 | $10.00 | $25.30 |
| 614E13350 OBJECT MARKER, ONE WAY | 57 EACH | $10.00 | $13.00 | $13.00 | $13.00 | $5.00 | $13.00 | $13.00 | $28.80 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.67 MILE | $500 | $5,165 | $5,165 | $5,165 | $300 | $5,200 | $5,165 | $2,640 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 1,320 FT | $3.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $4.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,360 FT | $3.00 | $27.50 | $27.50 | $13.75 | $5.00 | $22.00 | $27.50 | $25.30 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 31 MNHR | $150 | $85.00 | $60.00 | $100 | $200 | $100 | $100 | $150 |
| 514E10001 FINAL INSPECTION REPAIR, AS PER PLAN | 21 EACH | $150 | $100 | $150 | $100 | $200 | $200 | $100 | $500 |
| 516E46701 RESET BEARING, AS PER PLAN | 8 EACH | $800 | $1,000 | $725 | $572 | $796 | $1,200 | $1,200 | $920 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $6,500 | $2,250 | $6,000 | $18,500 | $6,600 | $6,000 | $5,000 | $7,590 |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 16,403 SF | $1.15 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $3.00 | $2.00 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 26 MNHR | $150 | $85.00 | $60.00 | $100 | $200 | $100 | $100 | $150 |
| 514E10001 FINAL INSPECTION REPAIR, AS PER PLAN | 16 EACH | $150 | $100 | $150 | $100 | $200 | $200 | $100 | $500 |
| 516E46701 RESET BEARING, AS PER PLAN | 4 EACH | $675 | $1,000 | $650 | $572 | $715 | $800 | $600 | $825 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $3,500 | $2,250 | $3,000 | $5,500 | $3,300 | $3,000 | $2,500 | $3,800 |
| 202E98100 REMOVAL MISC.: SCUPPER EXTENSION REMOVED | 12 EACH | $5.00 | $15.00 | $60.00 | $100 | $100 | $500 | $400 | $1,725 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 36 MNHR | $150 | $85.00 | $60.00 | $100 | $200 | $100 | $100 | $150 |
| 514E10001 FINAL INSPECTION REPAIR, AS PER PLAN | 22 EACH | $150 | $100 | $150 | $100 | $200 | $200 | $100 | $500 |
| 516E46701 RESET BEARING, AS PER PLAN | 9 EACH | $2,000 | $1,000 | $1,950 | $572 | $2,145 | $600 | $1,200 | $2,470 |
| 516E46701 RESET BEARING, AS PER PLAN GIRDER 5 PIER 1 | 1 EACH | $2,000 | $1,400 | $1,950 | $622 | $2,145 | $8,000 | $7,500 | $2,500 |
| 202E98100 REMOVAL MISC.: SCUPPER EXTENSION REMOVED | 15 EACH | $5.00 | $12.00 | $60.00 | $100 | $100 | $500 | $400 | $1,725 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 44 MNHR | $150 | $85.00 | $60.00 | $100 | $200 | $100 | $100 | $150 |
| 514E10001 FINAL INSPECTION REPAIR, AS PER PLAN | 26 EACH | $150 | $100 | $150 | $100 | $200 | $200 | $100 | $500 |
| 516E46701 RESET BEARING, AS PER PLAN | 9 EACH | $2,000 | $1,000 | $1,950 | $572 | $2,145 | $600 | $500 | $2,470 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $15,000 | $10,000 | $26,500 | $10,000 | $5,000 | $10,000 | $3,500 | $10,000 |
| Item |
|---|
| Qty |
|---|
| Unit price |
|---|
| Extended |
|---|
| % |
|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 55,642 SF | $6.65 | $370k | 22% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 43,522 SF | $6.65 | $289k | 17% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 19,668 SF | $6.65 | $131k | 8% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 16,403 SF | $6.65 | $109k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $70k | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 55,642 SF | $1.15 | $64k | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 55,642 SF | $1.15 | $64k | 4% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 55,642 SF | $1.15 | $64k | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $60,000 | $60k | 4% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 43,522 SF | $1.15 | $50k | 3% |