MUS-SR 146-24.60
MUS County · est $0.4M
Bid dateThursday, August 27—
MUS County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 32 more items below.
| Item | Quantity | R1Bcc Ohio INC | R2Bridge Specialists INC | R3Armstrong Steel Erectors INC | R4Shelly & Sands INC | R5Ohio-west Virginia Excavating CO | R6Complete General Construction Company | R7Axis Civil Construction LLC | R8Suburban Maintenance & Construction | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 30 CY | $1,171 | $975 | $1,450 | $1,475 | $2,500 | $2,100 | $1,975 | $2,800 | 14% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN, SUPERS | 29 CY | $854 | $875 | $787 | $1,500 |
| Item | Quantity | R1Bcc Ohio INC | R2Bridge Specialists INC | R3Armstrong Steel Erectors INC | R4Shelly & Sands INC | R5Ohio-west Virginia Excavating CO | R6Complete General Construction Company | R7Axis Civil Construction LLC | R8Suburban Maintenance & Construction |
|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $720 | $1,500 | $1,945 | $2,200 | $2,000 | $8,500 | $10,000 | $5,000 |
| 202E38000 GUARDRAIL REMOVED | 398 FT | $1.89 | $1.80 | $1.80 | $1.80 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1,200 |
| $2,100 |
| $1,550 |
| $1,800 |
| 10% |
| 511E71100 CONCRETE, MISC.: PUMPED SELF CONSOLIDATING CONCRE | 6 CY | $3,921 | $893 | $1,200 | $2,600 | $4,000 | $2,100 | $2,600 | $3,000 | 9% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 200 FT | $97.44 | $92.80 | $92.80 | $92.80 | $105 | $115 | $92.80 | $138 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $17,718 | $18,500 | $10,000 | $10,000 | $10,000 | $20,000 | $25,000 | $10,000 | 7% |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 200 FT | $80.22 | $76.40 | $76.40 | $76.40 | $89.00 | $80.00 | $76.40 | $95.00 | 6% |
| 632E90400 SIGNALIZATION, MISC.: MICROWAVE DETECTOR | 2 EACH | $7,388 | $2,000 | $12,750 | $3,750 | $1,800 | $2,000 | $2,000 | $2,600 | 6% |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $14,040 | $3,150 | $22,280 | $15,000 | $15,000 | $25,000 | $25,000 | $20,000 | 6% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 9 CY | $1,304 | $900 | $800 | $2,600 | $2,200 | $1,500 | $2,400 | $1,800 | 5% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 480 FT | $21.13 | $42.00 | $20.00 | $14.00 | $20.00 | $17.00 | $26.00 | $40.00 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 6,133 LB | $1.54 | $2.00 | $1.88 | $3.20 | $1.80 | $1.50 | $2.50 | $2.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,722 | $39,000 | $24,500 | $24,750 | $32,500 | $25,000 | $28,000 | $25,000 | 3% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,753 | $2,300 | $1,900 | $2,160 | $2,500 | $2,200 | $2,200 | $3,500 | 3% |
| 209E70000 BORROW | 96 CY | $72.19 | $68.75 | $68.75 | $69.00 | $40.00 | $35.00 | $35.00 | $45.00 | 3% |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $1,990 | $500 | $1,500 | $2,960 | $1,100 | $1,500 | $2,000 | $1,500 | 2% |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 260 EACH | $20.29 | $20.00 | $22.50 | $21.00 | $21.00 | $15.00 | $30.00 | $40.00 | 2% |
| 512E10300 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN | 384 SY | $12.93 | $16.00 | $11.50 | $12.00 | $16.00 | $11.50 | $11.50 | $30.00 | 2% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E - NCHRP 350 | 2 EACH | $2,436 | $2,320 | $2,320 | $2,320 | $2,500 | $2,320 | $2,320 | $2,200 | 2% |
| AA2 606E26150 ANCHOR ASSEMBLY, MGS TYPE E - NCHRP 350 (ALTERNATE | 2 EACH | $2,436 | $2,320 | $2,320 | $2,320 | $2,500 | $2,320 | $2,320 | $2,500 | 2% |
| 644E30030 REMOVAL OF PAVEMENT MARKING | 0.46 MILE | $8,967 | $15,000 | $9,070 | $7,400 | $5,000 | $23,000 | $9,070 | $5,000 | 2% |
| $2.00 |
| $1.80 |
| $4.00 |
| $5.00 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 5 STA | $52.50 | $50.00 | $50.00 | $50.00 | $150 | $50.00 | $650 | $70.00 |
| 606E13000 GUARDRAIL, TYPE 5 | 100 FT | $19.53 | $18.60 | $18.60 | $18.60 | $20.00 | $18.60 | $18.60 | $16.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 200 FT | $20.16 | $19.20 | $19.20 | $19.20 | $20.00 | $19.20 | $19.20 | $17.00 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 4 EACH | $861 | $820 | $820 | $820 | $900 | $820 | $820 | $800 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 566 SY | $5.20 | $4.95 | $3.46 | $3.50 | $5.00 | $4.50 | $2.00 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.08 TON | $662 | $630 | $638 | $639 | $650 | $610 | $600 | $800 |
| 659E31000 LIME | 0.12 ACRE | $42.00 | $40.00 | $150 | $150 | $40.00 | $80.00 | $300 | $500 |
| 659E35000 WATER | 3.1 MGAL | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $10.00 | $2.00 |
| 832E30000 EROSION CONTROL | 1,200 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 6 EACH | $7.46 | $7.10 | $7.10 | $7.10 | $8.00 | $7.10 | $7.10 | $10.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 12 EACH | $8.40 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 46 FT | $16.28 | $15.50 | $15.50 | $15.50 | $17.00 | $15.50 | $15.50 | $18.00 |
| 630E80100 SIGN, FLAT SHEET | 12 SF | $24.68 | $23.50 | $23.50 | $23.50 | $25.00 | $23.50 | $23.50 | $20.00 |
| 646E10010 EDGE LINE, 6" | 0.18 MILE | $9,348 | $8,903 | $14,380 | $8,903 | $9,500 | $8,903 | $14,380 | $15,000 |
| 646E10200 CENTER LINE | 0.28 MILE | $12,707 | $12,102 | $14,800 | $12,102 | $13,000 | $12,102 | $14,800 | $9,800 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $343 | $150 | $234 | $255 | $275 | $150 | $150 | $300 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 12 EACH | $23.54 | $25.00 | $11.00 | $8.50 | $27.00 | $25.00 | $14.00 | $30.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 12 EACH | $23.54 | $25.00 | $13.00 | $18.00 | $30.00 | $28.00 | $16.00 | $30.00 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.19 MILE | $16,920 | $5,400 | $7,700 | $5,400 | $6,000 | $5,400 | $5,400 | $6,000 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.33 MILE | $8,244 | $2,995 | $7,370 | $3,000 | $3,200 | $2,995 | $2,995 | $3,500 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 20 FT | $16.64 | $250 | $2.50 | $12.50 | $13.00 | $12.50 | $12.50 | $15.00 |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN, SUBSTR | 1 CY | $2,145 | $4,000 | $3,112 | $3,000 | $1,500 | $2,500 | $3,500 | $10,000 |
| 202E38500 BRIDGE RAILING REMOVED | 200 FT | $3.99 | $3.80 | $3.80 | $8.00 | $17.00 | $7.00 | $7.00 | $5.00 |
| 202E98200 REMOVAL MISC.: PORTABLE BARRIER, 32", AS PER PLAN | 270 FT | $4.88 | $20.00 | $10.33 | $3.00 | $10.00 | $20.00 | $12.00 | $10.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 75 SY | $12.98 | $26.00 | $12.00 | $12.00 | $18.00 | $12.00 | $12.00 | $18.00 |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 56 FT | $26.23 | $26.00 | $30.00 | $25.50 | $58.00 | $25.50 | $25.50 | $30.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 232 FT | $10.25 | $20.00 | $20.00 | $17.00 | $16.00 | $12.00 | $11.00 | $25.00 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 8 SF | $126 | $300 | $110 | $350 | $485 | $350 | $400 | $500 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,706 | $10,843 | $5,000 | $2,000 | $5,500 | $4,000 | $3,000 | $10,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,285 | $4,000 | $4,000 | $4,500 | $3,500 | $1,500 | $5,000 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 30 CY | $1,171 | $35k | 12% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN, SUPERS | 29 CY | $854.09 | $25k | 8% |
| 511E71100 CONCRETE, MISC.: PUMPED SELF CONSOLIDATING CONCRE | 6 CY | $3,921 | $24k | 8% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 200 FT | $97.44 | $19k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $17,718 | $18k | 6% |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 200 FT | $80.22 | $16k | 5% |
| 632E90400 SIGNALIZATION, MISC.: MICROWAVE DETECTOR | 2 EACH | $7,388 | $15k | 5% |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $14,040 | $14k | 5% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 9 CY | $1,304 | $12k | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 480 FT | $21.13 | $10k | 3% |