D10-Culverts FY2021
D10 County · est $0.4M
Bid dateThursday, February 11—
D10 County · est $0.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 19items by winning bid’s extended amount.
| Item | Quantity | R1Axis Civil Construction LLC | R2Litman Excavating INC | R3Bcc Ohio INC | R4Parker Corporation | R5Geotech Services INC | R6Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 1,254 FT | $35.00 | $14.78 | $15.06 | $70.00 | $25.00 | $39.75 | 22% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 72" DI | 492 FT | $65.00 | $50.00 | $98.00 | $150 | $145 | $113 | 16% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 54" DI | 452 FT | $65.00 | $50.00 | $75.75 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $150 |
| $125 |
| $94.50 |
| 15% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 96" DI | 252 FT | $85.00 | $75.00 | $128 | $150 | $195 | $159 | 11% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $18,000 | $8,435 | $17,000 | $10,000 | $54,526 | 8% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $13,500 | $23,375 | $2,340 | $100 | $34,000 | $51,919 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $15,250 | $21,126 | $8,000 | $75,000 | $58,000 | 5% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 103" X | 58 FT | $125 | $225 | $171 | $150 | $330 | $184 | 4% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 659E10000 SEEDING AND MULCHING | 1,000 SY | $5.00 | $6.00 | $2.08 | $1.00 | $6.50 | $5.25 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $4,500 | $3,400 | $1,560 | $8,000 | $5,500 | $45,782 | 2% |
| 511E47010 CLASS QC1 CONCRETE, CULVERT | 18 CY | $250 | $646 | $169 | $650 | $800 | $392 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 19 CY | $143 | $105 | $144 | $65.00 | $350 | $80.75 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,000 | $6,000 | $2,454 | $4,850 | $6,000 | $11,400 | 1% |
| 607E15000 FENCE, TYPE 47 | 80 FT | $8.00 | $95.00 | $62.74 | $15.00 | $90.00 | $85.25 | 0% |
| 202E75000 FENCE REMOVED | 80 FT | $3.00 | $12.50 | $4.20 | $5.00 | $5.00 | $5.25 | 0% |
| 659E20000 COMMERCIAL FERTILIZER | 0.09 TON | $610 | $275 | $630 | $5,556 | $610 | $525 | 0% |
| 659E31000 LIME | 0.2 ACRE | $80.00 | $2,000 | $63.00 | $2,500 | $80.00 | $210 | 0% |
| 659E35000 WATER | 4 MGAL | $1.00 | $100 | $1.05 | $0.05 | $25.00 | $1.00 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 1,254 FT | $35 | $44k | 22% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 72" DI | 492 FT | $65 | $32k | 16% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 54" DI | 452 FT | $65 | $29k | 15% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 96" DI | 252 FT | $85 | $21k | 11% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $15k | 8% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $13,500 | $14k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $10k | 5% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN 103" X | 58 FT | $125 | $7k | 4% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1 | $6k | 3% |
| 659E10000 SEEDING AND MULCHING | 1,000 SY | $5 | $5k | 3% |