D06-PMA FY21
D06 County · est $0.4M
Bid dateThursday, February 11—
D06 County · est $0.4M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 642E01300 LANE ARROW, TYPE 1 | 1,634 EACH | $40 | $65k | 19% |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 176,353 FT | $0.34 | $60k | 17% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 6 more items below.
| Item | Quantity | R1A & A Safety INC | R2Dura Mark INC | R3Oglesby Construction INC | R4Griffin Pavement Striping LLC | % of bid |
|---|---|---|---|---|---|---|
| 642E01300 LANE ARROW, TYPE 1 | 1,634 EACH | $40.00 | $62.00 | $85.00 | $65.00 | 19% |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 176,353 FT | $0.34 | $0.39 | $0.60 | $0.60 | 17% |
| 642E00500 STOP LINE, TYPE 1 | 18,687 FT | $2.55 | $3.00 | $4.95 | $3.00 | 14% |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 27,964 FT | $1.15 | $1.30 | $2.35 | $2.25 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $33,500 | $20,000 | $175,000 | 9% |
| 642E00600 CROSSWALK LINE, TYPE 1 | 19,589 FT | $1.20 | $1.35 | $2.40 | $2.50 | 7% |
| Item | Quantity | R1A & A Safety INC | R2Dura Mark INC | R3Oglesby Construction INC | R4Griffin Pavement Striping LLC |
|---|---|---|---|---|---|
| 642E00800 CURB MARKING, TYPE 1 | 209 FT | $2.50 | $3.00 | $4.00 | $2.50 |
| 642E00900 ISLAND MARKING, TYPE 1 | 803 SF | $1.20 | $3.00 | $1.50 | $2.00 |
| 642E01322 WRONG WAY ARROW, TYPE 1 | 5 EACH | $150 | $165 | $160 | $250 |
| 642E01702 HANDICAP SYMBOL MARKING, TYPE 1 | 26 EACH | $50.00 | $85.00 | $45.00 | $75.00 |
| 642E20802 YIELD LINE, TYPE 1 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 642E00720 CHEVRON MARKING, TYPE 1 | 8,874 FT | $1.15 | $1.30 | $2.40 | $2.55 | 3% |
| 642E01602 BIKE LANE SYMBOL MARKING, TYPE 1 | 102 EACH | $100 | $85.00 | $85.00 | $235 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10,000 | $12,480 | $100,000 | 3% |
| 642E01510 DOTTED LINE, 6", TYPE 1 | 13,442 FT | $0.65 | $0.65 | $1.50 | $0.65 | 3% |
| 642E01200 PARKING LOT STALL MARKING, TYPE 1 | 17,205 FT | $0.50 | $0.85 | $0.65 | $0.65 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $75.00 | $55.00 | $70.00 | $70.00 | 2% |
| 642E01110 SCHOOL SYMBOL MARKING, 96", TYPE 1 | 35 EACH | $200 | $300 | $285 | $300 | 2% |
| 642E01000 RAILROAD SYMBOL MARKING, TYPE 1 | 27 EACH | $200 | $300 | $275 | $300 | 2% |
| 624E15001 MOBILIZATION, AS PER PLAN | 20 EACH | $250 | $500 | $250 | $700 | 1% |
| 642E01410 WORD ON PAVEMENT, 96", TYPE 1 | 95 EACH | $50.00 | $72.00 | $100 | $75.00 | 1% |
| 642E01312 LANE REDUCTION ARROW, TYPE 1 | 14 EACH | $200 | $225 | $160 | $250 | 1% |
| 642E30001 REMOVAL OF PAVEMENT MARKING, AS PER PLAN | 2,500 FT | $1.00 | $3.50 | $4.30 | $2.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,400 | $2,557 | $2,600 | $15,010 | 1% |
| 642E40000 SPEED MEASUREMENT MARKING | 3 EACH | $500 | $988 | $410 | $1,000 | 0% |
| 250 FT |
| $5.00 |
| $3.50 |
| $3.25 |
| $4.00 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 25 EACH | $10.00 | $125 | $60.00 | $175 |
| 18,687 FT |
| $2.55 |
| $48k |
| 14% |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 27,964 FT | $1.15 | $32k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $30k | 9% |
| 642E00600 CROSSWALK LINE, TYPE 1 | 19,589 FT | $1.2 | $24k | 7% |
| 642E00720 CHEVRON MARKING, TYPE 1 | 8,874 FT | $1.15 | $10k | 3% |
| 642E01602 BIKE LANE SYMBOL MARKING, TYPE 1 | 102 EACH | $100 | $10k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 642E01510 DOTTED LINE, 6", TYPE 1 | 13,442 FT | $0.65 | $9k | 2% |