BUT-SR 4-10.83
BUT County · est $1.8M
Bid dateThursday, March 11—
BUT County · est $1.8M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 122 more items below.
| Item | Quantity | R1Eagle Bridge CO | R2Rack & Ballauer Excavating CO INC | R3John R Jurgensen Company | R4Sunesis Construction CO | R5Barrett Paving Materials INC | R6Complete General Construction Company | R7Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 29,619 CY | $12.25 | $20.00 | $17.30 | $21.11 | $22.00 | $31.00 | $34.50 | 26% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 1,141 CY | $170 | $185 | $168 | $176 | $160 | $166 | $172 | 14% |
| Item | Quantity | R1Eagle Bridge CO | R2Rack & Ballauer Excavating CO INC | R3John R Jurgensen Company | R4Sunesis Construction CO | R5Barrett Paving Materials INC | R6Complete General Construction Company | R7Eclipse CO LLC |
|---|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $300 | $285 | $319 | $266 | $100 | $500 | $133 |
| 202E32500 CURB AND GUTTER REMOVED | 543 FT | $3.50 | $5.80 | $10.20 | $12.14 | $10.00 | $6.00 | $5.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1,249 CY |
| $130 |
| $145 |
| $137 |
| $139 |
| $125 |
| $136 |
| $140 |
| 12% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 2,578 CY | $45.00 | $34.00 | $54.97 | $68.00 | $53.00 | $38.00 | $62.00 | 8% |
| 659E00300 TOPSOIL | 1,568 CY | $38.00 | $47.00 | $3.81 | $25.85 | $35.00 | $25.00 | $59.50 | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,624 FT | $20.00 | $18.00 | $19.07 | $18.94 | $18.00 | $18.00 | $19.00 | 4% |
| 304E20000 AGGREGATE BASE | 859 CY | $55.00 | $43.00 | $76.01 | $70.57 | $56.00 | $58.00 | $64.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" | 22,462 SY | $1.90 | $1.90 | $1.75 | $1.91 | $1.90 | $1.75 | $2.00 | 3% |
| 832E30000 EROSION CONTROL | 40,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $40,000 | $37,000 | $40,000 | $100,000 | $137,368 | 3% |
| 632E64000 STRAIN POLE FOUNDATION | 4 EACH | $9,900 | $11,762 | $11,762 | $11,840 | $11,762 | $11,000 | $12,350 | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 2,578 CY | $15.00 | $20.00 | $20.64 | $22.56 | $22.00 | $30.00 | $34.00 | 3% |
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (239 CY | $155 | $165 | $210 | $156 | $160 | $207 | $157 | 3% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 4 EACH | $7,850 | $7,083 | $7,083 | $7,130 | $7,083 | $6,200 | $7,437 | 2% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 3 EACH | $8,200 | $7,435 | $7,435 | $7,485 | $7,435 | $7,000 | $7,807 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,000 | $30,000 | $110,861 | $64,494 | $68,000 | $70,000 | $35,472 | 2% |
| 202E23000 PAVEMENT REMOVED | 2,140 SY | $9.00 | $7.80 | $8.60 | $11.68 | $15.00 | $12.00 | $8.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $19,000 | $23,000 | $21,081 | $20,134 | $50,000 | $75,000 | $32,000 | 1% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $18,470 | $2,806 | $2,806 | $2,825 | $2,806 | $9,000 | $2,947 | 1% |
| 659E10000 SEEDING AND MULCHING | 14,124 SY | $1.25 | $0.85 | $0.85 | $1.62 | $1.00 | $1.50 | $1.00 | 1% |
| 6 FT |
| $50.00 |
| $48.00 |
| $57.85 |
| $307 |
| $25.00 |
| $20.00 |
| $66.00 |
| 202E38000 GUARDRAIL REMOVED | 275 FT | $2.00 | $4.85 | $5.00 | $5.23 | $5.00 | $2.00 | $3.50 |
| 202E75000 FENCE REMOVED | 1,024 FT | $1.65 | $2.85 | $4.50 | $2.87 | $4.50 | $1.65 | $3.00 |
| 203E20000 EMBANKMENT | 191 CY | $10.00 | $11.25 | $15.23 | $10.77 | $18.00 | $7.00 | $19.50 |
| 204E10000 SUBGRADE COMPACTION | 5,157 SY | $1.75 | $1.65 | $1.77 | $3.15 | $2.00 | $2.50 | $2.00 |
| 204E45000 PROOF ROLLING | 3 HOUR | $150 | $180 | $188 | $361 | $725 | $200 | $226 |
| 204E50000 GEOTEXTILE FABRIC | 5,157 SY | $1.00 | $1.25 | $2.98 | $1.69 | $2.50 | $2.00 | $1.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 150 FT | $26.40 | $18.90 | $23.50 | $19.03 | $23.50 | $26.40 | $23.50 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,520 | $3,550 | $2,425 | $3,574 | $2,425 | $2,520 | $2,704 |
| 607E15000 FENCE, TYPE 47 | 1,009 FT | $10.60 | $16.40 | $26.00 | $16.51 | $26.00 | $10.60 | $13.00 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $12,000 | $10,000 | $27,750 | $7,153 | $9,000 | $8,000 | $10,429 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 5 SY | $125 | $95.00 | $130 | $333 | $100 | $120 | $153 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $100 | $100 | $101 | $150 | $75.00 | $210 |
| 659E14000 REPAIR SEEDING AND MULCHING | 706 SY | $1.25 | $0.85 | $0.85 | $0.86 | $1.25 | $3.00 | $0.50 |
| 659E15000 INTER-SEEDING | 706 SY | $1.00 | $0.40 | $0.40 | $0.40 | $1.00 | $3.00 | $0.01 |
| 659E20000 COMMERCIAL FERTILIZER | 1.99 TON | $750 | $775 | $775 | $780 | $750 | $425 | $525 |
| 659E31000 LIME | 2.92 ACRE | $250 | $60.00 | $60.00 | $60.40 | $250 | $10.00 | $210 |
| 659E35000 WATER | 79 MGAL | $10.00 | $1.00 | $1.00 | $1.01 | $10.00 | $1.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 364 SY | $2.50 | $3.00 | $3.00 | $3.02 | $5.00 | $1.85 | $2.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,750 | $1,725 | $1,625 | $1,636 | $2,000 | $2,500 | $3,360 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $11,000 | $5,000 | $2,280 | $3,473 | $3,500 | $6,000 | $7,875 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $5,500 | $9,000 | $8,509 | $9,166 | $8,510 | $8,000 | $8,935 |
| 602E20000 CONCRETE MASONRY | 0.33 CY | $2,500 | $2,000 | $2,808 | $4,486 | $1,700 | $2,500 | $4,925 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 400 FT | $15.00 | $8.50 | $20.77 | $14.03 | $12.00 | $16.00 | $12.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 50 FT | $15.00 | $10.00 | $18.96 | $14.08 | $15.00 | $18.00 | $17.00 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 400 FT | $12.00 | $8.50 | $18.95 | $10.20 | $12.00 | $15.00 | $12.00 |
| 605E31100 AGGREGATE DRAINS | 365 FT | $8.00 | $15.00 | $31.92 | $13.02 | $15.00 | $12.00 | $17.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 42 FT | $20.00 | $23.00 | $36.68 | $37.00 | $35.00 | $18.00 | $22.50 |
| 611E07400 18" CONDUIT, TYPE B | 20 FT | $150 | $68.00 | $419 | $80.61 | $100 | $75.00 | $224 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $275 | $210 | $332 | $299 | $250 | $250 | $271 |
| 407E20000 NON-TRACKING TACK COAT | 2,177 GAL | $3.00 | $3.00 | $4.50 | $3.02 | $3.00 | $5.00 | $3.00 |
| 638E10401 FIRE HYDRANT ADJUSTED TO GRADE, AS PER PLAN | 1 EACH | $1,000 | $865 | $3,492 | $828 | $1,200 | $1,343 | $2,776 |
| 625E00450 CONNECTION, FUSED PULL APART | 8 EACH | $95.00 | $63.04 | $63.04 | $63.46 | $63.04 | $115 | $66.00 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 18 EACH | $95.00 | $70.95 | $70.95 | $71.43 | $70.95 | $160 | $74.50 |
| 625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN | 2 EACH | $1,100 | $673 | $673 | $678 | $673 | $360 | $707 |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 2 EACH | $1,750 | $2,555 | $2,555 | $2,572 | $2,555 | $1,550 | $2,683 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 2,034 FT | $3.40 | $2.84 | $2.84 | $2.86 | $2.84 | $2.50 | $3.00 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 537 FT | $1.20 | $1.09 | $1.09 | $1.10 | $1.09 | $1.50 | $1.00 |
| 625E25504 CONDUIT, 3", 725.051 | 150 FT | $13.00 | $11.83 | $11.83 | $11.91 | $11.83 | $13.50 | $12.50 |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 3" | 119 FT | $38.00 | $50.15 | $50.15 | $50.49 | $50.15 | $38.00 | $52.50 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 4 EACH | $400 | $369 | $369 | $372 | $369 | $425 | $388 |
| 625E29002 TRENCH, 24" DEEP | 150 FT | $14.00 | $12.22 | $12.22 | $12.30 | $12.22 | $9.00 | $13.00 |
| 625E30700 PULL BOX, 725.08, 18" | 3 EACH | $950 | $1,160 | $1,160 | $1,167 | $1,160 | $1,050 | $1,218 |
| 625E30706 PULL BOX, 725.08, 24" | 2 EACH | $1,150 | $1,273 | $1,273 | $1,281 | $1,273 | $1,225 | $1,336 |
| 625E31510 PULL BOX REMOVED | 3 EACH | $175 | $272 | $272 | $273 | $272 | $325 | $285 |
| 625E32000 GROUND ROD | 2 EACH | $265 | $182 | $182 | $184 | $182 | $260 | $192 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 150 FT | $0.30 | $0.05 | $0.05 | $0.05 | $0.05 | $2.00 | $0.05 |
| 625E75400 LIGHT POLE REMOVED | 2 EACH | $300 | $238 | $238 | $239 | $238 | $230 | $250 |
| 625E75500 LIGHT POLE FOUNDATION REMOVED | 2 EACH | $200 | $543 | $543 | $547 | $543 | $375 | $570 |
| 625E75506 LUMINAIRE REMOVED | 2 EACH | $40.00 | $55.13 | $55.13 | $55.50 | $55.13 | $40.00 | $58.00 |
| 625E75510 POWER SERVICE REMOVED | 1 EACH | $400 | $973 | $973 | $980 | $973 | $850 | $1,022 |
| 625E75800 DISCONNECT CIRCUIT | 1 EACH | $300 | $82.01 | $82.01 | $82.56 | $82.01 | $340 | $86.00 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 5 EACH | $7.00 | $7.50 | $15.00 | $15.10 | $15.00 | $8.00 | $7.50 |
| 621E00100 RPM | 316 EACH | $27.90 | $26.60 | $27.90 | $28.09 | $27.90 | $38.75 | $28.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 271 EACH | $10.00 | $15.00 | $20.55 | $20.83 | $4.60 | $10.52 | $1.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 270.6 FT | $10.50 | $10.50 | $11.00 | $10.57 | $11.00 | $12.50 | $11.50 |
| 630E80100 SIGN, FLAT SHEET | 74.8 SF | $14.50 | $14.50 | $19.25 | $14.60 | $19.25 | $17.00 | $26.50 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 8 EACH | $10.00 | $10.00 | $30.00 | $10.07 | $30.00 | $10.00 | $21.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 7 EACH | $45.00 | $45.00 | $75.00 | $45.30 | $75.00 | $65.00 | $68.50 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 12 EACH | $15.00 | $15.00 | $35.00 | $15.10 | $35.00 | $15.50 | $26.50 |
| 644E00104 EDGE LINE, 6" | 1.26 MILE | $2,800 | $4,095 | $2,800 | $2,819 | $2,800 | $2,800 | $4,300 |
| 644E00204 LANE LINE, 6" | 0.68 MILE | $2,100 | $2,180 | $2,100 | $2,114 | $2,100 | $2,100 | $2,289 |
| 644E00300 CENTER LINE | 0.77 MILE | $5,500 | $4,805 | $5,500 | $5,537 | $5,500 | $5,500 | $5,045 |
| 644E00404 CHANNELIZING LINE, 12" | 4,156 FT | $1.55 | $1.25 | $1.55 | $1.56 | $1.55 | $1.55 | $1.50 |
| 644E00500 STOP LINE | 233 FT | $5.00 | $5.65 | $5.00 | $5.03 | $5.00 | $5.00 | $6.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 387 FT | $5.00 | $5.50 | $5.00 | $5.03 | $5.00 | $5.00 | $6.00 |
| 644E00720 CHEVRON MARKING | 88 FT | $5.00 | $5.50 | $5.00 | $5.03 | $5.00 | $5.00 | $6.00 |
| 644E00900 ISLAND MARKING | 63 SF | $3.25 | $4.00 | $3.25 | $3.27 | $3.25 | $3.25 | $4.00 |
| 644E01300 LANE ARROW | 67 EACH | $71.00 | $100 | $71.00 | $71.48 | $71.00 | $71.00 | $105 |
| 644E01350 LANE REDUCTION ARROW | 2 EACH | $231 | $250 | $231 | $233 | $231 | $231 | $263 |
| 644E01510 DOTTED LINE, 6" | 947 FT | $1.50 | $1.10 | $1.50 | $1.51 | $1.50 | $1.50 | $1.00 |
| 625E25400 CONDUIT, 2", 725.04 | 5 FT | $41.00 | $25.39 | $25.39 | $25.56 | $25.39 | $40.00 | $26.50 |
| 625E25600 CONDUIT, 4", 725.04 | 5 FT | $70.00 | $27.65 | $27.65 | $27.84 | $27.65 | $80.00 | $29.00 |
| 625E29000 TRENCH | 5 FT | $30.00 | $12.22 | $12.22 | $12.30 | $12.22 | $16.00 | $13.00 |
| 625E32000 GROUND ROD | 5 EACH | $265 | $182 | $182 | $184 | $182 | $260 | $192 |
| 630E79000 SIGN HANGER ASSEMBLY, SPAN WIRE | 13 EACH | $272 | $310 | $310 | $312 | $400 | $380 | $326 |
| 630E80100 SIGN, FLAT SHEET | 98.8 SF | $30.00 | $25.00 | $25.00 | $25.17 | $25.00 | $16.75 | $26.50 |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 8 EACH | $1,100 | $837 | $837 | $843 | $837 | $700 | $880 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 5 EACH | $1,600 | $1,263 | $1,263 | $1,272 | $1,263 | $1,200 | $1,327 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 13 EACH | $60.00 | $8.82 | $8.82 | $8.88 | $8.82 | $52.00 | $9.50 |
| 632E30400 MESSENGER WIRE, 7 STRAND, 1/2" DIAMETER WITH ACCES | 550 FT | $20.00 | $8.65 | $8.65 | $8.71 | $8.65 | $18.00 | $9.00 |
| 632E30600 TETHER WIRE, WITH ACCESSORIES | 550 FT | $20.00 | $11.62 | $11.62 | $11.70 | $11.62 | $20.50 | $12.00 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 1,530 FT | $2.80 | $4.11 | $4.11 | $4.14 | $4.11 | $3.00 | $4.50 |
| 632E69900 SERVICE CABLE, 3 CONDUCTOR, NO. 4 AWG | 90 FT | $5.20 | $3.92 | $3.92 | $3.95 | $3.92 | $8.00 | $4.00 |
| 632E70001 POWER SERVICE, AS PER PLAN | 1 EACH | $2,100 | $3,076 | $3,076 | $3,097 | $3,076 | $2,400 | $3,230 |
| 632E83600 STRAIN POLE, MISC.: COMBINATION STRAIN POLE, TYPE | 2 EACH | $1,300 | $673 | $673 | $678 | $673 | $2,200 | $707 |
| 632E86501 STRAIN POLE, TYPE TC-81.11, INSTALLATION ONLY, AS | 2 EACH | $1,300 | $673 | $673 | $678 | $673 | $2,200 | $707 |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 1 EACH | $3,200 | $5,274 | $5,274 | $5,309 | $5,274 | $7,500 | $5,538 |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 1 EACH | $12,500 | $13,642 | $13,642 | $13,734 | $13,642 | $11,000 | $14,325 |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 1 EACH | $2,700 | $2,116 | $2,116 | $2,130 | $2,116 | $4,500 | $2,222 |
| 633E67201 CONTROLLER WORK PAD, AS PER PLAN | 1 EACH | $486 | $1,030 | $1,030 | $1,037 | $1,030 | $1,200 | $1,081 |
| 633E68510 COMMUNICATIONS | 1 EACH | $1,300 | $1,899 | $1,899 | $1,912 | $1,899 | $1,500 | $1,994 |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 1 EACH | $5,800 | $5,914 | $5,914 | $5,953 | $5,914 | $5,400 | $6,209 |
| 809E60000 CCTV IP-CAMERA SYSTEM, DOME-TYPE | 1 EACH | $7,700 | $6,971 | $6,971 | $7,018 | $6,971 | $7,000 | $7,320 |
| 809E69123 ATC V6.24 CONTROLLER, AS PER PLAN | 1 EACH | $4,800 | $4,661 | $4,661 | $4,692 | $4,661 | $4,300 | $4,894 |
| 815E30000 SPREAD SPECTRUM RADIO | 1 EACH | $2,600 | $2,954 | $2,954 | $2,974 | $2,954 | $3,500 | $3,102 |
| 815E30100 TRAINING FOR SPREAD SPECTRUM RADIO | 1 LS | $950 | $848 | $848 | $853 | $848 | $850 | $890 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $75.00 | $70.00 | $92.14 | $70.47 | $65.00 | $80.00 | $68.50 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,160 | $1,900 | $2,303 | $1,913 | $1,900 | $2,200 | $1,995 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE WAY | 56 EACH | $7.00 | $10.00 | $9.78 | $10.07 | $10.00 | $9.00 | $10.50 |
| 614E13350 OBJECT MARKER, ONE WAY | 56 EACH | $12.00 | $13.00 | $13.00 | $13.09 | $13.00 | $12.00 | $13.50 |
| 614E20010 WORK ZONE LANE LINE, CLASS I, 6" | 0.27 MILE | $1,100 | $4,015 | $1,100 | $1,107 | $1,100 | $1,100 | $4,216 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 0.68 MILE | $1,100 | $1,995 | $1,100 | $1,107 | $1,100 | $1,100 | $2,095 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.56 MILE | $4,500 | $4,540 | $4,500 | $4,530 | $4,500 | $4,500 | $4,767 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.77 MILE | $4,500 | $2,270 | $4,500 | $4,530 | $2,250 | $4,500 | $2,384 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 1.18 MILE | $2,250 | $4,355 | $2,250 | $2,265 | $2,250 | $2,250 | $4,573 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 1.24 MILE | $2,250 | $2,175 | $2,250 | $2,265 | $0.60 | $2,250 | $2,284 |
| 614E23010 WORK ZONE CHANNELIZING LINE, CLASS I, 12" | 2,421 FT | $0.60 | $0.75 | $0.60 | $0.60 | $0.60 | $0.60 | $1.00 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 4,147 FT | $0.60 | $0.70 | $0.60 | $0.60 | $0.75 | $0.60 | $0.50 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 306 FT | $0.75 | $0.70 | $0.75 | $0.76 | $0.75 | $0.75 | $0.50 |
| 614E24612 WORK ZONE DOTTED LINE, CLASS III, 6", 642 PAINT | 947 FT | $0.60 | $0.65 | $0.60 | $0.60 | $0.60 | $0.60 | $0.50 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 69 FT | $3.50 | $2.50 | $3.50 | $3.52 | $3.50 | $3.50 | $2.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 233 FT | $3.00 | $2.40 | $3.00 | $3.02 | $3.00 | $3.00 | $2.50 |
| 614E30000 WORK ZONE ARROW, CLASS I | 50 EACH | $30.00 | $55.00 | $30.00 | $30.20 | $30.00 | $30.00 | $58.00 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 65 EACH | $30.00 | $50.00 | $30.00 | $30.20 | $30.00 | $30.00 | $52.50 |
| 614E32800 WORK ZONE ISLAND MARKING, CLASS III, 642 PAINT | 63 SF | $1.50 | $2.25 | $1.50 | $1.51 | $1.50 | $1.50 | $2.50 |
| 616E10000 WATER | 110 MGAL | $15.00 | $50.00 | $27.37 | $11.99 | $7.50 | $70.00 | $11.50 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $12,250 | $13,140 | $1.39 | $9,722 | $20,000 | $27,000 |
| 619E16000 FIELD OFFICE, TYPE A | 4 MNTH | $1,750 | $1,000 | $1,449 | $1,348 | $1,600 | $3,500 | $683 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $12,000 | $3,881 | $12,785 | $20,000 | $20,000 | $16,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E10000 EXCAVATION | 29,619 CY | $12.25 | $363k | 21% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 1,141 CY | $170 | $194k | 11% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 1,249 CY | $130 | $162k | 9% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 2,578 CY | $45 | $116k | 7% |
| 659E00300 TOPSOIL | 1,568 CY | $38 | $60k | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,624 FT | $20 | $52k | 3% |
| 304E20000 AGGREGATE BASE | 859 CY | $55 | $47k | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" | 22,462 SY | $1.9 | $43k | 2% |
| 832E30000 EROSION CONTROL | 40,000 EACH | $1 | $40k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 2% |