LAW-SR 243-12.76
LAW County · est $1.3M
Bid dateThursday, March 11—
LAW County · est $1.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 71 more items below.
| Item | Quantity | R1D G M INC | R2George J Igel & CO INC | R3Complete General Construction Company | R4Shelly & Sands INC | R5Ruhlin Company | % of bid |
|---|---|---|---|---|---|---|---|
| 515E15070 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 4 EACH | $42,750 | $45,000 | $37,400 | $38,000 | $44,500 | 17% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 147 CY | $1,140 | $855 | $950 | $1,330 | $989 | 16% |
| 511E43512 CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT INCLUDING | 163 CY | $500 | $500 | $610 | $750 | $565 | 8% |
| Item | Quantity | R1D G M INC | R2George J Igel & CO INC | R3Complete General Construction Company | R4Shelly & Sands INC | R5Ruhlin Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $14,000 | $8,000 | $9,000 | $1,500 | $45,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 41 FT | $15.00 | $17.00 | $25.00 | $10.00 | $40.00 |
| 202E38000 GUARDRAIL REMOVED | 875 FT | $1.00 | $2.00 | $1.80 | $1.40 | $1.40 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 4 EACH | $250 | $280 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1,800 FT |
| $35.00 |
| $25.00 |
| $35.00 |
| $22.00 |
| $32.00 |
| 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $60,000 | $65,000 | $15,000 | $70,000 | $50,000 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $60,000 | $40,000 | $40,000 | $40,000 | $40,000 | 6% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 200 SY | $260 | $275 | $290 | $313 | $300 | 5% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 42,814 LB | $1.10 | $1.30 | $1.31 | $1.30 | $1.40 | 5% |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $45,000 | $45,000 | $53,000 | $32,200 | $115,000 | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 187 CY | $230 | $215 | $215 | $215 | $223 | 4% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $40,000 | $77,900 | $115,000 | $60,000 | $60,000 | 4% |
| 203E20000 EMBANKMENT | 1,753 CY | $17.50 | $20.00 | $22.00 | $22.00 | $33.83 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 118 CY | $250 | $235 | $235 | $235 | $244 | 3% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 159.83 FT | $171 | $180 | $188 | $164 | $164 | 3% |
| 103E06000 PREMIUM FOR CONTRACT PERFORMANCE BOND, PAYMENT BON | 1 LS | $22,000 | $7,000 | $11,000 | $8,000 | $6,790 | 2% |
| 421E10010 MICROSURFACING, SURFACE COURSE | 984 SY | $20.00 | $20.00 | $18.87 | $18.90 | $30.82 | 2% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $17,500 | $25,000 | $25,000 | $64,000 | $45,000 | 2% |
| 832E30000 EROSION CONTROL | 16,359 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 231 CY | $70.00 | $65.00 | $88.00 | $62.00 | $86.00 | 2% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 224 SY | $70.00 | $50.00 | $85.00 | $80.00 | $83.13 | 2% |
| $295 |
| $200 |
| $200 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $250 | $100 | $55.00 | $200 | $200 |
| 203E10000 EXCAVATION | 640 CY | $17.50 | $16.00 | $20.00 | $12.00 | $10.92 |
| 204E10000 SUBGRADE COMPACTION | 1,174 SY | $3.00 | $5.00 | $3.00 | $5.00 | $6.89 |
| 606E15050 GUARDRAIL, TYPE MGS | 737.5 FT | $19.00 | $19.50 | $18.60 | $18.00 | $17.90 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 2 EACH | $1,200 | $1,350 | $1,225 | $1,185 | $1,185 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,600 | $2,400 | $2,425 | $2,560 | $2,550 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,000 | $1,000 | $960 | $985 | $985 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,300 | $2,050 | $2,080 | $2,275 | $2,275 |
| 659E00300 TOPSOIL | 65 CY | $15.00 | $20.00 | $30.00 | $75.00 | $23.14 |
| 659E10000 SEEDING AND MULCHING | 3,764 SY | $1.50 | $3.00 | $0.84 | $0.84 | $0.83 |
| 659E14000 REPAIR SEEDING AND MULCHING | 189 SY | $0.05 | $1.00 | $0.69 | $0.70 | $0.68 |
| 659E20000 COMMERCIAL FERTILIZER | 0.51 TON | $605 | $605 | $666 | $670 | $666 |
| 659E31000 LIME | 0.78 ACRE | $75.00 | $75.00 | $154 | $154 | $153 |
| 659E35000 WATER | 20.3 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 670E00500 SLOPE EROSION PROTECTION | 577 SY | $2.50 | $2.25 | $1.67 | $1.67 | $1.66 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $4,000 | $2,000 | $1,925 | $2,100 | $1,925 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,500 | $4,100 | $17,000 | $6,000 | $3,400 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $10,000 | $8,000 | $8,500 | $8,600 | $7,500 |
| 605E31100 AGGREGATE DRAINS | 136 FT | $20.00 | $25.00 | $14.00 | $15.00 | $92.00 |
| 611E07900 18" CONDUIT, TYPE D | 36 FT | $70.00 | $80.00 | $250 | $85.00 | $54.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 88 FT | $6.00 | $2.00 | $2.50 | $4.00 | $1.60 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" MAX) | 854 SY | $9.00 | $10.00 | $8.80 | $9.00 | $6.65 |
| 304E20000 AGGREGATE BASE | 196 CY | $75.00 | $75.00 | $95.00 | $86.00 | $132 |
| 407E10000 TACK COAT | 284 GAL | $1.75 | $1.75 | $1.75 | $1.75 | $1.82 |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (12 CY | $310 | $295 | $295 | $295 | $307 |
| 621E00100 RPM | 16 EACH | $200 | $200 | $240 | $200 | $200 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 14 EACH | $1.00 | $12.00 | $20.00 | $12.00 | $12.51 |
| 626E00112 BARRIER REFLECTOR, TYPE 3 (BI-DIRECTIONAL) | 16 EACH | $10.00 | $10.00 | $7.90 | $8.00 | $7.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 14 FT | $15.00 | $15.00 | $25.00 | $25.00 | $10.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $70.00 | $75.00 | $65.00 | $165 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $15.00 | $20.00 | $15.00 | $25.00 | $20.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.21 MILE | $5,000 | $4,625 | $5,824 | $4,625 | $4,625 |
| 642E00300 CENTER LINE, TYPE 1 | 0.12 MILE | $8,000 | $7,825 | $11,000 | $7,825 | $7,825 |
| 642E00500 STOP LINE, TYPE 1 | 29 FT | $12.00 | $12.00 | $5.00 | $12.00 | $12.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $40.00 | $73.50 | $85.00 | $72.00 | $65.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 780 FT | $2.00 | $1.00 | $1.75 | $0.90 | $1.75 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,200 | $2,200 | $2,300 | $2,300 | $2,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 21 EACH | $15.00 | $15.00 | $40.00 | $8.00 | $40.00 |
| 614E13314 BARRIER REFLECTOR, TYPE 3 (BI-DIRECTIONAL) | 17 EACH | $15.00 | $22.00 | $50.00 | $8.00 | $50.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 46 EACH | $15.00 | $20.00 | $32.00 | $20.00 | $32.00 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.45 MILE | $4,000 | $3,500 | $3,500 | $3,500 | $3,500 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.04 MILE | $17,000 | $16,550 | $16,550 | $16,600 | $16,550 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 42 FT | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,000 | $10,000 | $13,000 | $7,000 | $6,222 |
| 616E10000 WATER | 1 MGAL | $1.00 | $49.00 | $80.00 | $60.00 | $37.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 430 FT | $8.00 | $25.00 | $17.00 | $7.00 | $5.00 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 350 FT | $16.00 | $22.00 | $21.00 | $60.00 | $89.00 |
| 202E23500 WEARING COURSE REMOVED | 270 SY | $8.00 | $10.00 | $30.00 | $8.30 | $42.00 |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $5,000 | $10,000 | $20,000 | $19,900 | $48,000 |
| 507E00150 STEEL PILES HP10X42, DRIVEN | 1,600 FT | $7.00 | $15.00 | $10.00 | $19.50 | $12.00 |
| 507E93300 STEEL POINTS OR SHOES | 40 EACH | $100 | $100 | $97.00 | $96.50 | $128 |
| 511E33500 SEMI-INTEGRAL DIAPHRAGM GUIDE | 2 EACH | $1,600 | $3,100 | $3,500 | $2,600 | $1,250 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 253 SY | $25.00 | $20.00 | $22.50 | $22.50 | $31.50 |
| 512E33000 TYPE 2 WATERPROOFING | 85 SY | $15.00 | $30.00 | $23.50 | $23.50 | $41.00 |
| 515E20000 INTERMEDIATE DIAPHRAGMS | 3 EACH | $2,100 | $2,500 | $5,000 | $6,200 | $3,900 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 3 SF | $30.00 | $32.00 | $28.00 | $14.00 | $24.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 108 SF | $20.00 | $11.00 | $7.00 | $11.00 | $17.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 100 FT | $37.50 | $30.00 | $42.00 | $28.00 | $28.00 |
| 516E44100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 8 EACH | $1,600 | $1,500 | $1,350 | $1,500 | $1,600 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 56 CY | $90.00 | $105 | $150 | $146 | $100 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 141 FT | $15.00 | $20.00 | $13.50 | $13.50 | $42.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 120 FT | $15.00 | $8.00 | $10.00 | $3.00 | $21.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 26 FT | $15.00 | $8.00 | $17.00 | $18.00 | $22.00 |
| 526E90011 TYPE A INSTALLATION, AS PER PLAN | 74 FT | $200 | $150 | $200 | $233 | $150 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $200 | $250 | $350 | $230 | $660 |
| 619E16000 FIELD OFFICE, TYPE A | 5 MNTH | $700 | $1,500 | $2,000 | $3,300 | $1,949 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,000 | $10,500 | $4,000 | $20,000 | $35,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E15070 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 4 EACH | $42,750 | $171k | 13% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 147 CY | $1,140 | $168k | 13% |
| 511E43512 CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT INCLUDING | 163 CY | $500 | $82k | 6% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 1,800 FT | $35 | $63k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $60,000 | $60k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $60,000 | $60k | 5% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 200 SY | $260 | $52k | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 42,814 LB | $1.1 | $47k | 4% |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $45,000 | $45k | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 187 CY | $230 | $43k | 3% |