CRA-SR 100-22.23
CRA County · est $0.9M
Bid dateThursday, May 27—
CRA County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 53 more items below.
| Item | Quantity | R1R & I Construction INC | R2Mosser Construction INC | R3Rietschlin Construction INC | R4Miller Bros Const INC | R5Bcc Ohio INC | R6Vernon Nagel INC | R7Armstrong Steel Erectors INC | R8Shelly & Sands INC | R9Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 16 EACH | $12,075 | $14,300 | $11,950 | $13,375 | $13,314 | $16,150 | $13,000 | $12,925 | $14,600 | 29% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS |
| Item | Quantity | R1R & I Construction INC | R2Mosser Construction INC | R3Rietschlin Construction INC | R4Miller Bros Const INC | R5Bcc Ohio INC | R6Vernon Nagel INC | R7Armstrong Steel Erectors INC | R8Shelly & Sands INC | R9Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $2,500 | $6,000 | $2,000 | $390 | $10,000 | $2,500 | $18,100 | $9,000 |
| 202E23000 PAVEMENT REMOVED | 609 SY | $5.00 | $12.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $85,000 |
| $67,000 |
| $70,000 |
| $91,000 |
| $73,290 |
| $75,000 |
| $82,000 |
| $108,000 |
| $90,000 |
| 13% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 95 CY | $700 | $600 | $830 | $750 | $529 | $800 | $950 | $922 | $800 | 10% |
| 509E10001 EPOXY COATED REINFORCING STEEL, AS PER PLAN | 26,782 LB | $2.00 | $1.50 | $1.50 | $1.50 | $1.55 | $1.40 | $1.25 | $1.34 | $1.35 | 8% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 244 FT | $169 | $133 | $164 | $133 | $139 | $133 | $152 | $133 | $150 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $31,400 | $20,000 | $18,000 | $20,000 | $20,987 | $20,000 | $20,000 | $20,000 | $20,000 | 5% |
| 526E10000 REINFORCED CONCRETE APPROACH SLABS (T=12") | 107 SY | $250 | $240 | $215 | $250 | $288 | $200 | $280 | $301 | $275 | 4% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 55 CF | $450 | $406 | $545 | $406 | $318 | $400 | $410 | $406 | $410 | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 125 CY | $190 | $230 | $206 | $230 | $217 | $230 | $250 | $250 | $250 | 4% |
| 442E10500 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 56 CY | $298 | $300 | $322 | $300 | $465 | $300 | $350 | $350 | $350 | 2% |
| 507E92201 PREBORED HOLES, AS PER PLAN | 40 FT | $390 | $300 | $125 | $425 | $378 | $400 | $400 | $200 | $575 | 2% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 160 CY | $85.00 | $155 | $100 | $90.00 | $105 | $90.00 | $115 | $75.00 | $80.00 | 2% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 12 CY | $900 | $1,250 | $850 | $1,150 | $1,223 | $750 | $835 | $2,040 | $2,500 | 2% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 4 EACH | $2,600 | $2,475 | $2,635 | $2,475 | $2,599 | $2,475 | $2,440 | $2,475 | $2,475 | 2% |
| 526E90010 TYPE A INSTALLATION | 66 FT | $150 | $175 | $155 | $160 | $291 | $100 | $220 | $186 | $250 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,700 | $5,300 | $10,000 | $8,000 | $9,842 | $8,500 | $8,000 | $5,400 | $10,000 | 1% |
| 511E42510 CLASS QC1 CONCRETE, PIER CAP | 12 CY | $800 | $1,225 | $1,325 | $1,700 | $2,202 | $1,300 | $1,300 | $2,610 | $2,600 | 1% |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,275 | $2,160 | $2,500 | $2,160 | $2,268 | $2,160 | $2,200 | $2,160 | $2,160 | 1% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 10 CY | $900 | $950 | $890 | $1,150 | $1,250 | $1,000 | $675 | $2,400 | $3,000 | 1% |
| 304E20000 AGGREGATE BASE | 170 CY | $50.00 | $75.00 | $71.00 | $65.00 | $69.75 | $50.00 | $80.59 | $62.00 | $80.00 | 1% |
| $9.00 |
| $9.00 |
| $10.32 |
| $12.00 |
| $9.25 |
| $11.00 |
| $15.00 |
| 202E38000 GUARDRAIL REMOVED | 370 FT | $1.50 | $4.00 | $4.00 | $2.00 | $2.10 | $3.00 | $2.50 | $2.00 | $2.00 |
| 203E10000 EXCAVATION | 172 CY | $6.00 | $15.00 | $17.00 | $14.00 | $9.75 | $20.00 | $11.00 | $22.00 | $20.00 |
| 203E20000 EMBANKMENT | 233 CY | $12.00 | $7.00 | $14.00 | $14.00 | $9.75 | $12.00 | $33.00 | $22.00 | $35.00 |
| 204E10000 SUBGRADE COMPACTION | 782 SY | $1.00 | $4.00 | $2.00 | $1.25 | $1.95 | $1.00 | $13.00 | $4.50 | $6.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 150 FT | $17.70 | $22.60 | $23.25 | $22.60 | $23.73 | $22.60 | $21.50 | $22.60 | $22.60 |
| 623E38500 MONUMENT ASSEMBLY | 2 EACH | $600 | $1,250 | $1,158 | $900 | $1,795 | $750 | $2,000 | $2,000 | $1,500 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 1 CY | $70.00 | $130 | $500 | $200 | $107 | $125 | $1,562 | $345 | $195 |
| 659E00300 TOPSOIL | 169 CY | $12.00 | $20.00 | $30.00 | $20.00 | $48.45 | $25.00 | $55.00 | $42.00 | $30.00 |
| 659E10000 SEEDING AND MULCHING | 1,521 SY | $2.00 | $2.45 | $2.50 | $1.95 | $2.57 | $2.45 | $1.75 | $1.75 | $1.95 |
| 659E14000 REPAIR SEEDING AND MULCHING | 76 SY | $0.25 | $0.65 | $1.00 | $1.95 | $0.68 | $0.65 | $0.83 | $0.84 | $1.95 |
| 659E15000 INTER-SEEDING | 76 SY | $0.25 | $0.15 | $1.00 | $1.95 | $0.16 | $0.15 | $0.83 | $0.84 | $1.95 |
| 659E20000 COMMERCIAL FERTILIZER | 0.27 TON | $500 | $580 | $800 | $610 | $609 | $580 | $607 | $608 | $610 |
| 659E31000 LIME | 0.31 ACRE | $10.00 | $25.00 | $150 | $80.00 | $26.26 | $25.00 | $156 | $156 | $80.00 |
| 659E35000 WATER | 8.4 MGAL | $1.00 | $1.00 | $10.00 | $1.00 | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 108 FT | $8.00 | $11.00 | $14.00 | $15.00 | $8.81 | $15.00 | $30.00 | $17.00 | $20.00 |
| 611E00900 6" CONDUIT, TYPE B | 50 FT | $5.00 | $25.00 | $20.00 | $10.00 | $11.40 | $12.00 | $30.00 | $18.00 | $6.00 |
| 611E01400 6" CONDUIT, TYPE E | 50 FT | $5.00 | $11.00 | $13.00 | $5.00 | $11.40 | $10.00 | $30.00 | $18.00 | $6.00 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $5.00 | $11.00 | $13.00 | $5.00 | $14.40 | $10.00 | $30.00 | $18.00 | $6.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 133 SY | $20.00 | $8.50 | $8.00 | $8.50 | $32.55 | $8.50 | $10.00 | $10.00 | $10.00 |
| 407E10000 TACK COAT | 71 GAL | $3.50 | $2.50 | $4.00 | $2.50 | $2.52 | $2.50 | $2.00 | $2.00 | $2.00 |
| 621E00100 RPM | 11 EACH | $253 | $253 | $274 | $235 | $22.43 | $235 | $253 | $267 | $253 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 11 EACH | $1.00 | $60.00 | $44.00 | $7.00 | $24.27 | $23.00 | $45.00 | $17.00 | $20.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 10 EACH | $7.50 | $7.50 | $11.00 | $7.50 | $0.79 | $7.50 | $10.00 | $7.50 | $7.50 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 12 FT | $15.00 | $16.50 | $10.00 | $16.50 | $12.60 | $12.00 | $9.30 | $12.00 | $16.50 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 33 FT | $15.00 | $19.00 | $15.00 | $19.00 | $14.70 | $14.00 | $13.85 | $14.00 | $19.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 7 EACH | $40.00 | $65.00 | $27.00 | $65.00 | $78.75 | $75.00 | $25.00 | $75.00 | $65.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3 EACH | $10.00 | $50.00 | $11.00 | $15.00 | $15.75 | $15.00 | $10.00 | $15.00 | $15.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.16 MILE | $4,227 | $4,227 | $4,600 | $4,500 | $4,725 | $4,500 | $4,227 | $4,500 | $4,227 |
| 642E00300 CENTER LINE, TYPE 1 | 0.08 MILE | $8,507 | $8,507 | $9,200 | $9,000 | $9,450 | $9,000 | $8,507 | $9,000 | $8,507 |
| 614E12420 DETOUR SIGNING | 1 LS | $6,023 | $6,023 | $6,600 | $6,500 | $6,825 | $6,500 | $8,000 | $6,600 | $9,000 |
| 202E22900 APPROACH SLAB REMOVED | 93 SY | $50.00 | $50.00 | $95.00 | $28.00 | $55.62 | $85.00 | $25.00 | $30.00 | $60.00 |
| 202E23500 WEARING COURSE REMOVED | 457 SY | $5.00 | $5.00 | $6.00 | $7.00 | $10.50 | $12.00 | $5.50 | $7.50 | $20.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $250 | $9,500 | $20,000 | $1.00 | $11,696 | $5,000 | $35,000 | $23,000 | $15,000 |
| 503E21100 UNCLASSIFIED EXCAVATION | 21 CY | $100 | $55.00 | $420 | $200 | $237 | $125 | $380 | $150 | $750 |
| 507E00101 STEEL PILES HP10X42, FURNISHED, AS PER PLAN | 80 FT | $70.00 | $65.00 | $60.00 | $55.00 | $72.23 | $30.00 | $40.00 | $98.00 | $80.00 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 700 LB | $1.00 | $1.25 | $1.50 | $2.00 | $1.55 | $1.40 | $1.07 | $1.34 | $3.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 150 SY | $30.00 | $19.00 | $26.00 | $25.00 | $24.47 | $25.00 | $23.50 | $23.50 | $23.50 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 4 FT | $100 | $225 | $810 | $200 | $345 | $175 | $300 | $750 | $100 |
| 512E33000 TYPE 2 WATERPROOFING | 35 SY | $20.00 | $14.00 | $14.00 | $28.00 | $23.33 | $18.00 | $25.50 | $25.50 | $25.50 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 219 SF | $4.00 | $6.00 | $5.00 | $6.00 | $3.08 | $10.00 | $8.00 | $6.50 | $5.00 |
| 516E41100 1/8" PREFORMED BEARING PAD | 32 EACH | $3.00 | $19.00 | $36.00 | $20.00 | $19.92 | $15.00 | $50.00 | $19.00 | $44.00 |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 64 EACH | $90.00 | $105 | $104 | $80.00 | $14.25 | $125 | $55.00 | $69.00 | $100 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 31 CY | $60.00 | $95.00 | $90.00 | $90.00 | $93.39 | $70.00 | $110 | $135 | $180 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 288 FT | $10.00 | $23.00 | $12.50 | $16.00 | $11.85 | $10.00 | $13.50 | $13.50 | $13.50 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 97 FT | $8.00 | $18.00 | $12.50 | $9.00 | $7.75 | $8.00 | $8.50 | $5.50 | $12.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 21 FT | $8.00 | $18.00 | $21.50 | $18.00 | $7.27 | $8.00 | $12.50 | $6.00 | $18.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 4 SF | $200 | $275 | $425 | $300 | $236 | $150 | $460 | $1,250 | $250 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $2,843 | $2,843 | $4,000 | $4,500 | $5,040 | $2,500 | $20,000 | $4,000 | $17,000 |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $500 | $2,200 | $1,200 | $2,500 | $1,623 | $1,000 | $1,700 | $3,200 | $2,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $3,600 | $5,000 | $4,800 | $2,235 | $6,640 | $5,000 | $12,000 | $13,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 16 EACH | $12,075 | $193k | 26% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $85,000 | $85k | 11% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 95 CY | $700 | $67k | 9% |
| 509E10001 EPOXY COATED REINFORCING STEEL, AS PER PLAN | 26,782 LB | $2 | $54k | 7% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 244 FT | $169 | $41k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $31,400 | $31k | 4% |
| 526E10000 REINFORCED CONCRETE APPROACH SLABS (T=12") | 107 SY | $250 | $27k | 4% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 55 CF | $450 | $25k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 125 CY | $190 | $24k | 3% |
| 442E10500 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 56 CY | $298 | $17k | 2% |